Management of DredgedExcavated Sediment

Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

Ref.

: ETWB(W) 209/32/96
Group : 5, 12

15 August 2002

Environment, Transport and Works Bureau

Technical Circular (Works) No. 34/2002

Management of Dredged/Excavated Sediment

Scope

This Circular sets out the procedure for seeking approval to dredge/excavate
sediment and the management framework for marine disposal of such sediment.

2. The Secretary for Economic Development and Labour, the Director of


Environmental Protection (DEP), the Director of Housing and the Director of Home Affairs
have agreed to the content of this Circular.

Effective Date

3. With respect to seeking approval to dredge/excavate sediment, this Circular


applies with immediate effect to all projects or portions of projects which involve the marine
disposal of dredged/excavated sediment, for which mud dredging/excavation proposals have
not already been agreed by the Marine Fill Committee (MFC).

Effect on Existing Circulars

4. This Circular should be read in conjunction with WBTC No. 12/2000 "Fill
Management".

5. WBTC No. 22/92 and 3/2000 become obsolete with immediate effect. For
dredged/excavated sediment disposal proposals previously approved in accordance with
WBTC No. 22/92 or 3/2000, re-testing of sediment in accordance with this Circular will be
required for projects if the time lapse between commencement of sampling and
commencement of construction works is more than 3 years, unless the re-testing requirement
is waived by DEP.

ETWB TCW No. 34/2002 Page 1 of 4


Introduction

6. In 1996, Contracting Parties to the London Convention 1972 agreed to adopt a


new protocol for the assessment of waste and other matter that may be considered for marine
dumping, including dredged material. The protocol sets out generic guidelines for
considering waste management options, waste characterization, dump site selection,
assessment of potential effects of disposal options, permit issue and monitoring. A new
framework based on the protocol was developed for Hong Kong and this was introduced in
WBTC No. 3/2000. It has since been reviewed further and the details are set out in this
Circular.

7. This Circular covers the approval of dredging/excavation proposals and


marine disposal of dredged/excavated sediment. It does not cover the use of
dredged/excavated sediment to form land but the carrying out of such dredging and
reclamation works must satisfy the requirements of the Environmental Impact Assessment
Ordinance. This Circular shall be brought to the attention of all consultants engaged in
Government and quasi-Government projects which involve the dredging/excavation and
marine disposal of sediment. Applications for approval of dredging/excavation proposals and
allocation of marine disposal space shall be made to the Secretary of MFC.

Rationale for Dredging

8. The allocation of sediment disposal space at sea will not be considered until
the need for removal of the sediment has first been satisfactorily demonstrated. The rationale
for sediment removal must therefore be provided to the Secretary of MFC for agreement, as
early as possible, preferably at the Environmental Impact Assessment Stage, if one is
conducted. Volumes of Category L sediment (see Appendix A) below 50,000 m3 are
exempted from this requirement.

9. Dredging of sediment will be allowed without justification in the following


cases:

(a) emergency dredging for safety reasons or averting environmental hazards;


(b) maintenance/deepening of the harbour fairways, berths, anchorages, navigation
channels or approaches; and
(c) maintenance (but not construction) of watercourses, rivers, stream courses,
drainage channels or outfalls.

10. In all other cases, project proponents shall plan their projects on the
assumption of keeping the mud in place. Time for consolidation of mud, with treatment if
necessary, and consequential programme constraints shall be allowed for in programming.
Additional time required for consolidation of mud left in place will not be accepted as
justification for mud dredging. MFC will scrutinise applications for exemption taking into
account factors including the practicality of performance specifications, completeness of risk
management strategies, and comprehensiveness of option assessments including
consideration of new technology. Where cost is considered, the estimation must include a
fair and complete estimate of all cost components, including the actual cost of mud disposal
(obtainable from MFC Secretariat) and necessary dredging and transportation, disposal
management, monitoring and other associated activities.

ETWB TCW No. 34/2002 Page 2 of 4


Classification of Sediment

11. DEP, as the Authority under the Dumping at Sea Ordinance Cap. 466 (DASO),
will classify sediments based on their contaminant levels with reference to the Chemical
Exceedance Levels (CEL) laid down in Appendix A.

Determination of Sediment Quality

12. Guidelines on the initial data assessment, the sampling and testing procedures,
the biological test criteria, and the submission requirements are set out in Appendix B. DEP
may waive the sediment sampling and testing requirements in cases of:

(a) emergency dredging for reasons of safety or averting environmental hazards;


and
(b) for small scale dredging works of maintenance nature and involving dredging
volumes of less than 5,000 m3 in situ.

