Assignment 1 Name: Vinay Kumar Roll No.: GCET/229/17 Semester: 8 Branch: Mechanical Subject: Production Planning & Control
Assignment 1 Name: Vinay Kumar Roll No.: GCET/229/17 Semester: 8 Branch: Mechanical Subject: Production Planning & Control
Branch: Mechanical
Subject: Production Planning
& Control
Early & Finish Time of CPM
Analysis
CPM:
The critical path method (CPM) is a project modeling
technique developed in the late 1950s by Morgan R. Walker
of DuPont and James E. Kelley, Jr. of Remington Rand.
Kelley and Walker related their memories of the development
of CPM in 1989. Kelley attributed the term "critical path" to
the developers of the Program Evaluation and Review
Technique which was developed at about the same time by
Booz Allen Hamilton and the U.S. Navy. The precursors of
what came to be known as Critical Path were developed and
put into practice by DuPont between 1940 and 1943 and
contributed to the success of the Manhattan Project. CPM is
commonly used with all forms of projects, including
construction, aerospace and defense, software development,
research projects, product development, engineering, and
plant maintenance, among others. Any project with
interdependent activities can apply this method of
mathematical analysis. Although the original CPM program
and approach is no longer used, the term is generally applied
to any approach used to analyze a project network logic
diagram.
The essential technique for using CPM is to construct a model
of the project that includes the following:
1. A list of all activities required to complete the project
(typically categorized within a work breakdown structure),
2. The time (duration) that each activity will take to complete,
3. The dependencies between the activities and,
4. Logical end points such as milestones or deliverable items.
A simple network diagram is shown below using an example:
A business wishes to build a new factory
Before it can do so it needs to:
1. Buy the land (Activity A- will take 12 weeks)
2. Draw up Plans (activity B- will take 3 weeks)
A simple network may be drawn to illustrate this scenario:
In this section you will see how this can be used to find the
critical path. This will first involve finding the earliest
possible start for each activity, by going forwards through the
network. Secondly, the latest possible start time for each
activity is found by going backwards through the network.
Activities which have equal earliest and latest start time are on
the critical path. The technique will be illustrated using the
following sample problem:
The numbers in the top half of each circle will indicate the
earliest possible starting time. So, for activities A, B and C,
the number zero is inserted.
I 29-2=27
F 27-2=25
H 32-8=24
D 25-8-17
A 7-7=0
B 7-2=5
C 27-15=12
This gives a completed network as shown below:
The vertices with equal earliest and latest starting times define
the critical path. This is clearly seen to be
AEDFIJ
Some important points:
• The EST of the first activity is always zero.
• Calculate the EST by working left to right across a
network.
• It is calculated using the following formula:
EST = EST of Previous activity + Duration of previous
activity
• When there are 2 simultaneous activities the HIGHEST
figure is used as the EST.
• The LFT of the last activity is always equal to its EST.
• The LFT of the first activity is always zero.
• Calculate the LFT by working right to left across a
network.
• It is calculated using the following formula:
LFT = LFT at end of following activity - Duration of
following activity
• When there are 2 simultaneous activities the LOWEST
figure is used as the LFT.