Risk Ology Manual
Risk Ology Manual
The purpose of this note is to make the Riskology simulator accessible to you
and give you some idea of how to tailor it for your own needs.
What riskology is not
First of all you need to know that riskology is not a parametric estimator.
That is, it does not have the logic built into it to tell you how long your project
will take or how much it will cost. All it can tell you is how wide a window
you’ll need to leave in order to cover all the uncontrollable risks of your project.
You will still have to use a parametric analyzer or equivalent in order to calculate
the most optimistic delivery date. Once you have come up with that, it becomes
an input to riskology.
Riskology is also not a free-standing program. You need to purchase a copy
of Excel or other compatible spreadsheet program to run the simulator.
Riskology was constructed using Office X, so a version of Excel or equivalent
from 2002 or beyond will probably be sufficient.
Basic use of the simulator
Open the spreadsheet called RiskologyV4.xls. If your version of Excel
queries about macros, click to enable. This should present you with a workbook
of a dozen or so pages. In the yellow boxes on the first sheet, fill in the name of
your project, its start date, and its most optimistic end date. In order for this
exercise to have any meaning at all, it is essential that the end date you offer not
be totally unreasonable; there has to be at least some possibility of achieving the
date. It should represent the best case scenario, a date achievable if and only if
all variables break in your favor (no turnover, maximum productivity, virtually
no change of spec, etc.).
Once these three basic parameters are filled in, click once on the Run
Simulation button. After a short delay, the graph will present the result of 500
simulations of your project. The graph should be interpreted as an uncertainty
diagram, showing delivery in different date ranges due to differing impact of the
five core risks on the project.
Toggling risk factors on and off
Next, click on the tab for the second page of the workbook, entitled “Risk
Factor Setup.” This page is where you enable or disable up to ten risk factors, the
five core risks plus customized risks of your own.
You can disable any of the risks and then run the simulation again by
returning to the first page. You must click on the Recalculate button (back on the first
page) each time you want to see the result of your changes, since calculation mode is
set to Manual. By toggling a risk factor off and on, you can see the impact it is
having on your result.
Overriding the core risks with data of your own
Worksheet tabs 4-8 show the data and logic used to implement that portion
of the simulation associated with each of the five core risks.
• Tab 4: Schedule Flaw