BOQ & Resource Assignment-Initials !

The document provides a bill of quantities and specifications for the construction of a school project with an estimated total cost of 9.7 million. It includes 9 items: 1) sub-structure works such as excavation and concrete footing; 2) super-structure works like reinforced concrete columns and beams, masonry walls, roofing and doors/windows; 3) finishing works including plastering, flooring and pavement; 4) electrical works for wiring, switches and fittings; and 5) provisional sums. The document lists detailed descriptions, units, quantities, rates and costs for each work.

Uploaded by

Anteneh tesfaye
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
333 views2 pages

BOQ & Resource Assignment-Initials !

The document provides a bill of quantities and specifications for the construction of a school project with an estimated total cost of 9.7 million. It includes 9 items: 1) sub-structure works such as excavation and concrete footing; 2) super-structure works like reinforced concrete columns and beams, masonry walls, roofing and doors/windows; 3) finishing works including plastering, flooring and pavement; 4) electrical works for wiring, switches and fittings; and 5) provisional sums. The document lists detailed descriptions, units, quantities, rates and costs for each work.

Uploaded by

Anteneh tesfaye
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

BOQ and Specification for the construction of school project

It No Descriptions of Work Unit Qty Rate Amount

TOTAL PROJECT COST 10,000,000.00


CONTIGENCY 3% 301,859.49
TOTAL COST 9,698,140.51
A. SUB- STRUCTURE 2,685,968.02
1. EXCAVATION & EARTH WORK 613,071.00
1.01 Site clearing M² 1,530.00 20.00 30,600.00
1.02 Bulk Excavation M³ 761.60 120.00 91,392.00
1.03 Trench Excavation M³ 323.00 145.00 46,835.00
1.04 Selected Fill under hard core & Masonary M³ 432.48 350.00 151,368.00
1.05 20cm thick hard core M² 952.00 220.00 209,440.00
1.06 Disposal/Cart away M³ 1,390.60 60.00 83,436.00
2.CONCRETE WORK 1,518,017.02
2.01 C-5 Lean concrete Under Masonary M² 255.00 120.00 30,600.00
2.02 C-25 In Grade beam M³ 40.80 3,500.00 142,800.00
2.03 C-20 In Ground Floor Slab M² 952.00 700.00 666,400.00
2.04 Formwork To Grade Beam M² 204.00 370.00 75,480.00
2.05 Supply & Fix Reinforcement bar to Grade beam -

a) dia. 8mm deformed bar kg 1,107.04 85.00 94,098.49


b) dia. 12mm deformed bar kg 1,883.98 85.00 160,138.53
2.06 Supply & Fix Reinforcement bar to Ground floor
a) dia. 8mm deformed bar kg 3,740.00 85.00 317,900.00

20mm thick chipwood or styrofoam expansion


2.07 Ml 510.00 60.00 30,600.00
joint

3.MASONRY WORK 554,880.00


3.01 40 cm thick stone masonary Below ground level M³ 163.20 2,200.00 359,040.00
3.01 Ditto but Above natural ground level M³ 81.60 2,400.00 195,840.00
B. SUPER- STRUCTURE 7,012,172.49
1.CONCRETE WORK 674,235.84
1.01 Supply & Fix Reinforcement bar to Grade beam
1.011 a) In Elevation column M³ 8.16 3,500.00 28,560.00
1.012 b) In Top tie beams M³ 30.60 3,500.00 107,100.00
Supply, cut and fix in position wooden or steel
1.02
formwork
1.021 a) In Elevation column M² 163.20 370.00 60,384.00
1.022 b) In Top tie beams M² 306.00 370.00 113,220.00
1.02 Supply & Fix Reinforcement bar
1.021 To Elevation Column Kg 352.24 85.00 29,940.43
1.022 a) dia. 8mm deformed bar Kg 1,151.80 85.00 97,903.21
1.023 b) dia. 14mm deformed bar
1.024 To Top tie beams
1.025 a) dia. 8mm deformed bar Kg 905.76 85.00 76,989.68
1.026 b) dia. 12mm deformed bar Kg 1,883.98 85.00 160,138.53

1
BOQ and Specification for the construction of school project
2.BLOCK WORK 892,500.00
Supply and supply class B, 200x200x400mm
2.01 M² 1,785.00 500.00 892,500.00
HCB
3.ROOFING WORK 1,276,020.00
3.01 G-30 CIS roofing M² 1,224.00 650.00 795,600.00
3.02 Galvanized roof ridge Ml 153.00 250.00 38,250.00
3.03 G-30 galvanized flat metal sheet gutter Ml 578.00 390.00 225,420.00
3.04 Ribbed sheet on verendha M² 289.00 750.00 216,750.00
4. CARPENTRY & JOINERY WORK 1,136,960.00
4.01 Truss Members
a/ Supply and Fix Diameter 100-120mm for
Ml 1,955.00 120.00 234,600.00
upper & lower TRUSS member
b/ Supply and Fix Diameter 80-100mm for
Ml 1,870.00 100.00 187,000.00
vertical &diagonal truss member.
c/ 50x70mm Zigba wood Purlin c/c 900mm.
Ml 1,836.00 180.00 330,480.00
4.02 Fix fascia board 250x25mm. Ml 646.00 80.00 51,680.00
4.02 Fix Chipwood ceilings M² 952.00 350.00 333,200.00
5.METAL WORK 530,158.64
Fully Metal windows and doors manufactured
from 38X1mm LTZ frame profile and 1.5 mm
thick ribbed sheet
5.01 Door size 90x210cm No 17.00 6,615.80 112,468.64
5.02 Window size 130x180cm No 51.00 8,190.00 417,690.00
6. FINISHING WORK 1,766,300.00
6.01 Internal Plastering M² 1,632.00 200.00 326,400.00
6.02 External Plastering M² 1,632.00 220.00 359,040.00
6.03 Internal Gypsum Plastering M² 2,584.00 70.00 180,880.00
6.04 Pointing for external Masonry M² 204.00 150.00 30,600.00
6.05 50 mm thick smooth finished cement sand screed M² 952.00 300.00 285,600.00
6.06 80cm C-15 10cm thick mass concrete pavement M² 462.40 450.00 208,080.00
6.07 Half Dia 400mm wide concrete pipe ditch Ml 578.00 650.00 375,700.00
7. PAINTING WORK 440,640.00
Apply three coats of synthetic emulsion paint to
7.01 M² 1,632.00 75.00 122,400.00
internal plastered wall surface.
7.02 Apply quartz paint to External wall surface M² 1,632.00 195.00 318,240.00
8. SANITARY WORK 45,900.00
8.01 Fix 110mm diameter PVC down pipe Ml 306.00 150.00 45,900.00
9. ELECTRICAL WORK 249,458.00
9.01 Flush mounted main distribution Set 17.00 6,000.00 102,000.00
9.02 Flush mounted light point No 51.00 682.00 34,782.00
9.03 Ditto, but switch point makel or equivalent type No 34.00 682.00 23,188.00
9.04 Flush mounted socket out let No 34.00 682.00 23,188.00
FITTINGS
9.06 Switch approved makel or equivalent type No 34.00 150.00 5,100.00
9.07 Fluorescent fitting No 51.00 900.00 45,900.00
9.08 Socket No 34.00 450.00 15,300.00