Lect 1 - Cost Control
Lect 1 - Cost Control
COST
CONTROL
Preparation • The Client Requirements for the project are considered in more
& Briefing detail, in connection with a specific site or sites, and the
outcomes recorded in the Project Brief.
• Appointment of Design Team – architect, engineers, Qs.
• Two key activities involved:
1) Feasibility study – a proposal to determine whether a
project is viable or feasible from business, technical and
social points of view
2) Preparation of project brief - a statement of needs of the
client, how the propose facility will be used, define the
client’s requirements in terms of concept, time, cost and
functionality.
• Cost control systems needs to be established in order to
produce a realistic first estimate, known as the cost limit. The
cost limit is to test the feasibility of achieving the emerging
Project Brief.
Cost Limit
Total Cost of
Proposed = Cost /m2 GFA x Gross Floor Area
Building (analysed) (proposed)
COST CONTROL PROCESS
Stage of Description
work
3.2 Internal floor finishes RM45,000.00 RM90.00 Homogenous tiles to main areas, timber floor strip to bedrooms
and granite tiles to living areas.
SUB-TOTAL RM 888,375
8.0 Contingencies 5% x RM888,375=RM 44,418.75 RM88.84
TOTAL PROJECT COST RM 932,793.75 RM1865.60
COST CONTROL PROCESS
Stage of Description
work
Technical • Stage 4 involves the preparation of all information
Design required to manufacture and construct a building.
• It is to include all architectural, structural and building
services information, specialist subcontractor’s design
and final specification.
• The presence of detailed drawings and specification
permits the QS to prepare accurate estimate and
detailed quantities.
• BQ & tender document is prepared and tenderers are
invited.
• Submit Building Plan Application to local authority.
• Appointment of Contractors (traditional procurement)
COST CONTROL PROCESS
Stage of work Description
• Indirect Cost
QUANTITY SURVEYOR’S
COST CONTROL FUNCTION
Scrutinized the priced bills of quantities
and schedule of rates.
Agree with the contractor on ground
levels, suitable arrangements for dealing
with day works.
Claims for materials price fluctuation.
Costing for variation orders.
Measurements and interim valuation.
QUANTITY SURVEYOR’S COST
CONTROL FUNCTION (cont’d)
Comparison of the estimate with the total
allocated financial resources.
Assessment of profitability of the contract
secured.
Preparation of cash flow projection. Many
construction companies become
insolvent through bad estimating and
planning, ineffective cost control or
inadequate site control.
EFFECTIVE COST CONTROL
Effective cost control can be achieved by:
Establishing that all decisions taken during
design and construction are based on a
forecast of the cost implications of the
alternatives being considered.
Encouraging the project team to design within
the cost plan at all stages and follow the
variation/change and design development
control procedures for the project.
Regularly updating and reissuing the cost plan
and variation orders causing any alterations to
the brief.
EFFECTIVE COST CONTROL (cont’d)
Effectivecost control can be achieved by:
Checking that the agreed change
management process is strictly followed at all
stages of the project.
Arranging for the contractor to be given the
correct information at the correct time in order
to minimise claims.
Contingency provisions are based on a
thorough evaluation of the risks and are
available to pay for events which are
unforeseen and unforeseeable.
EFFECTIVE COST CONTROL (cont’d)
Effective cost control can be achieved by:
Submitting regular, up-to-date and accurate
cost reports.
Ensuring that all parties are clear about the
meaning of each entry in the cost report.
Ensuring that the project costs are always
reported back against the original approved
budget.
Plotting actual expenditure against predicted
to give an indication of the project’s progress.
QUICK REVIEW ON TERMINOLOGIES
Cost Studies – A process whereby cost information of similar
buildings is gathered and compared to provide a financial
dimension of new development and to review possible options.
Cost Limit – It simply means ‘maximum expenditure’. It also
mentioned as a statement of the limit of cost for clearly defined
client requirement beyond which a client is not prepared to enter
into a building contract.
Cost Plan - Cost plan is a cost statement in terms of how a
designer intends to design each element or part of a building.
Cost Check – It is a cost-monitoring activity to secure a genuine
design for elements that can be built based on the cost plan,
which have been prepared within the cost limit.
THE END…