Critical Path Method E-Book
Critical Path Method E-Book
PDF generated using the open source mwlib toolkit. See http://code.pediapress.com/ for more information.
PDF generated at: Thu, 07 Aug 2014 13:18:19 UTC
Contents
Articles
Critical path method 1
Float (project management) 4
Critical path drag 6
Program evaluation and review technique (PERT) 7
References
Article Sources and Contributors 15
Image Sources, Licenses and Contributors 16
Article Licenses
License 17
Critical path method 1
History
The critical path method (CPM) is a project modeling technique
developed in the late 1950s by Morgan R. Walker of DuPont and
James E. Kelley, Jr. of Remington Rand. Kelley and Walker related PERT chart for a project with five milestones (10
their memories of the development of CPM in 1989. Kelley attributed through 50) and six activities (A through F). The
the term "critical path" to the developers of the Program Evaluation project has two critical paths: activities B and C,
or A, D, and F – giving a minimum project time
and Review Technique which was developed at about the same time by
of 7 months with fast tracking. Activity E is
Booz Allen Hamilton and the U.S. Navy. The precursors of what came sub-critical, and has a float of 1 month.
to be known as Critical Path were developed and put into practice by
DuPont between 1940 and 1943 and contributed to the success of the
Manhattan Project.
CPM is commonly used with all forms of projects, including construction, aerospace and defense, software
development, research projects, product development, engineering, and plant maintenance, among others. Any
project with interdependent activities can apply this method of mathematical analysis. Although the original CPM
program and approach is no longer used, the term is generally applied to any approach used to analyze a project
network logic diagram.
Basic technique
The essential technique for using CPM [1] is to construct a model of the project that includes the following:
1. A list of all activities required to complete the project (typically categorized within a work breakdown structure),
2. The time (duration) that each activity will take to complete,
3. The dependencies between the activities and,
4. Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the
project, and the earliest and latest that each activity can start and finish without making the project longer. This
process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be
delayed without making the project longer). In project management, a critical path is the sequence of project network
activities which add up to the longest overall duration. This determines the shortest time possible to complete the
project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is
no float on the critical path). A project can have several, parallel, near critical paths. An additional parallel path
through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path.
CPM analysis tools allow a user to select a logical end point in a project and quickly identify its longest series of
dependent activities (its longest path). These tools can display the critical path (and near critical path activities if
desired) as a cascading waterfall that flows from the project's start (or current status date) to the selected logical end
point.
Although the activity-on-arrow diagram ("PERT Chart") is still used in a few places, it has generally been
superseded by the activity-on-node diagram, where each activity is shown as a box or node and the arrows represent
the logical relationships going from predecessor to successor as shown here in the "Activity-on-node diagram".
Critical path method 2
Crash duration
"Crash duration" is a term referring to the shortest possible time for which an activity can be scheduled. It is
achieved by shifting more resources towards the completion of that activity, resulting in decreased time spent and
often a reduced quality of work, as the premium is set on speed. Crash duration is typically modeled as a linear
relationship between cost and activity duration, however in many cases a convex function or a step function is more
applicable.
Expansion
Originally, the critical path method considered only logical dependencies between terminal elements. Since then, it
has been expanded to allow for the inclusion of resources related to each activity, through processes called
activity-based resource assignments and resource leveling. A resource-leveled schedule may include delays due to
resource bottlenecks (i.e., unavailability of a resource at the required time), and may cause a previously shorter path
to become the longest or most "resource critical" path. A related concept is called the critical chain, which attempts
to protect activity and project durations from unforeseen delays due to resource constraints.
Since project schedules change on a regular basis, CPM allows continuous monitoring of the schedule, which allows
the project manager to track the critical activities, and alerts the project manager to the possibility that non-critical
activities may be delayed beyond their total float, thus creating a new critical path and delaying project completion.
In addition, the method can easily incorporate the concepts of stochastic predictions, using the program evaluation
and review technique (PERT) and event chain methodology.