Previously obtained data or known history of the sediment in the vicinity should be submitted
to DEP for consideration of the most appropriate arrangements for handling these materials.

13. Upon agreement of the rationale for sediment removal by the Secretary of
MFC, the project proponent (government department or office) or its consultant shall, in
consultation with DEP, assess whether the existing data can conclusively demonstrate that the
sediment1 is suitable for open sea disposal. If no such conclusion can be drawn, the project
proponent must submit proposals for sampling and chemical testing of the sediment to DEP
for approval. The proposals shall be copied to the Secretary of MFC, together with details of
the anticipated disposal requirements.

14. Upon completion of the sampling and chemical testing, the project proponent
shall submit a Preliminary Sediment Quality Report (PSQR) to DEP with a copy to the
Secretary of MFC. This report shall include the sampling details, the chemical testing results,
quality control records, proposed classification and delineation of sediment according to
Appendix A, and the information and/or records as specified by DEP in his approval of
sediment sampling and testing plan.

15. If Category M sediment and/or certain Category H sediment are found in the
sediment, the project proponent will be required to carry out a biological screening in
accordance with Section 3 of Appendix B, and submit a formal Sediment Quality Report
(SQR) to DEP for approval. This must be done at least 3 months prior to the dredging
contract being tendered or at least 2 months prior to the works order for maintenance
dredging being issued. In cases where biological screening is not required, subject to the
approval of DEP, the PSQR will be deemed to be the formal SQR.

16. At the time of approval of the SQR, DEP will specify the period beyond which
the reliability of the SQR data must be reviewed. This period starts on the actual date of
commencement of sampling and will be not less than three years. The project proponent
shall obtain DEP's prior agreement to the review methodology and sampling locations.
1
"The sediment" in paragraph 13 and subsequent paragraphs refers to the dredged/excavated sediment for
disposal under a project/contract as proposed by the project proponent.

ETWB TCW No. 34/2002 Page 3 of 4


Depending on the review finding, further sampling and testing to update the data of the SQR
may be required.

17. The project proponent must schedule the preparation of the SQR or its
subsequent review in such a way that the SQR will still be reliable for a reasonable period of
time after the award of the contract, to allow the contractor to apply for a dumping permit.
The project proponent should also include a particular specification clause in the contract to
draw the contractor's attention to the requirement that the SQR must still be reliable at the
time of applying for a dumping permit under the DASO. The clause should also state the
expiry date of the reliability period of the current SQR and that it is the contractor's
responsibility for carrying out, at his own expense, any work required to extend the reliability
period of the SQR should he fail to apply for a dumping permit before the expiry date.

Allocation of Sediment Disposal Site

18. MFC will determine the most appropriate open sea or confined marine
disposal site on the basis of the chemical and biological test results and formally allocate
disposal space in accordance with the flow chart in Appendix C. For projects with disposal
requirements of less than 50,000 m3 Category L sediment, the allocation of disposal space has
been delegated to DEP. The project proponent may request the Secretariat of MFC to
provisionally indicate an appropriate marine disposal site or sites after the rationale for
sediment removal has been agreed. An estimate of the volume and quality of sediment to be
dredged, supported by available ground investigation and testing data, should be provided to
the Secretary of MFC at the time of submission of the request. The contract document should
include the disposal requirements from MFC & DEP, and relevant guidelines given under
Notes (1) to (6) in Appendix C.

Application for Marine Dumping Permit

19. DEP controls dumping at sea by means of DASO permits which are issued to
contractors or other parties responsible for the disposal of dredged/excavated sediment. The
contractor who will be undertaking the works must make a formal application to DEP for a
dumping permit, and if the permit is granted, it will be the contractor's responsibility to
ensure that the permit conditions are met to DEP's satisfaction.

20. Any queries regarding this Circular or related issues should be directed to the
MFC Secretariat (Tel. no.: 2762 5397) or the Waste and Water Management Group (WMG) of
EPD (Tel. no.: 2835 1287).

( W S Chan )

Deputy Secretary for the Environment,

Transport and Works (Transport and Works) W2

ETWB TCW No. 34/2002 Page 4 of 4


Appendix A

Sediment Quality Criteria for the Classification of Sediment

Lower Chemical Upper Chemical


Contaminants Exceedance Level Exceedance Level
(LCEL) (UCEL)
Metals (mg/kg dry wt.)

