Load Frequency Control in Power System: Md. Al-Amin Sarker and A K M Kamrul Hasan
Load Frequency Control in Power System: Md. Al-Amin Sarker and A K M Kamrul Hasan
SEU Journal of Science and Engineering, Vol. 10, No. 2, December 2016
Keywords: Load Frequency Control (LFC), Area Control Error (ACE), Multiple generators, Load control in
interconnected systems, Tie-line power, Automatic Generation Control (AGC).
machines are as follow; two generating stations that are Previous in this system have some problems such
connected to each other by tie line. If the change in load as disturbance, fluctuation and LFC is not sufficient
is either at A or at B and the generation of A is regulated enough but in this model most of problems are solved.
so as to have constant frequency then this kind of
regulation is called as Flat Frequency Regulation. The B. Two area power systems
other way of sharing the load is that both A and B would The Load Frequency Control (LFC) problem for
regulate their generations to maintain the frequency two area power systems is presented in (Singh et al.
constant. This is called parallel frequency regulation. 2012). Due to non-linearity in the connected load
The third possibility is that the change in the frequency and governor dead bands, the actual system response
of a particular area is taken care of by the generator of characteristic is non- linear. Therefore, a linear tie-line
that area thereby maintain the tie-line loading. This bias characteristic does not match the actual system
method is known as flat tie-line loading control. In response characteristic (Fosha C et al. 1970). This
Selective Frequency control each system in a group is mismatch causes unnecessary fuel consumption and
taken care of the load changes on its own system and increased wear and tear on generators. The LFC of two-
does not help the other systems, the group for changes area hydro–hydro-power system with Proportional
outside its own limits. In Tie-line Load-bias control, Integral Derivative (PID) controller based on maximum
all the power systems in the interconnection aid in peak resonance specification that is graphically
regulating frequency regardless of where the frequency supported by the Nichols chart is discussed in (Sudha
changes originates. KR et al. 2012). The automatic generation of three types
A. Single area power systems of interconnected two-area multi-unit all-hydropower
system, all-thermal and thermal-hydro mixed have
The Load Frequency Control (LFC) problem been investigated in (K Khshian et al. 2010). There
for single area thermal power systems is including heat thermal power system with governor dead zone is
Generation Rate Constraint (GRC) is presented in (A discussed in (Bahtti P 2010), while reheat thermal power
P Battebury et al. 1974). The LFC scheme of one-area system with GRC is presented in (T. Sou, 2011). The
thermal system with single time delay is presented LFC of two-area thermal–thermal power system with
in (Pan CT et al. 1989). The LFC with multi-source time delay is considered in (Shuda KR, 2012). The two-
(Thermal–Hydro) as single area is proposed in (Wang area interconnected thermal reheat power system with
Y et al. 1994). The LFC problem for single area hydro- Inter- line Power Flow Controller (IPFC) and Redox
power system is presented in (Jiang en L et al. 2012). Flow Batteries (RFB) units for LFC is proposed in (IA
The transient speed response of a single, isolated, Chidambaram et al 2012). The two-area power system
governed hydro-generator operating at, or near full consisting of identical reheat turbines interconnected
load is discussed in. The automatic generation control via AC link and AC/DC links are presented for LFC in
of hydro- plant is presented in (Jiang en L et al. 2012). (Ibraheem et al. 2012).
The LFC of an isolated small- hydro-power system with
reduced dump load is described in (TS, 2006). This
power plant for LFC design consists of governor G_g(s)
non-reheated turbine G_t(s), load and machine G_p(s),
and 1/R is the droop characteristics, a kind of feedback
gain to improve the damping properties of the power
system. The dynamics of these subsystems are-
There are some problems such as disturbance, The Transfer Functions of different blocks used in
accuracy shortage and LFC is not sufficient enough but power system model are given below:
in this model most of problems are solved.
Transfer function (T/F) of hydraulic Turbine is,
C. Three area power systems
The Load Frequency Control (LFC) challenges in
three area power systems are presented in (Milan, 1972).