Currently, there are several software solutions available in industry that use the CPM method of scheduling, see list
of project management software. The method currently used by most project management software is based on a
manual calculation approach developed by Fondahl of Stanford University.
Critical path method 3
Flexibility
A schedule generated using critical path techniques often is not realised precisely, as estimations are used to
calculate times: if one mistake is made, the results of the analysis may change. This could cause an upset in the
implementation of a project if the estimates are blindly believed, and if changes are not addressed promptly.
However, the structure of critical path analysis is such that the variance from the original schedule caused by any
change can be measured, and its impact either ameliorated or adjusted for. Indeed, an important element of project
postmortem analysis is the As Built Critical Path (ABCP), which analyzes the specific causes and impacts of
changes between the planned schedule and eventual schedule as actually implemented.
References
[1] Samuel L. Baker, Ph.D. "Critical Path Method (CPM)" (http:/ / hspm. sph. sc. edu/ COURSES/ J716/ CPM/ CPM. html) University of South
Carolina, Health Services Policy and Management Courses
Further reading
• Project Management Institute (2013). A Guide To The Project Management Body Of Knowledge (5th ed.). Project
Management Institute. ISBN 978-1-935589-67-9.
• Klastorin, Ted (2003). Project Management: Tools and Trade-offs (3rd ed.). Wiley. ISBN 978-0-471-41384-4.
• Heerkens, Gary (2001). Project Management (The Briefcase Book Series). McGraw–Hill. ISBN 0-07-137952-5.
• Harold Kerzner (2003). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (8th
ed.). ISBN 0-471-22577-0.
• Lewis, James (2002). Fundamentals of Project Management (2nd ed.). American Management Association.
ISBN 0-8144-7132-3.
• Milosevic, Dragan Z. (2003). Project Management ToolBox: Tools and Techniques for the Practicing Project
Manager. Wiley. ISBN 978-0-471-20822-8.
• O'Brien, James J.; Plotnick, Fredric L. (2010). CPM in Construction Management, Seventh Edition. McGraw Hill.
ISBN 978-0-07-163664-3.
• Woolf, Murray B. (2012). CPM Mechanics: The Critical Path Method of Modeling Project Execution Strategy.
ICS-Publications. ISBN 978-0-9854091-0-4.
• Woolf, Murray B. (2007). Faster Construction Projects with CPM Scheduling. McGraw Hill.
ISBN 978-0-07-148660-6.
• Trauner, Manginelli, Lowe, Nagata, Furniss (2009). Construction Delays, 2nd Ed.: Understanding Them Clearly,
Analyzing Them Correctly (http://www.amazon.com/Construction-Delays-Second-Edition-Understanding/dp/
1856176770). Burlington, MA: Elsevier. p. 266. ISBN 978-1-85617-677-4.
• Malakooti, B (2013). Operations and Production Systems with Multiple Objectives. John Wiley & Sons.
ISBN 978-1-118-58537-5.
Float (project management) 4
Example
Consider the process of replacing a broken pane of glass in the window of your home. There are various component
activities involved in the project as a whole; obtaining the glass and putty, installing the new glass, choosing the
paint, obtaining a tin once it has set, wiping the new glass free of finger smears etc.
Some of these activities can run concurrently e.g. obtaining the glass, obtaining the putty, choosing the paint etc.,
while others are consecutive e.g. the paint cannot be bought until it has been chosen, the new window cannot be
painted until the window is installed and the new putty has set. Delaying the acquisition of the glass is likely to delay
the entire project - this activity will be on the critical path and have no float, of any sort, attached to it and hence it is
a 'critical activity'. A relatively short delay in the purchase of the paint may not automatically hold up the entire
project as there is still some waiting time for the new putty to dry before it can be painted anyway - there will be
some 'free float' attached to the activity of purchasing the paint and hence it is not a critical activity. However a delay
in choosing the paint in turn inevitably delays buying the paint which, although it may not subsequently mean any
delay to the entire project, does mean that choosing the paint has no 'free float' attached to it - despite having no free
float of its own the choosing of the paint is involved with a path through the network which does have 'total float'.
