Table of Contents
Table of Contents
Table of Contents
1 Scrum 9
1.1 Facts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
1.1.6 Self-Organization . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
1.4 Roles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
1.5 Estimating ¨ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.1 Sprint . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
2.2.1 SP1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.2.2 SP2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.5 Retrospective . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
2.6 Others . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
3 Artifacts 24
4 Treasures 29
4.6 No Estimation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
5.8.1 Check-In . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.8.3 ESDP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.9.1 Timeline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.11 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
6 Scrum Test 49
6.4 Who should know the most about the progress toward a business objective or a release, and be
able to explain the alternatives most clearly? . . . 50
6.5 Which two (2) things does the Development Team not do during the first
Sprint? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
6.8 The Development Team should have all the skills needed to . . . . . . . . 51
6.10 When multiple teams are working together, each team should maintain a
6.11 What is the recommended size for a Development Team (within the Scrum
Team)? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
6.12 When many Development Teams are working on a single product, what
6.18 What is the primary way a Scrum Master keeps a Development Team
6.54 Who is responsible for committing to work in the Sprint Planning Meeting? 62 6.55 Which is a
better measure of progress? . . . . . . . . . . . . . . . . . . . . . 62 6.56 How many Sprints are planned during
a Sprint Planning Meeting? . . . . 62 6.57 Who must attend the Sprint Planning Meeting? (Choose
three) . . . . . . . 63 6.58 What does a Scrum Team attempt to do during its very first Sprint? . . . . 63
6.59 Which of the following are true regarding Product Backlog Items (PBIs) and tasks? (Choose four)
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63 6.60 Which of the following are explicitly defined questions in
the Daily Scrum Meeting?(Choose three) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63 6.61 Is TDD part of
Scrum? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 6.62 The Daily Scrum is one technique to encourage
team collaboration. Which physical arrangement encourage collaboration the most? . . . . . . . . . . 64
6.63 What is a good size for a Sprint task? . . . . . . . . . . . . . . . . . . . . . . 64 6.64 During the Sprint
Execution, a Scrum Team uses “information radiators” such as the taskboard or sometimes a Sprint
Burndown Chart. Who are these for? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 6.65 In an
organisation that embraces Agile values, who would be responsible for tool selection and
configuration? . . . . . . . . . . . . . . . . . . . . . . 64 6.66 When is Sprint execution completed? . . . . . . . . . . . .
. . . . . . . . . . 65 6.67 What’s the first thing we should see at the Sprint Review Meeting? . . . . 65 6.68
When were the PBIs committed to the Sprint? . . . . . . . . . . . . . . . . . 65 6.69 To whom should the
stakeholder direct his complaint about priorities? . . 65 6.70 Does Scrum have a concept of a
“partially done” PBI? . . . . . . . . . . . . 65 6.71 When should a PBI be considered
done? . . . . . . . . . . . . . . . . . . . . 66 6.72 What should a PO usually do with a partially complete PBI? . . .
. . . . . 66 6.73 What’s a good use for velocity? . . . . . . . . . . . . . . . . . . . . . . . . . 66 6.74 Henry Ford
discovered the more adapted you become to an unchanging situation, the less adaptable you are. In
an unvertain world, which is a wiser area for a ScrumMaster to focus on? . . . . . . . . . . . . . . . . . . . 66
6.75 Is restrospective safety enhanced by inviting outside spectators who weren’t working on the
team? . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66 6.76 Is a safety check by itself a complete Sprint
Retrospective? . . . . . . . . . 67 6.77 In Scrum, how often is the Sprint Retrospective Meeting
conducted? . . . 67 6.78 Groups often fool themselves with “pseudo-solutions” that don’t really
change anything. Which of the following are more effective? (Choose three) 67 6.79 Which of the
following best describes the approach for determining the iteration (timebox) length? . . . . . . . . . . . . .
. . . . . . . . . . . . . . . 67 6.80 Who is responsible for prioritizing the product backlog? . . . . . . . . . . 68 6.81
What are the advantages of maintaining consistent iteration (timebox) length throughout the
project? . . . . . . . . . . . . . . . . . . . . . . . . . 68 6.82 Why is it important to trust the team? . . . . . . . . . . . . . .
. . . . . . . 68 6.83 An effective workshop facilitator will always ... . . . . . . . . . . . . . . . . 68 6.84 If a
timebox (iteration) plan needs to be reprioritised in a hurry, who should re-prioritise? . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 69 6.85 What is the effect of having a large visible project plan on a wall? . . . . .
69 6.86 How should work be allocated to the team in an Agile project? . . . . . . . 69 6.87 What should
the developers do if the customer representative is repeatedly too busy to be
available? . . . . . . . . . . . . . . . . . . . . . . . . . . 69