Cadmium (Cd) 1.5 4


Chromium (Cr) 80 160
Copper (Cu) 65 110
Mercury (Hg) 0.5 1
Nickel (Ni)* 40 40
Lead (Pb) 75 110
Silver (Ag) 1 2
Zinc (Zn) 200 270

Metalloid (mg/kg dry wt.)

Arsenic (As) 12 42

Organic-PAHs (µg/kg dry wt.)

Low Molecular Weight PAHs 550 3160


High Molecular Weight PAHs 1700 9600

Organic-non-PAHs (µg/kg dry wt.)

Total PCBs 23 180

Organometallics (µg TBT/L in


Interstitial water)

Tributyltin* 0.15 0.15

* The contaminant level is considered to have exceeded the UCEL if it is greater than the
value shown.

The sediment is classified into 3 categories based on its contaminant levels :

Category L: Sediment with all contaminant levels not exceeding the Lower Chemical
Exceedance Level (LCEL). The material must be dredged, transported and
disposed of in a manner which minimizes the loss of contaminants either into
solution or by resuspension.
Category M: Sediment with any one or more contaminant levels exceeding the Lower
Chemical Exceedance Level (LCEL) and none exceeding the Upper Chemical
Exceedance Level (UCEL). The material must be dredged and transported
with care, and must be effectively isolated from the environment upon final
disposal unless appropriate biological tests demonstrate that the material will
not adversely affect the marine environment.
Category H: Sediment with any one or more contaminant levels exceeding the Upper
Chemical Exceedance Level (UCEL). The material must be dredged and
transported with great care, and must be effectively isolated from the
environment upon final disposal.

ETWB TCW No. 34/2002 - Appendix A Page A1 of 1


Appendix B

Guidelines for Sediment Assessment

The purpose of these guidelines is to set out the requirements for assessing, sampling,
testing and categorising the sediment. The sampling and testing procedures are critical to the
accurate evaluation of the sediment contamination, and close supervision by the project
proponent is therefore necessary. All project departments/offices, consultants, developers or
contractors (hereinafter called the "project proponent") must comply with these requirements
when notifying Director of Environmental Protection (DEP) and Marine Fill Committee
(MFC) of an intention to dredge/excavate and dispose of the sediment.

The sampling and testing procedures and the subsequent submission of a Sediment
Quality Report normally require 8 months to complete.

A list of accredited laboratories capable of carrying out biological testing stipulated


under these guidelines is kept and updated by DEP.

1. TIER 1 - Review of Existing Information for Site Contamination Assessment

The purpose of Tier I screening is to review available information to determine whether


the sediment belongs to Category L material suitable for open sea disposal. If the
project proponent considers that there is insufficient information to arrive at such a
conclusion, the project proponent may proceed directly to Tier II screening.

(a) Submission requirements

The project proponent shall submit a formal proposal to DEP and copy to the
Secretary of MFC in the Civil Engineering Department. The proposal should
contain the following information:

(i) project name;

(ii) plan showing detailed location and boundary of the dredging/excavation site;

(iii) estimated volume of dredged/excavated sediment requiring disposal;

(iv) timetable for dredging/excavation operation and the corresponding disposal


space required;

(v) p revious dredging/excavation history of the site;

(vi) previous use of the site; and

(vii) other available site specific information (e.g. sediment grain size, total
organic carbon (TOC), geotechnical data and previous testing results).

ETWB TCW No. 34/2002 - Appendix B Page B1 of 10


Appendix B

(b) Necessity to proceed to Tier II - chemical screening

DEP will examine the submission and advise whether :

(i) the information is sufficient to conclude that the sediment is suitable for
open sea disposal and the submission can be accepted as a formal Sediment
Quality Report; or

(ii) Tier II - chemical screening is required.

2. TIER II - Chemical Screening

Tier II screening is designed to categorise the sediment based on its chemical


contaminant levels, and to determine whether the sediment is suitable for open sea
disposal without further testing.