Float (project management) 5
References
• AACE International (August 2007). "Cost Engineering Terminology, AACE International Recommended
Practice No. 10S-90" (http://www.aacei.org/technical/rps/10s-90.pdf) (PDF). www.aacei.org.
Critical path drag 6
Sources
[1] William Duncan and Stephen Devaux "Scheduling Is a Drag" (http:/ / www. projectsatwork. com/ content/ articles/ 246653. cfm)
Projects@Work on-line magazine
[2] Stephen A. Devaux "The Drag Efficient: The Missing Quantification of Time on the Critical Path" (http:/ / www. dau. mil/ pubscats/ ATL
Docs/ Jan_Feb_2012/ Devaux. pdf) Defense AT&L magazine of the Defense Acquisition University.
Further reading
• Wideman, R. Max (2004). Total Project Control: A book review (http://www.maxwideman.com/papers/
totalcontrol/totalcontrol.pdf)
• Borfitz, Deb (2009). [www.ecliniqua.com/2009/08/07/prochain.html "ProChain Solutions: Diagnosing the Drag
in Clinical Development" eCliniqua Magazine]
• Mosaic Projects. Basic CPM Calculations (http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.
pdf)
History PERT network chart for a seven-month project with five milestones (10 through 50)
and six activities (A through F).
Program evaluation and review
technique
The Navy's Special Projects Office, charged with developing the Polaris-Submarine weapon system and the
Fleet Ballistic Missile capability, has developed a statistical technique for measuring and forecasting progress
in research and development programs. This program evaluation and review technique (code-named PERT) is
applied as a decision-making tool designed to save time in achieving end-objectives, and is of particular
interest to those engaged in research and development programs for which time is a critical factor.
The new technique takes recognition of three factors that influence successful achievement of research and
development program objectives: time, resources, and technical performance specifications. PERT employs
time as the variable that reflects planned resource-applications and performance specifications. With units of
time as a common denominator, PERT quantifies knowledge about the uncertainties involved in
developmental programs requiring effort at the edge of, or beyond, current knowledge of the subject – effort
accomplishments (events) essential to achieve end-objectives; the inter-dependence of those events; and
estimates of time and range of time necessary to complete each activity between two successive events. Such
time expectations include estimates of "most likely time", "optimistic time", and "pessimistic time" for each
activity. The technique is a management control tool that sizes up the outlook for meeting objectives on time;
highlights danger signals requiring management decisions; reveals and defines both methodicalness and slack
in the flow plan or the network of sequential activities that must be performed to meet objectives; compares
current expectations with scheduled completion dates and computes the probability for meeting scheduled
dates; and simulates the effects of options for decision – before decision.
The concept of PERT was developed by an operations research team staffed with representatives from the
Operations Research Department of Booz, Allen and Hamilton; the Evaluation Office of the Lockheed Missile
Systems Division; and the Program Evaluation Branch, Special Projects Office, of the Department of the
Navy.
— Willard Fazar (Head, Program Evaluation Branch, Special Projects Office, U. S. Navy), The American
Statistician, April 1959.[1]
Overview
PERT is a method to analyze the involved tasks in completing a given project, especially the time needed to
complete each task, and to identify the minimum time needed to complete the total project.
PERT was developed primarily to simplify the planning and scheduling of large and complex projects. It was
developed for the U.S. Navy Special Projects Office in 1957 to support the U.S. Navy's Polaris nuclear submarine
project.[2] It was able to incorporate uncertainty by making it possible to schedule a project while not knowing
precisely the details and durations of all the activities. It is more of an event-oriented technique rather than start- and
completion-oriented, and is used more in projects where time is the major factor rather than cost. It is applied to very
large-scale, one-time, complex, non-routine infrastructure and Research and Development projects. An example of
this was for the 1968 Winter Olympics in Grenoble which applied PERT from 1965 until the opening of the 1968
Games.[3]
This project model was the first of its kind, a revival for scientific management, founded by Frederick Taylor
(Taylorism) and later refined by Henry Ford (Fordism). DuPont's critical path method was invented at roughly the
same time as PERT.
