How To Calculate Earned Value in Project Management
How To Calculate Earned Value in Project Management
Project Management
Earned value (EV) is a way to measure and monitor the level of work completed
on a project against the plan. Simply put, it’s a quick way to tell if you’re behind
schedule or over budget on your project. You can calculate the EV of a project by
multiplying the percentage complete by the total project budget. For example,
let’s say you’re 60% done, and your project budget is $100,000 — your earned
value is then $60,000. However, to properly use earned value, a few additional
calculations must be considered. The largest benefits of earned value result
from completing both cost and schedule variance analyses.
4. Cost Performance Index (CPI): As with SPI, CPI allows you to simplify the
answer for better analysis. The CPI calculation is: CPI = EV/AC. When CPI is
over 1.00, you’re under budget, and when it’s under 1.00, you’re
overspending. In the scenario above, CPI = 60,000/ 70,000 = 0.86,
indicating an overspend. CPI can be used to forecast your project’s
completion. For example, you can divide your total project budget by your
current CPI to get the expected total cost at completion. The formula is
Estimate at Completion (EAC) = Budget/ CPI. In the above example, this
would be $100,000/ 0.86 = $116,279.07. Meaning, that at this point in the
project, based on current trends, you will likely end up overspending your
budget by $16,279.07. Knowing this early allows you the time to either
find ways to cut costs or secure more funding.