Concrete Mix Design With GGBS M25

The document provides a mix design for concrete with a target mean strength of 31.6 N/mm2 using ground granulated blast furnace slag (GGBS) as a partial cement replacement. The mix design calculations involve determining the water-cement ratio, cementitious content, proportions of coarse and fine aggregates, and final mix quantities. The resulting mix design for 1 cubic meter of concrete consists of 191 kg of cement, 128 kg of GGBS, 168 liters of water, 1132 kg of coarse aggregate, 853 kg of fine aggregate, and 3.19 kg of superplasticizer.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3K views13 pages

Concrete Mix Design With GGBS M25

The document provides a mix design for concrete with a target mean strength of 31.6 N/mm2 using ground granulated blast furnace slag (GGBS) as a partial cement replacement. The mix design calculations involve determining the water-cement ratio, cementitious content, proportions of coarse and fine aggregates, and final mix quantities. The resulting mix design for 1 cubic meter of concrete consists of 191 kg of cement, 128 kg of GGBS, 168 liters of water, 1132 kg of coarse aggregate, 853 kg of fine aggregate, and 3.19 kg of superplasticizer.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 13

Aequs SEZ Pvt Ltd

Concrete Mix Design With GGBS

Input Data's Results for 1 cum of concrete


Grade Of concrete M 25 N/mm2 1 Target mean Strength 31.6 N/mm2
2 Cement 191.00 kg/m3
Sl No Material Grade Specific gravity 3 GGBS 128.00 kg/m3
1 Cement OPC 43 3.15 4 water 168.00 liters/m3
4 Superplasticizers 3.19 kg/m3
Percentage of
Material addition Specific gravity 5 coarse Aggregte 1132.00 kg/m3
2 GGBS 40% 3 6 Fine aggregate 853.00 kg/m3

Material Size in mm Specific gravity water absorption


3 Coarse Aggregate 20 2.74 0.50% Water cement Ratio 0.483

Material Zone Specific gravity water absorption


4 Fine aggregate 2 2.65 1.00%

Material Admixture Specific gravity Pozzolana material


4 Chemical Admixture Superplasticizer 1.145 Nil

Sump 110 mm
Method of placing Pumping
Step 1
Target mean strength
fck' = fck + 1.65 *S
or
fck' = fck + X

fck = 25

S= 4
X= 5.5
fck'= 31.6 N/mm2
0r
fck'= 30.5 N/mm2

Step 2
Approximate air content
Size of aggregate 20 mm

Entraped air from table 3 1%


which is 0.01

Step 3
water cement ratio
fck'= 32
Cement Grade 43
W/c = 0.4833333333

Step3 (selection of water content)


Now water content as per table 04 of IS 10262
Aggegate size 20
water content= 186 kg/m3

Above water content is for slump 50mm, for desired slump the water content will be
WCx = WC50 + ((x-50)/25)*(3/100)*WC50
x= 110 mm
WC50 186 kg/m3
WCx= 199.392 kg/m3
step 4 (Reduction of water content for Chemical adixture)
For water reducing admixture reduce water content by 5 to 10%
for superplasticizer reduce water content by 20-30%
Therefore reduce 23% water content for 1% superplasticizer

WCx= 153.532
WCx= 154.000 kg/m3

Step 5: Calculation of cementitious content


Cementitious content = water content / Wc ratio > Minimum cementitious content table 5 IS 456:2000

Cementitious content = 318.62


Say 319.00 kg/m3

GGBS = 40% of total cementious material


GGBS= 127.6 kg/m3
say 128 kg/m3

Now cement content = Cementitious content - GGBS


Cement = 191.00 kg/m3

Step 6 : Proportion of volume of coarse aggregate & fine Aggregate (clause 5.5 IS 10262)
Zone of FA = 2
Nominal Size of CA = 20 mm

Volume of CA = from Table 5 IS 10262 0.62


But above table is for water-cementitious material ratio 0.5, therefore we have to change the volume to t

Therefore Vca@w = [email protected] + ((0.5-w)/0.05)* 0.01


Now Vca@w 0.6233333333
Now according to clause 5.5.2 reduce the volume of CA by 10% for pumping
Now Vca@w 0.561
& Vfa@w = 1-Vca@w
Therefore Vfa@w= 0.439