Terminology
• PERT event: a point that marks the start or completion of one or more activities. It consumes no time and uses no
resources. When it marks the completion of one or more activities, it is not "reached" (does not occur) until all of
the activities leading to that event have been completed.
• predecessor event: an event that immediately precedes some other event without any other events intervening. An
event can have multiple predecessor events and can be the predecessor of multiple events.
• successor event: an event that immediately follows some other event without any other intervening events. An
event can have multiple successor events and can be the successor of multiple events.
• PERT activity: the actual performance of a task which consumes time and requires resources (such as labor,
materials, space, machinery). It can be understood as representing the time, effort, and resources required to move
from one event to another. A PERT activity cannot be performed until the predecessor event has occurred.
• PERT sub-activity: a PERT activity can be further decomposed into a set of sub-activities. For example, activity
A1 can be decomposed into A1.1, A1.2 and A1.3 for example. Sub-activities have all the properties of activities,
in particular a sub-activity has predecessor or successor events just like an activity. A sub-activity can be
decomposed again into finer-grained sub-activities.
Program evaluation and review technique (PERT) 9
• optimistic time (O): the minimum possible time required to accomplish a task, assuming everything proceeds
better than is normally expected
• pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong
(but excluding major catastrophes).
• most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as
normal.
• expected time (TE): the best estimate of the time required to accomplish a task, accounting for the fact that things
don't always proceed as normal (the implication being that the expected time is the average time the task would
require if the task were repeated on a number of occasions over an extended period of time).
TE = (O + 4M + P) ÷ 6
• float or slack is a measure of the excess time and resources available to complete a task. It is the amount of time
that a project task can be delayed without causing a delay in any subsequent tasks (free float) or the whole project
(total float). Positive slack would indicate ahead of schedule; negative slack would indicate behind schedule; and
zero slack would indicate on schedule.
• critical path: the longest possible continuous pathway taken from the initial event to the terminal event. It
determines the total calendar time required for the project; and, therefore, any time delays along the critical path
will delay the reaching of the terminal event by at least the same amount.
• critical activity: An activity that has total float equal to zero. An activity with zero float is not necessarily on the
critical path since its path may not be the longest.
• Lead [4] time: the time by which a predecessor event must be completed in order to allow sufficient time for the
activities that must elapse before a specific PERT event reaches completion.
• lag time: the earliest time by which a successor event can follow a specific PERT event.
• fast tracking: performing more critical activities in parallel
• crashing critical path: Shortening duration of critical activities
Implementation
The first step to scheduling the project is to determine the tasks that the project requires and the order in which they
must be completed. The order may be easy to record for some tasks (e.g. When building a house, the land must be
graded before the foundation can be laid) while difficult for others (There are two areas that need to be graded, but
there are only enough bulldozers to do one). Additionally, the time estimates usually reflect the normal, non-rushed
time. Many times, the time required to execute the task can be reduced for an additional cost or a reduction in the
quality.
In the following example there are seven tasks, labeled A through G. Some tasks can be done concurrently (A and B)
while others cannot be done until their predecessor task is complete (C cannot begin until A is complete).
Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time
estimate (M), and the pessimistic time estimate (P). The expected time (TE) is computed using the formula (O + 4M
+ P) ÷ 6.
Program evaluation and review technique (PERT) 10
A — 2 4 6 4.00
B — 3 5 9 5.33
C A 4 5 7 5.17
D A 4 6 10 6.33
E B, C 4 5 7 5.17
F D 3 4 8 4.50
G E 3 5 8 5.17
Once this step is complete, one can draw a Gantt chart or a network diagram.