(a) Submission requirements

The project proponent shall submit for approval a test proposal to DEP and copy to
the Secretary of MFC. The proposal should contain the following information :

(i) project name;

(ii) plan showing detailed location and boundary of the dredging/excavation site;

(iii) estimated volume of dredged/excavated sediment requiring disposal;

(iv) the anticipated timetable for taking the sample, carrying out the tests, and
producing the Sediment Quality Report for chemical & biological screening;

(v) a plan showing the area to be dredged, the locations to be sampled and their
Hong Kong metric grid coordinates;

In general, the following sampling arrangement should be adopted:

Expected contamination level Recommended Sampling


Arrangement
Low 200 x 200 m grid, surface sample only
High 100 x 100 m grid, vertical profile of
samples
Very high 50 x 50 m grid, vertical profile of
(e.g. near outfalls, or nullahs) samples

When biological screening is anticipated, samples of reference sediment


should also be taken. Reference sediment required for the test may be
collected from reference sites in Hong Kong waters designated by DEP from
time to time. Alternative reference sites may be used. However, these
alternative sites should be outside the influence of previous disposal

ETWB TCW No. 34/2002 - Appendix B Page B2 of 10


Appendix B

operations but close enough to reflect similar natural environmental


characteristics (e.g. grain size and TOC) of potential disposal sites. The
project proponent should furnish information on these alternative sites to
show that their sediments are clean and are of similar natural characteristics
to that of the disposal sites.

(vi) a schedule of the types of samples to be taken (e.g. grab samples, gravity
coring, piston samples, vibrocores, etc.) with their locations and depths;

Where vertical profiles of samples are to be taken, samples should be


continuous, and the top level of the sub-samples should be the seabed, 0.9m
down, 1.9m down, 2.9m down, and then every 3m to the bottom of the
dredged layers.

The size of samples collected should be adequate for this tier of chemical
testing as well as the next tier of biological testing described in subsequent
sections.

Parameters to be tested Sample size*


Metals and metalloid 0.5 litre
Organic 0.5 litre
Biological response 6 litres

* Quantity to be confirmed by testing laboratory. The quantity of reference


sediment to be collected needs to be separately worked out for each case,
especially if biological dilution tests are anticipated.

(vii) a schedule of tests to be carried out on the samples.

Unless otherwise specified, all samples shall be tested for all the
contaminants (except Tributytin (TBT)) stated in Table 1 - Analytical
Methodology at the end of this Appendix. Analysis for other contaminants,
such as TBT, Dichloro-diphenyl-trichloroethane (DDT), other organo-
chlorine compounds, and other hazardous chemicals which arise from
specific industrial discharge or spillage, may also be required by DEP in
areas where contamination by such compounds is suspected. The composite
samples for biological testing should also be tested for moisture content,
grain size (% <63µm), TOC and ammonia (as mgN/L) and salinity in
porewater.

(b) Sampling and testing requirements

(i) Sampling practice and sample storage

All sampling bottles should be labelled with the station number, sample
length, diameter and depth, sampling date and time, together with a full
description of the sample.

ETWB TCW No. 34/2002 - Appendix B Page B3 of 10


Appendix B

The recommended types of sampling bottle and pretreatment methods are:

Parameters Sampling bottle Pretreatment


to be tested Procedure#
Metals and metalloid High density polyethylene USEPA SW-
bottles* 846+ Chapter 3
Organic Wide mouth Borosilicate USEPA SW-846
glass bottles with Teflon Chapter 4
lined lid
Biological response Wide mouth Borosilicate USEPA SW-846
glass bottles with Teflon Chapter 3 or
lined lid or high density Chapter 4 as
polyethylene bottles * appropriate.

* Heavy duty plastic bags may be used for the storage of sediment sample
for testing metals, metalloid and biological response.

# Other equivalent methods may be used subject to the approval of DEP.

+ Test methods for evaluating solid waste: physical/chemical methods,


SW-846, 3rd edition, United States Environmental Protection Agency.

The samples should be kept at 4°C in the dark and should not be frozen. All
samples should be promptly analysed. If this is impractical, the
recommended maximum holding time is:

Sample type Maximum holding time


Chemical test 2 weeks
Biological test 8 weeks

(ii) Analytical methodologies for chemical screening

The analytical method used for detecting each contaminant should be in


accordance with the methodology described in Table 1 - Analytical
Methodology at the end of this Appendix.

(c) Quality assurance/quality control (QA/QC) requirements

All tests must be conducted by laboratories accredited by Hong Kong Laboratory


Accreditation Scheme (HOKLAS) or, in case of overseas laboratories, by
equivalent national accreditation for these tests.