Step 7: Mix Calculations

Quantities Mass Sp Gravity Volume


Volumne of entrapped air (a) 0.01
Volume of water (b) 154.000 1.000 wc/(sp gv *1000)
Volume of Cement © 191.000 3.150 cement/(sp gv *1000)
Volumne of GGBC (d) 128.000 3.000 GGBS/(sp gv *1000)
Volume of Chemical Admix (e) (1%
of cementitious material) 3.190 1.145 Ch. adm/(sp gv *1000)
Total volume of aggregate 1-(a+b+c+d+e) =
Toatl volumne % of Aggregate Sp gravity
Mass of Coarse Aggregate 0.740 0.561 2.740
Mass of fine aggregate 0.740 0.439 2.650

Step 8 Mix proportion trail 1 for 1cum


Sl no Material Qty unit
1 Cement 191.00 kg/m3
2 water 154.00 kg/m3
3 water/cemtitious ratio 0.48
4 GGBS 128.00 kg/m3
5 Superplasticizer 3.19 kg/m3
6 Coarse Aggregate (SSD) 1137.35 kg/m3
7 Fine aggregate (SSD) 860.78 kg/m3

Step 9 Adjustment in Mix Design


1) Fine aggregates (Dry) = Mass of fine aggregate in SSD condition /(1+(%water absorption/100)-(%m
water abortion= 1.00%
Moisture content 0
Fine aggregates (Dry) = 852.25452954
say 853 kg/m3

2) Extra water required for the fine aggregate simulate a SSD condition
A = (Mass of fine aggregate in SSD condition) -(Mass of fine aggregate in dry condition)
A= 7.78 kg/m3

1) Coarse aggregates (Dry) = Mass of corse aggregate in SSD condition /(1+(%water absorption/100)-(%
water abortion= 0.50%
Moisture content 0
Coarse aggregates (Dry) = 1131.6904734 kg/m3
say 1132 kg/m3

2) Extra water required for the coarse aggregate simulate a SSD condition
B = (Mass of coarse aggregate in SSD condition) -(Mass of coarse aggregate in dry condition)
A= 5.35 kg/m3

Total water required = water requirement + A+B


Total water required = 167.13 kg/m3
say 168 kg/m3

Step 10 Mix proportion after adjustment for 1cum


Sl no Material Qty unit
1 Cement 191.00 kg/m3
2 water 168.00 kg/m3
3 water/cemtitious ratio 0.48
4 GGBS 128.00 kg/m3
5 Superplasticizer 3.19 kg/m3
6 Coarse Aggregate (SSD) 1132.00 kg/m3
7 Fine aggregate (SSD) 853.00 kg/m3
Table 02 IS 10262

Sl no Grade Of concrete

1 M
2 M
3 M
4 M
5 M

6 M

7 M
8 M
9 M
10 M
11 M
12 M

13 M
14 M
15 M

Table 01 Value of X IS 1
Sl no Grade Of concrete
1 M
2 M
3 M
4 M
5 M
6 M
7 M
8 M
9 M
10 M
11 M
p the water content will be 12 M65 & above

Free
Compressive
Sl no streingth 33
N/mm2
1 60.00
2 59.00
3 58.00
4 57.00
table 5 IS 456:2000 5 56.00
6 55.00
7 54.00
8 53.00
9 52.00
10 51.00
11 50.00
12 49.00
13 48.00
14 47.00
15 46.00
16 45.00
10262) 17 44.00
18 43.00
19 42.00
20 41.00
21 40.00
e to change the volume to the desired W/c raio 22 39.00
23 38.00
24 37.00
25 36.00
26 35.00
CA by 10% for pumping 27 34.00
28 33.00
29 32.00
30 31.00
31 30.00
32 29.00
33 28.00
Volume 34 27.00
35 26.00
0.154 m3 36 25.00
0.061 m3 37 24.00
0.043 m3 38 23.00

39 22.00
0.003
0.740 40 21.00
Mass og aggregate 41 20.00
1137.349 kg/m3 42 19.00
860.777 kg/m3 43 18.00
44 17.00
45 16.00
46 15.00
%water absorption/100)-(%moisture content/100))

dry condition)