A network diagram can be created by hand or by using diagram software. There are two types of network diagrams,
activity on arrow (AOA) and activity on node (AON). Activity on node diagrams are generally easier to create and
interpret. To create an AON diagram, it is recommended (but not required) to start with a node named start. This
"activity" has a duration of zero (0). Then you draw each activity that does not have a predecessor activity (a and b
in this example) and connect them with an arrow from start to each node. Next, since both c and d list a as a
predecessor activity, their nodes are drawn with arrows coming from a. Activity e is listed with b and c as
predecessor activities, so node e is drawn with arrows coming from both b and c, signifying that e cannot begin until
both b and c have been completed. Activity f has d as a predecessor activity, so an arrow is drawn connecting the
activities. Likewise, an arrow is drawn from e to g. Since there are no activities that come after f or g, it is
recommended (but again not required) to connect them to a node labeled finish.
By itself, the network diagram pictured above does not give much
more information than a Gantt chart; however, it can be expanded to
display more information. The most common information shown is:
1. The activity name
2. The normal duration time
3. The early start time (ES)
4. The early finish time (EF)
5. The late start time (LS)
6. The late finish time (LF)
A node like this one (from Microsoft Visio) can
7. The slack
be used to display the activity name, duration,
In order to determine this information it is assumed that the activities ES, EF, LS, LF, and slack.
and normal duration times are given. The first step is to determine the
ES and EF. The ES is defined as the maximum EF of all predecessor activities, unless the activity in question is the
first activity, for which the ES is zero (0). The EF is the ES plus the task duration (EF = ES + duration).
• The ES for start is zero since it is the first activity. Since the duration is zero, the EF is also zero. This EF is used
as the ES for a and b.
• The ES for a is zero. The duration (4 work days) is added to the ES to get an EF of four. This EF is used as the ES
for c and d.
• The ES for b is zero. The duration (5.33 work days) is added to the ES to get an EF of 5.33.
• The ES for c is four. The duration (5.17 work days) is added to the ES to get an EF of 9.17.
• The ES for d is four. The duration (6.33 work days) is added to the ES to get an EF of 10.33. This EF is used as
the ES for f.
• The ES for e is the greatest EF of its predecessor activities (b and c). Since b has an EF of 5.33 and c has an EF of
9.17, the ES of e is 9.17. The duration (5.17 work days) is added to the ES to get an EF of 14.34. This EF is used
as the ES for g.
• The ES for f is 10.33. The duration (4.5 work days) is added to the ES to get an EF of 14.83.
• The ES for g is 14.34. The duration (5.17 work days) is added to the ES to get an EF of 19.51.
• The ES for finish is the greatest EF of its predecessor activities (f and g). Since f has an EF of 14.83 and g has an
EF of 19.51, the ES of finish is 19.51. Finish is a milestone (and therefore has a duration of zero), so the EF is
also 19.51.
Barring any unforeseen events, the project should take 19.51 work days to complete. The next step is to determine
the late start (LS) and late finish (LF) of each activity. This will eventually show if there are activities that have
slack. The LF is defined as the minimum LS of all successor activities, unless the activity is the last activity, for
which the LF equals the EF. The LS is the LF minus the task duration (LS = LF − duration).
• The LF for finish is equal to the EF (19.51 work days) since it is the last activity in the project. Since the duration
is zero, the LS is also 19.51 work days. This will be used as the LF for f and g.
• The LF for g is 19.51 work days. The duration (5.17 work days) is subtracted from the LF to get an LS of 14.34
work days. This will be used as the LF for e.
• The LF for f is 19.51 work days. The duration (4.5 work days) is subtracted from the LF to get an LS of 15.01
work days. This will be used as the LF for d.
• The LF for e is 14.34 work days. The duration (5.17 work days) is subtracted from the LF to get an LS of 9.17
work days. This will be used as the LF for b and c.
