Case Problem R.C. Coleman
Case Problem R.C. Coleman
Case Problem R.C. Coleman
A D I
Start C E F K Finish
B G H J
A 6 0.44
B 9 2.78
C 4 0.44
D 12 7.11
E 10 1.00
F 6 0.44
G 8 7.11
H 6 0.44
I 7 2.78
J 4 0.11
K 4 0.44
A 0 3 6 9 3
B 0 0 9 9 0 Yes
C 9 9 13 13 0 Yes
D 13 17 25 29 4
E 13 13 23 23 0 Yes
F 23 23 29 29 0 Yes
G 13 21 21 29 8
H 29 29 35 35 0 Yes I 29 32 36
39 3
J 35 35 39 39 0 Yes
K 39 39 43 43 0 Yes
Chapter 9
The expected project completion time is 43 weeks. The critical path activities are B-C-E-F-H-J-K.
The variance of the critical path is 5.67.
40−43
z ==−1.26
5.67
Area = 0.3962
Given the above calculations, we can conclude that there is about a 10% chance that the project can be
completed in 40 weeks or less. Coleman should consider crashing project activities.
2.
20%
80%
40−E T( )
=
0.84
5.67
R.C. Coleman should crash activities to reduce the expected project completion time to 38 weeks.
3. In this section, we will use expected activity times as normal times and use a linear programming
model based on expected times to make the crashing decisions.
Min 450yA + 400yB + 600yC + 300yD + 1000yE + 550yF + 750yG + 700yH + 800yI + 400yJ +
500yK
s.t.
xA + yA ≥ 6 xK ≤ 38
xB + yB ≥ 9 yA ≤ 2
xC + yC – xA ≥ 4 yB ≤ 2
xC + yC – xB ≥ 4 yC ≤ 2
xD + yD – xC ≥ 12 yD ≤ 4
xE + yE – xC ≥ 10 yE ≤ 3
xF + yF – xE ≥ 6 yF ≤ 2
xG + yG – xC ≥ 8 yG ≤ 3
xH + yH – xF ≥ 6 yH ≤ 2
xH + yH – xG ≥ 6 yI ≤ 3
xI + yI – xD ≥ 7 yJ ≤ 1
xI + yI – xF ≥ 7 yK ≤ 1
xJ + yJ – xH ≥ 4 All xi,yi ≥ 0
xK + yK – xI ≥ 4
xK + yK – xJ ≥ 4
B 2 800
F 1 550
J 1 400
K 1 500
Total 2250
Chapter 9
A 0 1 6 7 1
B 0 0 7 7 0 Yes
C 7 7 11 11 0 Yes D 11 14 23 26 3
E 11 11 21 21 0 Yes
F 21 21 26 26 0 Yes G 11 18 19
26 7
H 26 26 32 32 0 Yes I 26 28 33
35 2
J 32 32 35 35 0 Yes
K 35 35 38 38 0 Yes
The student should comment on the fact that the crashing decisions may alter the variance in the
project completion time. By defining revised optimistic, most probable, and pessimistic times for
crashed activities B, F, J, and K, a revised variance in the project completion time can be found.
Using this result, a revised probability of a 40-week completion time can be computed.