(d) Necessity to proceed to Tier III - biological screening

There is no need to proceed to Tier III for Category L sediment. However, the
project proponent must proceed to Tier III for further analysis of Category M and
certain Category H sediment. For the latter, Tier III screening is only required if
one or more contaminant levels exceed 10 times the Lower Chemical Exceedence
Level (LCEL).

ETWB TCW No. 34/2002 - Appendix B Page B4 of 10


Appendix B

3. TIER III - Biological Screening

The purpose of Tier III screening is to identify the most appropriate disposal option for
Category M and certain Category H sediments.

(a) Submission requirements

The project proponent shall submit for approval a test proposal to DEP and copy
to the Secretary of MFC. The proposal should contain the following information :

(i) the number of biological tests;

(ii) the arrangement for preparing the composite samples; and

(iii) the test species and test conditions.

In general, all biological tests should be conducted on composite samples.


Composite sample is prepared by mixing up to 5 samples of the same category
(M or H) which are continuous in vertical or horizontal profile.

Sediment classified as Category M shall be subjected to the following three


toxicity tests (to be considered as one set) on each composite sample:

a 10-day burrowing amphipod toxicity test ; and

a 20-day burrowing polychaete toxicity test; and

a 48-96 hour larvae (bivalve or echinoderm) toxicity test.

Sediment classified as Category H and with one or more contaminant levels


exceeding 10 times LCEL shall also be subjected to the above three toxicity tests
but in a diluted manner (dilution test). The samples shall be prepared prior to
toxicity testing as follows:

Sediment characteristics Preparation method

Category H sediment Sample to be mixed with 9 portions of


(> 10 x LCEL) reference sediment

Category M sediment or Category Additional set of sample (after dilution for


H sediment (> 10 x LCEL) Cat. H sediment) to be purged# for
suspected of ammonia ammonia removal (for amphipod test
contamination only).

# If the ammonia concentration in the overlying water of the test system is


≥ 20 mg/L, purging of sediment is required. This is performed by
replacing the overlying water at a rate of 6 volume replacements/24 h for
24 hours, and repeated once only if the ammonia level still exceeds
20 mg/L.

ETWB TCW No. 34/2002 - Appendix B Page B5 of 10


Appendix B

(b) Testing requirements

The test endpoints and decision criteria are summarized in Table 2 at the end of
this Appendix. The sediment is deemed to have failed the biological test if it fails
in any one of the three toxicity tests.

Only ecologically relevant species should be used for carrying out the biological
screening tests. The species to be used for each type of test can be selected from
the following:

Test Types Species Reference Test


Conditions*
10-day burrowing Ampelisca abdita U.S.EPA(1994)/PSEP(1995)
amphipod toxicity
test Leptocheirus plumulosus U.S.EPA(1994)

Eohaustorius estuarius U.S.EPA(1994)/PSEP(1995)


20-day burrowing Neanthes arenaceodentata PSEP(1995)
polychaete toxicity
test
48-96 hour larvae Bivalve:
(bivalve or Mytilus spp. PSEP(1995)
echinoderm)
toxicity test Crassostrea gigas PSEP(1995)

Echinoderm :
Dendraster excentricus PSEP(1995)

Strongylocentrotus spp. PSEP(1995)

*U.S.EPA (U.S. Environmental Protection Agency) 1994. Methods for assessing


the toxicity of sediment-associated contaminants with estuarine and marine
amphipods. Office of Research and Development. U.S. Environmental Protection
Agency, Cincinnati, OH. EPA/600/R94/025.

PSEP (Puget Sound Estuary Program) 1995. Recommended guidelines for


conducting laboratory bioassays on Puget Sound sediments.

(c) Quality assurance/quality control (QA/QC) requirements

All biological tests must be conducted by laboratories with appropriate


accreditation.

The biological test shall include appropriate quality assurance/quality control such as:

(i) Negative Control

(ii) Positive Control

ETWB TCW No. 34/2002 - Appendix B Page B6 of 10


Appendix B

4. Reporting Requirement after Completion of Chemical & Biological Screening

Submission requirements

Upon completion of each stage of screening (chemical and biological), the project
proponent shall submit to DEP and copy to the Secretary of MFC a report on the results
covering all tests conducted so far. The report should include the following information
where appropriate:

(i) plans showing the delineation of each of the 3 categories of dredged/excavated


material and the corresponding types of disposal required based on the chemical
and biological screening results, and

(ii) the following information :

− Name and location of the testing laboratory


− Location of samples and source of reference sediments, method of collection,
handling, preservation and storage, dates and times of sample collection and
receipt at the testing laboratory