• The LF for d is 15.01 work days. The duration (6.33 work days) is subtracted from the LF to get an LS of 8.68
work days.
• The LF for c is 9.17 work days. The duration (5.17 work days) is subtracted from the LF to get an LS of 4 work
days.
Program evaluation and review technique (PERT) 12
• The LF for b is 9.17 work days. The duration (5.33 work days) is subtracted from the LF to get an LS of 3.84
work days.
• The LF for a is the minimum LS of its successor activities. Since c has an LS of 4 work days and d has an LS of
8.68 work days, the LF for a is 4 work days. The duration (4 work days) is subtracted from the LF to get an LS of
0 work days.
• The LF for start is the minimum LS of its successor activities. Since a has an LS of 0 work days and b has an LS
of 3.84 work days, the LS is 0 work days.
The next step is to determine the critical path and if any activities have slack. The critical path is the path that takes
the longest to complete. To determine the path times, add the task durations for all available paths. Activities that
have slack can be delayed without changing the overall time of the project. Slack is computed in one of two ways,
slack = LF − EF or slack = LS − ES. Activities that are on the critical path have a slack of zero (0).
• The duration of path adf is 14.83 work days.
• The duration of path aceg is 19.51 work days.
• The duration of path beg is 15.67 work days.
The critical path is aceg and the critical time is 19.51 work days. It is important to note that there can be more than
one critical path (in a project more complex than this example) or that the critical path can change. For example, let's
say that activities d and f take their pessimistic (b) times to complete instead of their expected (TE) times. The critical
path is now adf and the critical time is 22 work days. On the other hand, if activity c can be reduced to one work day,
the path time for aceg is reduced to 15.34 work days, which is slightly less than the time of the new critical path, beg
(15.67 work days).
Assuming these scenarios do not happen, the slack for each activity can now be determined.
• Start and finish are milestones and by definition have no duration, therefore they can have no slack (0 work days).
• The activities on the critical path by definition have a slack of zero; however, it is always a good idea to check the
math anyway when drawing by hand.
• LFa – EFa = 4 − 4 = 0
• LFc – EFc = 9.17 − 9.17 = 0
• LFe – EFe = 14.34 − 14.34 = 0
• LFg – EFg = 19.51 − 19.51 = 0
• Activity b has an LF of 9.17 and an EF of 5.33, so the slack is 3.84 work days.
• Activity d has an LF of 15.01 and an EF of 10.33, so the slack is 4.68 work days.
• Activity f has an LF of 19.51 and an EF of 14.83, so the slack is 4.68 work days.
Therefore, activity b can be delayed almost 4 work days without delaying the project. Likewise, activity d or activity
f can be delayed 4.68 work days without delaying the project (alternatively, d and f can be delayed 2.34 work days
each).
Program evaluation and review technique (PERT) 13
Advantages
• PERT chart explicitly defines and
makes visible dependencies
(precedence relationships) between
the work breakdown structure
(commonly WBS) elements.
• PERT facilitates identification of
the critical path and makes this
visible.
• PERT facilitates identification of
early start, late start, and slack for
each activity.
• PERT provides for potentially
reduced project duration due to
A completed network diagram created using Microsoft Visio. Note the critical path is in
better understanding of
red.
dependencies leading to improved
overlapping of activities and tasks where feasible.
• The large amount of project data can be organized & presented in diagram for use in decision making.
Disadvantages
• There can be potentially hundreds or thousands of activities and individual dependency relationships.
• PERT is not easily scalable for smaller projects.
• The network charts tend to be large and unwieldy requiring several pages to print and requiring specially sized
paper.
• The lack of a timeframe on most PERT/CPM charts makes it harder to show status although colours can help
(e.g., specific colour for completed nodes).
References
[1] Fazar, W., "Program Evaluation and Review Technique", The American Statistician, Vol. 13, No. 2, (April 1959), p.10.
