Risk Manangement Sample Uap
Risk Manangement Sample Uap
Risk Manangement Sample Uap
Risk Management
An Overview of ISO 31000
Seminar Workshop
SAMPLE
RISK MANAGEMENT PLAN
Case Assumption:
With the context below, a group of government employees was called to form a Risk
Management Team in order to formulate a Risk Management Plan for a new project –
Corn Processing and Trading Center.
Name of Selected Project: Corn Post Harvest Processing and Trading Center
Location: Sagay City, Negros Occidental
Purpose
This document describes how Risk Management will be structured and performed
on this project. The risk management plan includes methodology, roles and
responsibilities, budgeting, timing, risk categories, definitions of risk probability and impact,
probability and impact matrix, reporting formats, and tracking.
This Project Risk Management Plan will be utilized as primary reference and
guideline.
Note: The originator of this document would like to consider other informations However; informations
collected are only within the time, scope and resources acquired in a one –day. Some informations are
assumed, but without compromising the principles, concepts and procedures of Risk Management in the
context of ISO 31000.
A. The Context
The project is the subject of evaluation on Risk Management is the Corn Post
Harvest Processing and Trading Center of Sagay City .This project was created for the
benefit of the of the local corn producers in order to assist them in the marketing of their
products as well as those wholesalers, not only in the surrounding areas but in the regional
or national as well.
Being the first plant in the entire region, this plant has a corn plantation source of six
hectares. This has four (4) drying bins with a capacity of 50,000 kg capacity each, with a
total of 200,000 kg of corn with Moisture Content (MC) requirement of 30%. Corn is
processed from 30% up to 14% moisture content within 36 hours.
There could be a lot of risks innate in the project as part of the project operations.
The risk aspects of this shall be given attention. The following are:
A. Technical Aspect
1. Site Development
2. Building Design
2.1. Building space Requirements
2.2. Building Layout
B.Legal Aspects
1. Environmental
2. Risk Assessment
1. Site Security
2. Site Development and
3. Safety Measures
1. Site Security
2. Site Development
3. Safety Essentials
1. Site Security
A.1.No permanent perimeter fencing around the structure
Temporary fencing may cause interested parties, and other unwanted
elements to intrude the area. Eventually, when unfavorable elements
get inside the premises, uncertain disturbances during plant operation
may be created and would affect the production target objective.
Intruding elements may be curious enough to observe the operations
and be exposed in restricted areas that may cause accidents.
Persons of unknown identity may enter the area and properties may
be exposed to theft when opportunity favors.
2. Site Development
3. Safety Essentials
Photo 1 Photo 2
Low rail barriers at discharge pit Open access of person to Dry Bins
Risk Assessment Table
Corn Post Parvest Processing Plant and Trading Center
002 Difficulty
Site Discomfort of
Development of movements Truck Likely Clearing of
due to Delivery Serious Grounds
Unpaved On rainy Is
And Days/ Insufficient High(16)
Undeveloped
Soil Hazard- 4 4 2
Grounds ous
Breathing
On dry
Days
Slippage
Of Uses
On wet
Days
003 Safety
Essentials Accidental Injury Very Height of
Fall Likely Railing is Extreme(2
Due to Low Major deficient
0) 4 5 1
Railing
Rate Scale:
5.Risk Treatment
1.Site Security
Fence shall provide a gate as a means of control .Access for delivery trucks
and of pedestrian shall be provided of functional and reasonable width .
2.Site Development
Concrete pavements can also help the mixing of soil dusts and the corn.
3.Safety Essentials
6.Risk Monitoring
1.Site Security
Once permanent fence is constructed ,regular inspection of the state of
existing walls especially on the outside face of the walls that are not visible from
the inside. A person shall be in charge to update the present condition of the wall.
2.Site Development
3.Safety Essentials
This railing shall always be in dry condition to avoid rusting of any part
especially joints of structural elements. Use stainless steel materials to lessen much
maintenance on painting and rust proofing.