Those three-area are interconnected (D Rerkpreedapong
et al. 2003) consists one steam plus one hydro unit,
which forms area 1, while one steam plus one hydro
unit of area 2 and area 3 with one steam. The thermal
power system interconnected as three areas is presented
in (SP, 2003). The three interconnected areas that
consist of two thermal and one hydro unit in each area
is considered in (SP, 2005). Three thermal generating
units in each area of three-area interconnected power
system are considered in (H Bevrani et al. 2009). Two
different interconnections (a) Radial type and (b) Ring
type with thermal unit in three area power systems
have been considered in (F Daneshfar et al. 2010). The Previous in this system have some problems such
LFC problem for three-area thermal power system as accuracy shortage, disturbance, fluctuation and
with communication delays is discussed in (W. Jiang LFC is not sufficient enough but in this model most of
L et al. 2012). In order to consider AGC, the area-1is problems are solved.
modeled by two generators while the other two areas
have single generator equivalents of four and three III. Simulation Results
generators in area-2 and area-3, respectively (X.Alrifai A. Uncontrolled Single-Area
MT et al. 2011). The LFC for three area power system
with time delays has been also discussed in (J Uang CF In an uncontrolled single area power system has
et al. 2006). The load frequency controller for a three governor, turbine and inertia load. By changing of value
area thermal power system is proposed in (F Daneshfar its output looks much better than others and reliable.
26
SEU Journal of Science and Engineering, Vol. 10, No. 2, December 2016
(a) (c)
(b) (d)
Figure 6: Output of two area hydro-thermal reheats power system.
(a) (b)
29
SEU Journal of Science and Engineering, Vol. 10, No. 2, December 2016
(c) (d)
Figure 8: Output of three-area hydro-thermal reheats power system.
In Fig 8, there have scopes (a), (b), (c), (d) time 0-5.5s References
change of frequency looks stable after that frequency Load Frequency Control (LFC). (2013, March 06).
smoothly increase. All of those scopes it showing same Retrieved November 01, 2016, from Electrical
but with respect to time change of frequency fluctuating installation & energy efficiency: http://engineering.
different to each other. electrical-equipment.org/power-quality/load-
frequency-control-lfc.html
IV. Conclusions
Ashmoe PH Battebury DR, B. R. (1974). Frequency
In this paper a Load frequency control (LFC) of
disturbances. Power-system model for large
interconnected multi-area power system is studied.
frequency disturbances proceedings of IEEE, 601-
The impact of LFC control method on the fluctuations
8.
caused by step load disturbance is examined. Therefore,
power utilities consider the frequency and active power Bahtti P, Ghoshal SP, Roy R. (2010). Load frequency
balance throughout their networks to sustain the inter stabilization. Load frequency stabilization by
connection. In interconnection between national/ coordinated control of Thyristor controlled phase
continental networks, providing the constant frequency shifters and super conducting magnetic energy
between areas is a serious operational problem. Hence storage for three types of interconnected two-area
fast and no delay decision-making mechanism have to power systems., 1111-24.
be installed in network control units namely the LFC.
Bevrani H, Hiyama T. (2009). On load–frequency
The load frequency control is achieved within three
regulation with time delays. On load–frequency
levels, considering many issues from maintaining
regulation with time delays: design and real-time
constant frequency and the minimization of the losses
implementation., 292-300.
for taking saturation, integrator through tie lines to the
optimal dispatch of generation between units or even Chidambaram IA, Raramasivam B. (2012). Control
areas. The simulation techniques are very useful in performance standards based load-frequency
studying and predicting the response of control systems, controller. Control performance standards based
giving the opportunity to optimize the response and so load-frequency controller considering Redox flow
the behavior of the system under study. batteries coordinate with interline power flow
controller, 292-304.
Daneshfar F, Bevrani H. (2010). LFC of a GA-based
multi-agent reins. Load frequency control: a GA-
based multi-agent reins for cement learning, 13-26.