(For chemical screening)

− Dates of analysis
− Analytical methods and detection limits
− Tabulated sample results with units, including reporting basis (e.g., wet,
dry, TOC normalized)
− QA/QC results
− Explanations for all departures from the standard protocols and
discussion of possible effects on the data

(For biological screening)

− Test species information such as the source, size, history and age of test
organisms
− Source of control seawater and control sediment used, including any
pretreatment
− Preparation procedures for test sediment sample and test organisms
− Test conditions for each test including any deviation from standard
procedures and discussion of possible effects on the data
− Water quality measurement during testing
− QA/QC results
− Effect measurements, end point results and their statistical significance

ETWB TCW No. 34/2002 - Appendix B Page B7 of 10


Appendix B

Table 1 - Analytical Methodology

Preparation Method Determination Method Reporting


Parameters
US EPA Method US EPA Method Limit
Metals
(mg/kg dry wt.)

Cadmium (Cd) 3050B 6020A or 7000A or 0.2


7131A
Chromium (Cr) 3050B 6010C or 7000A or 8
7190
Copper (Cu) 3050B 6010C or 7000A or 7
7210
Mercury (Hg) 7471A 7471A 0.05
Nickel (Ni) 3050B 6010C or 7000A or 4
7520
Lead (Pb) 3050B 6010C or 7000A or 8
7420
Silver (Ag) 3050B 6020A or 7000A or 0.1
7761
Zinc (Zn) 3050B 6010C or 7000A or 20
7950

Metalloid
(mg/kg dry wt.)

Arsenic (As) 3050B 6020A or 7000A or 1


7061A

Organic-PAHs
(µg/kg dry wt.)

Low Molecular Weight 3550B or 3540C and 8260B or 8270C 55


PAHs+ 3630C
High Molecular Weight 3550B or 3540C and 8260B or 8270C 170
PAHs++ 3630C

Organic-non-PAHs
(µg/kg dry wt.)

Total PCBs+++ 3550B or 3540C and 8082 3


3665A
Organometallics
(µg TBT/L in interstitial
water)

Tributyltin Krone et al. (1989)* - Krone et al. (1989)* - 0.015


GC/MS GC/MS
UNEP/IOC/IAEA** UNEP/IOC/IAEA**

ETWB TCW No. 34/2002 - Appendix B Page B8 of 10


Appendix B

Footnotes: (i) The reporting limits shown in this table are the most stringent limits which
will be specified by DEP. Project proponents should consult DEP on the
required limits in the preparation of proposals for sampling and chemical
testing of the sediment.

(ii) Other equivalent methods may be used subject to the approval of DEP.

+ Low molecular weight PAHs include acenaphthene, acenaphthylene,


anthracene, fluorene, naphthalene, and phenanthrene
++ High molecular weight PAHs include benzo[a]anthracene, benzo[a]pyrene,
chrysene, dibenzo[a,h]anthracene, fluoranthene, pyrene,
benzo[b]fluoranthene, benzo[k]fluoranthene, indeno[1,2,3-c,d]pyrene and
benzo[g,h,i]perylene
+++ The reporting limit is for individual PCB congeners. Total PCBs include 2,4'
diCB, 2,2',5 triCB, 2,4,4' triCB, 2,2',3,5' tetraCB, 2,2',5,5' tetraCB, 2,3',4,4'
tetraCB, 3,3',4,4' tetraCB, 2,2',4,5,5' pentaCB, 2,3,3',4,4' pentaCB, 2,3',4,4',5
pentaCB, 3,3',4,4',5 pentaCB, 2,2',3,3',4,4' hexaCB, 2,2',3,4,4',5' hexaCB,
2,2',4,4',5,5' hexaCB, 3,3',4,4',5,5' hexaCB, 2,2',3,3',4,4',5 heptaCB,
2,2',3,4,4',5,5' heptaCB, 2,2',3,4',5,5',6 heptaCB (ref: the "summation"
column of Table 9.3 of Evaluation of Dredged Material Proposed for
Discharge in Waters of the U.S. - Testing Manual (The Inland Testing
Manual) published by USEPA).
* Krone et al. (1989), A method for analysis of butyltin species and
measurement of butyltins in sediment and English Sole livers from Puget
Sound, Marine Environmental Research 27 (1989) 1-18. Interstitial water to
be obtained by centrifuging the sediment and collecting the overlying water.
** UNEP/ICO/IAEA refers to IAEA's Marine Environment Laboratory
reference methods. These methods are available free of charge from
UNEP/Water or Marine Environmental Studies Laboratory at IAEA's
Marine Environment Laboratory. Interstitial water to be obtained by
centrifuging the sediment and collecting the overlying water.