1.Identification process
Every department shall present the functions and activities of the job to
perform. This could be done in writing down logical sequencing of activities or steps in the
accomplishment of objectives. Once these steps and activities are formulated, a list of all
the risks and their likelihood of occurrence shall be identified. List of risks could be taken
from the following sources:
Once these risks are identified, they shall be evaluated in order to qualify
their impact to the objectives or the operations of the organization. Evaluation or
assessment shall be determined according to the degree of impact to the objectives of the
project. Degree of impact is determined as High, Medium, and High. Finally Risks shall be
rank according to the degree of impact level .Each level shall be given corresponding
value . High Impact shall be equated with the highest priority equivalent to rank 1 and
followed by a lower impact as 2, and so forth.
The following are the approaches or methods in order to maintain the Risk
plan.
2.as need arises, risk plan shall be reviewed according to the log updates
submitted by the person in charge.
3.A Risk register shall be created as a checklist and review document for
whatever updates and precautions in line with the risks identified.
Individual Responsibility
1.Identify continuous potential risks every plant operation.
4.Generate report on the above responsibilities and submit these reports during
the regular meeting for documentation and update of the risk register.
5.Submit Incident , Injuries, Near Miss reports. (See Appendix 2)
1.Identify continuous potential risk within the Buildings and grounds of the
Buildings and processing plant.
Grounds
2. Implement Risk prevention strategy according to the Risk Management plan
Administrator and develop means of other mitigations applicable.
4.Generate report on the above responsibilities and submit these reports during
the regular meeting for documentation and update of the risk register.
Security 1.Identify continuous potential risks in all security aspects of the whole activities
Officer of the plant for 24 hours round the clock.
4.Generate report on the above responsibilities and submit these reports during
the regular meeting for documentation and update of the risk register.
Site Discomfort
Development of movements
002 due to 4 4 Loss of time, 3 Months
undeveloped/ Expenditures
unpaved Of
grounds Resources
Safety Accidental
003 Essentials Fall due to 3 Months
Low Railings Physical
Of Discharge Injuries,
Pit ,
4 5
Uninformed of
safety
due to
Insufficient
safety
instructions
Note: 1.Probability of Occurrence is the percentage of likelihood that the risk will occur
2.Impact level is a score of 1 to 5. 1 is the least impact and 5 is the highest.
3.Prove time frame in fiscal years and quarters if known.
Construction
Priority 3 001 Site Security Security Call for
(Encroachment) Officer of Perimeter Assistance
Fence
E. Mitigation Cost
Risk Priority No : 1
Risk No : 003
Risk Name : Safety Essentials
Risk Treatment: : 1.Raising the height of railings
2: Safety signs, Safety instructions labels, etc
Cost
**LIN ITEM DESCRIPTION Duration (Pesos) Remarks
Total
1.0 Internal staff Buildings and Grounds 1 year *109,200.0 Annual
Administrator 0 Salary
2.0 Development Monitor sheets, computers, As 35,000.00 Package
Tools Seminars on Safety required
3.0 Materials and Visual aids, safety labels, Annual 30,000.00 Package
Supply Poster prints
Co
4.0 Construction of Materials and Labor -existent 5,000.00 Lump
Pavement with plant sum
operation
s
5.0 Contingency 10,000.00
Tota For
l 179,200.00 Approval
Cost
*Assumption :
Risk Priority No : 2
Risk No : 002
Risk Name : Site Development
Risk Treatment: : Provision of Concrete Pavement
Cost
**LIN ITEM DESCRIPTION Duration (Pesos) Remarks
Total
1.0 Internal staff Buildings and Grounds 1 year *109,200.0 Annual
Administrator 0 Salary
2.0 Development Monitor sheets, computers, As 35,000.00 Package
Tools Seminars on Safety required
3.0 Materials and Visual aids, safety labels, Annual 30,000.00 Package
Supply Poster prints
Co
4.0 Construction of Materials and Labor -existent Lump
Pavement with plant 100,000.00 sum
operation
s
5.0 Contingency 10,000.00
Tota For
l 274,000.00 Approval
Cost
*Assumption :
Risk Priority No : 3
Risk No : 001
Risk Name : Site Security
Risk Treatment: : Provision of Permanent Fence
Cost
**Ll ITEM DESCRIPTION Duration (Pesos) Remarks
N
Total
1.0 Internal staff Security Officer 1 year *109,200.00 Annual
Salary
2.0 Development As
Tools required 35,000.00 Package
