Program Evaluation and Review Technique
Program Evaluation and Review Technique
1. The Optimistic Time Estimate ( to ) : This is the shortest possible time in which
an activity can be completed, under ideal conditions.
2. The Pessimistic Time Estimate ( tp) : It is the maximum time that would be
required to complete the activity even if everything went wrong and abnormal
situations prevailed.
3. The Most Likely Time Estimate (tm ): It is the time which the activity will take
most frequently, if performed a number of times. This time estimate lies between
the optimistic and pessimistic time estimates.
The Expected Average Time based upon these three estimates is calculated using
the formula
te = (to + tp + 4 tm ) / 6
Z = ( t - te ) / σ
if the target date is before the estimated project duration, Z is negative and
Example Question.
Example problem
From the following data find the critical path and the probability that the project
will be completed in 41 days.
Solution
Find EST,EFT, LST, LFT and calculate total float. Zero float activities in this example
are 1-2, 2-3, 3-5, and 5-8. So this is considered as critical path for the project and
the duration of critical path (te) is 36 days ( 7+14 + 11+ 4)
Now we have to calculate the probability of project completion in 41 days.
Now find Z
Z = ( t - te ) / σ
so , σ = √ 4+ 16 +4 +1
= √25 =5
Z = ( 41 - 36) / 5
=1
Table value of Z =.3413 ( from the log book table of Standard Normal Curve,
Normal Distribution; take Z=1 (row wise ) and Column wise take 0 column always)
Only the row wise value changes depending on the Z value and column remains
the same
= .8413
Assignment Questions
1. Assuming that the expected time is normally distributed find the critical path of
the project and also the probability of project completion in 31 days.
Activity to tm tp
1-2 2 5 14
1-3 9 12 15
2-4 5 14 17
3-4 2 5 8
3-5 8 17 20
4-5 6 9 12
2. Assuming that the expected time is normally distributed find the critical path of
the project and also the probability of project completion in 11 days and also in
16 days
Activity Preceding to tm tp
activity
A - 2 3 10
B - 2 3 4
C A 1 2 3
D A 4 6 14
E B 4 5 12
F C 3 4 5
G D,E 1 1 7