Project Operation
Project Operation
Project Operation
PROJECT MANAGEMENT
(CENG 6101)
BY
TADESSE AYALEW
LECTURER , EIABC, AAU
160
140
120
Activity Days Cost ($) Cost/day
Cost ($)
A 2 200 100 100
B 5 500 100 80
C 2 200 100 60
D 7 500 71.4 40
E 1 100 100 20
F 2 100 50
0
Day Activity Cost of day Total cost 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 A 100 100 Day
2 A 100 200
Cumulative Expenses
3 B 100 300
4 B 100 400 1800
1000
10 D,E 171.4 1214
800
11 D 71.4 1286
12 D 71.4 1357 600
14 D 71.4 1500
200
15 F 50 1550
16 F 50 1600 0
Month Budget Cost in Month (Birr) Cumulative Cost at end of month (Birr
January 500,000 500,000
February 1,000,000 1,500,000
March 2,000,000 3,500,000
April 2,000,000 5,500,000
May 2,500,000 8,000,000
June 3,000,000 11,000,000
July 4,000,000 15,000,000
August 4,000,000 19,000,000
September 3,000,000 22,000,000
October 2,500,000 24,500,000
November 2,000,000 26,500,000
December 1,500,000 28,000,000
January 1,000,000 29,000,000
February 500,000 29,500,000
March 500,000 30,000,000
30000000
20000000
Measure of Project Time
Slippage at Each Stage
15000000
5000000
0
0 Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar
Months of Project
Chart
28
40000000
Chart 3: Comparison of Budget & Actual Costs Based on Actual Timing
35000000
Actual Cost of Work
Completed (Table 3)
30000000
25000000
Cumulative Costs: Birr
20000000
10000000
5000000
0
0 Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar
Months of Project
All together
29
Current Date
Maintenance
Construction Period
Period
6.1.3 Quality management
Quality planning
Quality control
6.1.4 Safety management
Although they are not part of the project manager’s ‘big three’
objectives of schedule, budget and quality, the monitoring and
control of safety and environmental impact are major issues in all
construction operations.
The most important resources that project managers have to plan and
manage on day-to-day basis are people, machines, materials, and
money.
On the other hand, if these resources are severely limited, then the
result most likely will be a delay in the project completion time.
No Description 1 2 3 4 5 6 7 8 9 10 11 12 13
3 3
1 Upstream clearing
3 3
2
45 Downstream clearing
5 5 5
Excavation Abut 1
3
5 5 5
4 Excavation Abut 2
2
5 Blinding Abut 1
2
6 Blinding Abut 2
2 2 5 1
7 Foundation Abut 1
2c 2c 2c
2sf 2sf
1 2 5 1
8 Foundation Abut 2
2c 2c 2c 2c
2sf 2sf
2 2
9 Backfill Abut 1
2 2
10 Backfill Abut 2
Labourers 11 11 5 7 7 7 7 2 4 7 1 2 2 73
Carpenters 2 2 2 2 2 2 2 14
Steelfixers 2 2 2 2 8
Formwork 1 1 1 1 1 1 1 7
Backactor 1 1 1 1 1 1 1 1 1 1 10
Pump 1 1 1 2 2 2 2 2 2 2 1 1 1 20
6.2.2. Materials Management
Order costs are usually only a small portion of total costs for
material management in construction projects, although ordering
may require substantial time.
C) Holding Costs
The holding costs or carrying costs are primarily the result of capital costs,
handling, storage, obsolescence, shrinkage and deterioration.
Capital cost results from the opportunity cost or financial expense of capital tied
up in inventory.
Handling and storage represent the movement and protection charges incurred
for materials.
Storage costs also include the disruption caused to other project activities by large
inventories of materials that get in the way. Obsolescence is the risk that an item
will lose value because of changes in specifications.
Shrinkage is the decrease in inventory over time due to theft or loss. Deterioration
reflects a change in material quality due to age or environmental degradation.
D) Unavailability Cost
Variation requests and approval. Requests from the owner for proposals for
changes in the work and their approval;