ETWB TCW No. 34/2002 - Appendix B Page B9 of 10


Appendix B

Table 2 - Test Endpoints and Decision Criteria for Tier III Biological Screening

Toxicity test Endpoints Failure criteria


measured

10-day amphipod Survival Mean survival in test sediment is


1
significantly different (p≤0.05) from mean
survival in reference sediment and mean
survival in test sediment < 80% of mean
survival in reference sediment.
2
20-day polychaete Dry Weight Mean dry weight in test sediment is
1
worm significantly different (p≤0.05) from mean
dry weight in reference sediment and mean
dry weight in test sediment < 90% of mean
dry weight in reference sediment.
3
48-96 hour larvae Normality Survival Mean normality survival in test sediment is
1
(bivalve or significantly different (p≤0.05) from mean
echinoderm) normality survival in reference sediment and
mean normality survival in test sediment <
80% of mean normality survival in reference
sediment.

1
Statistically significant differences should be determined using appropriate two-sample
comparisons (e.g., t-tests) at a probability of p≤0.05.
2
Dry weight means total dry weight after deducting dead and missing worms.
3
Normality survival integrates the normality and survival end points, and measures
survival of only the normal larvae relative to the starting number.

ETWB TCW No. 34/2002 - Appendix B Page B10 of 10


Appendix C

Management Framework for Dredged/Excavated Sediment

Sediment to be Disposed of

Data Indicates
Little or No
Contamination
Tier I
Desk Top Study
of Available Data

Insufficient Data or Data Indicates Potential


Contamination

Tier II
Chemical Screening

Category L Material Category M Category H


≤Lower Chemical Material Material
Exceedance Level >Lower & ≤Upper Chemical >Upper Chemical
Exceedance Level Exceedance Level

>10 x Lower Chemical


Exceedance Level
No

Yes

Tier III Tier III


Biological Screening
Biological Screening
(Dilution Test)

Pass Fail Pass Fail

Type 1 - Type 1 - Type 2 - Type 3 -


Open Sea Open Sea Disposal Confined Marine Special Treatment/
Disposal (Dedicated Sites) Disposal Disposal
(see Note 1) (see Note 1 & 2) (see Note 3) (see Note 3 & 4)

Notes
(1) Most open sea disposal sites are multi-user facilities and as a consequence their
management involves a flexibility to accommodate varying and unpredictable
circumstances. Contract documents should include provisions to allow the
same degree of flexibility should it be necessary to divert from one disposal site
to another during the construction period of a contract.

(2) Dedicated Sites will be monitored to confirm that there is no adverse impact.

ETWB TCW No 34/2002 - Appendix C Page C1 of 2


Appendix C

(3) For sediment requiring Type 2 or Type 3 disposal, contract documents should
state the allocation conditions of MFC and DEP. At present, East Sha Chau
mud pits are designated for confined marine disposal.

(4) If any sediment suitable for Type 3 disposal (Category H sediment failing the
biological dilution test) is identified, it is the responsibility of the project
proponent, in consultation with DEP, to identify and agree with him/her, the
most appropriate treatment and/or disposal arrangement. Such a proposal is
likely to be very site and project specific and therefore cannot be prescribed.
This will not preclude treatment of this sediment to render it suitable for
confined marine disposal.

(5) The allocation of disposal space may carry a requirement for the project
proponent to arrange for chemical analysis of the sediment sampled from 5% of
the vessels en-route to the disposal site. For Category M and certain Category
H sediment, the chemical tests will be augmented by biological tests. Vessel
sampling will normally entail mixing five samples to form a composite sample
from the vessel and undertaking laboratory tests on this composite sample. All
marine disposal sites will be monitored under the general direction of the Civil
Engineering Department. However, exceptionally large allocations might
require some additional disposal site monitoring. These will be stipulated at the
time of allocation.

(6) Trailer suction hopper dredgers disposing of sediment at East Sha Chau must
use a down-a-pipe disposal method, the design of which must be approved in
advance by DCE. The dredging contractor must provide equipment for such
disposal.

ETWB TCW No 34/2002 - Appendix C Page C2 of 2

You might also like