30
SEU Journal of Science and Engineering, Vol. 10, No. 2, December 2016
Daneshfar F, Bevrani H. (2012). Multi-objective design Singh Parmer KP, Majhi S, Kothari DP. (2012). LFC of
of LFC. Multi-objective design of load frequency multi-source power generation. Load frequency
control using genetic algorithms. , 257-63. control of a realistic power system with multi-
source power generation, 426-33.
Dong L, Zhang Y. (2012). A robust decentralized LFC.
A robust decentralized load frequency controller SP, G. (2003). Multi-are frequency and tie-line power
for interconnected power systems., 410-9. flow control . Multi-are frequency and tie-line
power flow control with fuzzy logic based integral
K. G. (1988). Automatic generation control. Automatic
in scheduling., 135-41.
generation control for hydro systems, 33-9.
SP, G. (2005). GA-fuzzy based fast acting adaptive
Fosha C, Elgerd OI. (1970). Mega-watt-frequency.
active PFC. GA-fuzzy based fast acting adaptive
The mega-watt-frequency control problem: a new
active power-frequency control of interconnected
approach via optimal control , 566-70.
multiple thermal generating areas. , 209-15.
Ibraheem, Kumar P, H Nazimuddin. (2012). Sub-optimal
Sudha KR, Santhi RV. (2012). LFC of an interconnected
automatic generation control of interconnected
reheat thermal system. Load frequency control of
power system. Sub-optimal automatic generation
an interconnected reheat thermal system using
control of interconnected power system using
type-2 fuzzy system including SME Sunits. , 1383-
output vector feedback control strategy, 977-94.
92.
J Uang CF, LU CF. (2006). LFC by hybrid devolutionary
Tain-Sou, T. (2011). LFC of interconnected power
fuzzy PI controller. Load–frequency control by
system. .Load–frequency control of interconnected
hybrid devolutionary fuzzy PI controller, 196-204.
power system with governor back lash on linarites.,
Jiang en L, Yao W, Wu QH, Cheng SJ. (2012). Delay- 1542-9.
dependent stability. Delay-dependent stability for
TR, F. (1978). Governor hydro- generator. Step response
load frequency control with constant and time-
of a governed hydro- generator, 125 (11).
varying delays, 932-41.
TS, D. S. (2006). LFC of an isolated small hydro power
Khodaba Khshian A, Hooshmand R. (2010). PID
plant. Load frequency control of an isolated small
Controller design for AGC. A new PID controller
–hydro power plant with reduced dumped load,
design for automatic generation control of hydro
1912-9.
power systems., 375-82.
W. Jiang L, Yao W, Wu QH, Wen JY, Cheng SJ. (2012).
Milan, C. (1972). Linear regulator design. Linear
Delay-dependent stability for LFC. Delay-
regulator design for a load and frequency control,
dependent stability for load frequency control with
2271-85.
constant and time-varying delays., 932-41.
Pan CT, Liaw CM. (1989). Adaptive controller for
Wang Y, Zhou R, Wen C. (1994). New robust adaptive
power system. An adaptive controller for power
LFC. New robust adaptive load-frequency control
system load–frequency control IEEE Transactions
with system parametric uncertainties., 141.
on Power Systems., 122-8.
X.Alrifai MT, Hassan MF, Zribi M. (2011).
Rerkpreedapong D, Hasanovic A, Feliachi A. (2003).
Decentralized load frequency controller for a multi-
Robust load frequency control. Robust load
area. Decentralized load frequency controller for a
frequency control using genetic algorithms and
multi-area interconnected power system., 198-209.
linear matrix inequalities., 855-61.
Shuda KR, Raju YB, Sekhar AC. (2012). Robust
decentralized load frequency control of
interconnected power system. Fuzzy C-Means
clustering for robust decentralized load frequency
control of interconnected power system with
generation rate constraint, 58-66.