[2] Malcolm, D. G., J. H. Roseboom, C. E. Clark, W. Fazar Application of a Technique for Research and Development Program Evaluation
OPERATIONS RESEARCH Vol. 7, No. 5, September–October 1959, pp. 646–669
[3] 1968 Winter Olympics official report. (http:/ / www. la84foundation. org/ 6oic/ OfficialReports/ 1968/ or1968. pdf) p. 49. Accessed 1
November 2010. &
[4] http:/ / en. wiktionary. org/ wiki/ lead#Verb_2
Further reading
• Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (5th ed.). Project
Management Institute. ISBN 978-1-935589-67-9.
• Klastorin, Ted (2003). Project Management: Tools and Trade-offs (3rd ed. ed.). Wiley. ISBN 978-0-471-41384-4.
• Harold Kerzner (2003). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (8th
Ed. ed.). Wiley. ISBN 0-471-22577-0.
• Milosevic, Dragan Z. (2003). Project Management ToolBox: Tools and Techniques for the Practicing Project
Manager. Wiley. ISBN 978-0-471-20822-8.
Float (project management) Source: http://en.wikipedia.org/w/index.php?oldid=612155566 Contributors: Busy Stubber, CPMTutor, Carabinieri, CertSchool PMP, ChrisGualtieri, Dia^, Fti74,
Jojalozzo, Krellis, LoganLopez, McGeddon, Mkoval, Mplemmons, Nuggetkiwi, Rjwilmsi, Smjg, SueHay, Tijuana Brass, Timkeys, Topbanana, 24 anonymous edits
Program evaluation and review technique (PERT) Source: http://en.wikipedia.org/w/index.php?oldid=616700617 Contributors: A Magician, Achalmeena, Amarvk, Avishek Barua, Benwu,
Bhadani, Bhause, Bjdehut, Blueronin, C1776M, Cagnol, CanadianLinuxUser, Catgut, Cgs, Chachrist, Cvanhasselt, Cybersteel8, Dbsheajr, Delaszk, Diego Azeta, Disquetemestizo, Dissolve,
Djanke, Druzhnik, E. Ripley, Enderminh, FF2010, Flyer22, Former user, Gavin White, George100, Georgia guy, Gilliam, GoShow, Graham87, Graibeard, Guy Siedes, Harej, Harryboyles,
Harsh.humtum.eng, Hazmat2, Hooperbloob, Ironwolf, JEBBAH, Jack Greenmaven, JavierMC, Jeff G., Jemoederiseenhoer1, Jeremykemp, Jojalozzo, JorgeGG, Karada, Kate, Kaushalarchana,
Ketiltrout, Klavierspieler, Kstarsinic, Kuru, L Kensington, LaurensvanLieshout, Leszek Jańczuk, Ligulem, Lindsay658, Maclir2001, MagnusA, Manofradio, Markhurd, Marlon.dumas,
Materialscientist, Maurreen, MaxPont, Mdd, Miller17CU94, Minesweeper, Mkoval, Mydogategodshat, Niravsdesai, Nixdorf, Olaf2, Oubiwann, Pasternaker, PatrickWeaver, Piano non troppo,
Pm master, Pmtoolbox, Recognizance, RedWolf, Rgephart, RichardF, Ronz, Rui Covelo, SFK2, Saurabh13686, Sbugs, Scirocco6, SeanDuggan, Seangies, SkipHuffman, Smjg, Sspecter, Stovl,
Swpb, Tga123, Tifoo, Tim Pritlove, Tolly4bolly, Tommy2010, Tony1, Truthraj, TutterMouse, Vrenator, Wayne Slam, Wikisteff, Wonderfl, Yuripobrasil, Zooloo, ﺃﺣﻤﺪ ﻣﺼﻄﻔﻰ ﺍﻟﺴﻴﺪ, 260
anonymous edits
Image Sources, Licenses and Contributors 16
License
Creative Commons Attribution-Share Alike 3.0
//creativecommons.org/licenses/by-sa/3.0/