3.0 Materials and Security Paraphernalias
Supply 1 Year 10,000.00 Package
4.0 Co
Provision Materials and Labor -existent
Of Permanent with plant 150,000.00 Lump
Fence operation sum
s
5.0 Contingency 15,000.00
Total For
Cost 319,200.00 Approval
*Assumption :
Appendix 1
Risk Assessment Matrix
Likelihood, Impact, Risk Level
Appendix 2
Proposed Incident Report Form
Adapted from Risk Management Manual
Association of Bay Area Government
_____________________ ________________________
_____________________ ________________________
Department:__________________________________________________________________
Location:_____________________________________________________________________
Injured Party:
Name : ________________________________________________________
Address: _______________________________________________________
Phone:_________________________________________________________
Description of Incident:
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
Appendix 2A
Accident Investigation Format
Adapted from Risk Management Manual
Association of Bay Area Government
Fact Finding
1.Emphasis is placed on gathering facts, not placing blame or determining the cause
Of the accident.
5.Interview the injured party and witnesses as soon as possible after an accident.
Record pre-accident conditions, the accidents sequence of events, and post- accident conditions.
7.Ask who, what, when, where, why, and how during interviews.
8.Re-interview the injured party and witnesses to resolve any conflicting accounts.
Interviews
1.Get preliminary statements from injured party and witnesses as soon as possible.
2.Explain the purpose of the investigation (accident prevention) and put the witness
At ease.
3.Let the witness speak freely and take notes without distracting the witness.
4.Record the exact words used by the witness to describe each observation.
6.Identify the witness completely (name, occupation, years of experience, phone number).
7.Supply each witness with a copy of his or her statement (signed statements are desirable).
Investigation Reporting
1.Provide complete, thorough information about the accident.
2.Describe the accident. Document the sequence of events and identify the extent of
3.Identify hazardous conditions and/or unsafe work practices for each event of the
accident.
4.Identify the root cause of each hazardous condition or unsafe work practice.
5.Provide short-term and long-term corrective actions that prevent or eliminate the
identified hazardous conditions, unsafe work practices, and root causes.
6.Describe the corrective actions recommended, the persons accountable for each
corrective action, and the approximate timeframe for completion of each corrective action.
Corrective Actions
4.Estimate the cost to implement each immediate and long-term corrective action.
Appendix 2b
Supervisor's Report Format Sample
Adapted from Risk Management Manual
Association of Bay Area Government
Employee Status:
Full Time :_____________Part Time ____________Seasonal__________ Volunteer ____________
What type of Illness/Injury was sustained by the employee and what body part was involved?
(cut to left index finger, low back strain, burn to right leg, etc.)
Names of Witnesses:______________________________________________________
1. Describe fully and as with as much detail as possible, where the incident occurred (facility,
department, office, workstation, if outdoors). Was equipment or property damaged? Use
additional sheets of paper if needed.
2. Describe fully and as with as much detail as possible, what events led up to the incident
(condition of the work area, weather conditions). Use additional sheets of paper if needed.
3. Was equipment being used at the time of the incident? Yes____ No___
If YES, was equipment in proper working order? Yes _____ No ____
If NO, what problems were occurring? Use additional sheets of paper if needed.
4. Describe as fully and as with as much detail as possible what the employee was doing at
the time the incident occurred. (What specifically caused the injury; i.e. cut, burn, struck
by object.) Use additional sheets of paper if needed.
5. Does this job require use of personal protective equipment (PPE)? Is there a relationship
between the severity of the injury and using PPE?
6. Have similar incidents occurred? Yes No If YES, list dates and locations.
9. What long-term actions are needed? By Whom? Target date for completion?
10. What post-loss actions should be taken (Early Return-to-Work program, other actions to
mitigate overall severity of loss?)