%water absorption/100)-(%moisture content/100))

ate in dry condition)


Table 02 IS 10262 Table 3 10262 : 2019 Approximate Air content
Assumed
standard Nominal Maximum size of
Grade Of concrete Sl no
deviation aggregate mm
N/mm2
10 3.5 1 10
15 3.5 2 20
20 4 3 40
25 4
30 5

Table 4 10262 : 2019 water content per cubic meter of concrete for
35 5 Nominal Maximum size of aggregate
Nominal Maximum size of
40 5 Sl No Aggregate mm
45 5 1 10
50 5 2 20
55 5 3 40
60 5
65 6 Table 5 IS 10262 : 2019
Nominal Maximum Size
70 6 SL No of aggregate mm
75 6
80 6 1 10
2 20

3 40
Table 01 Value of X IS 10262
Grade Of concrete Value of x
10 5
15 5
20 5.5
25 5.5
30 6.5
35 6.5
40 6.5
45 6.5
50 6.5
55 6.5
60 6.5
65 8

Free water ratio graph value according to IS 10262


Compressive Compressive
Free water
streingth 43 Free water ratio streingth 53 Free water ratio
ratio
N/mm2 N/mm2
0.25 66.00 0.25 74.00 0.25
0.26 65.00 0.26 73.00 0.26
0.26 64.00 0.26 72.00 0.26
0.27 63.00 0.27 71.00 0.27
0.27 62.00 0.27 70.00 0.28
0.28 61.00 0.28 69.00 0.28
0.28 60.00 0.28 68.00 0.29
0.29 59.00 0.29 67.00 0.29
0.29 58.00 0.29 66.00 0.30
0.30 57.00 0.30 65.00 0.31
0.30 56.00 0.31 64.00 0.31
0.31 55.00 0.31 63.00 0.32
0.31 54.00 0.32 62.00 0.32
0.32 53.00 0.33 61.00 0.33
0.33 52.00 0.33 60.00 0.33
0.34 51.00 0.34 59.00 0.34
0.34 50.00 0.34 58.00 0.34
0.35 49.00 0.35 57.00 0.35
0.36 48.00 0.36 56.00 0.36
0.37 47.00 0.36 55.00 0.36
0.38 46.00 0.37 54.00 0.37
0.38 45.00 0.38 53.00 0.38
0.39 44.00 0.39 52.00 0.38
0.40 43.00 0.39 51.00 0.39
0.41 42.00 0.40 50.00 0.39
0.41 41.00 0.41 49.00 0.40
0.42 40.00 0.42 48.00 0.41
0.43 39.00 0.43 47.00 0.42
0.44 38.00 0.43 46.00 0.43
0.44 37.00 0.44 45.00 0.43
0.45 36.00 0.45 44.00 0.44
0.46 35.00 0.46 43.00 0.45
0.47 34.00 0.47 42.00 0.46
0.48 33.00 0.48 41.00 0.47
0.49 32.00 0.48 40.00 0.48
0.50 31.00 0.49 39.00 0.49
0.52 30.00 0.50 38.00 0.50
0.53 29.00 0.51 37.00 0.51

0.54 28.00 0.53 36.00 0.52

0.55 27.00 0.54 35.00 0.53


0.57 26.00 0.55 34.00 0.54
0.58 25.00 0.56 33.00 0.55
0.60 24.00 0.58 32.00 0.56
0.62 23.00 0.59 31.00 0.58
0.63 22.00 0.60 30.00 0.59
0.65 21.00 0.62 29.00 0.60
20.00 0.63 28.00 0.62
19.00 0.65 27.00 0.63
26.00 0.65
19 Approximate Air content

Entrapped Air, as percentage


of volumne of concrete

1.5
1
0.8

ontent per cubic meter of concrete for


imum size of aggregate

Water content kg
208
186
165

Table 5 IS 10262 : 2019


Volume of coarse aggregate per unit volumne of total
aggregate for different zones of fine aggregate
Zone IV Zone III Zone II Zone I
0.54 0.52 0.5 0.48
0.66 0.64 0.62 0.6

0.73 0.72 0.71 0.69