Business Accounts
827 Hausman Road, Allentown, PA 18104
Tel: 888-220-9991
Fax: 484-634-3260
[email protected]
www.pplelectric.com/business
Thank you for downloading PPL Electric Utilities’ (PPL EU) application for electric service. To provide timely
electric service to your facility, an accurate and complete application is essential. NOTE: INCOMPLETE
APPLICATIONS WILL NOT BE PROCESSED AND WILL BE RETURNED.
Please complete the entire application and return it as soon as possible. Your application will be processed within two
working days after we receive a satisfactorily completed application. We will then send you a confirmation letter
informing you of your work order number. The work order number is unique to your job, will be used to track its status,
and will remain active for one (1) year from date of issue.
PPL EU’s service wires, transformers, meters and other equipment will be installed to meet the load requirements as
provided to us on the submitted application and will have a limited excess capacity. For a typical secondary service it
takes approximately 6 months to provide service and approximately 8 months for 12 kV Primary services.
If you have any questions concerning this application, please contact Business Accounts at
1-888-220-9991 option 4, or refer to PPL EU’s Rules for Electric Meter & Service Installations (REMSI) at:
https://www.pplelectric.com/at-your-service/electric-rates-and-rules/remsi.aspx
Return only the completed application at this time. Our confirmation letter will instruct you where to send drawings and
other supporting information.
1
APPLICATION FOR NEW AND CHANGE OF THREE-PHASE
SECONDARY/PRIMARY ELECTRIC SERVICE AND
RELOCATION OF PPL FACILITIES
Your electric service request will be processed after this form is completed in its entirety and returned to PPL Electric Utilities.
Timely completion of this form will avoid delay in providing service. PPL EU’s Rules for Electric Meter & Service Installation
(REMSI) is available on the PPL EU Website: https://www.pplelectric.com/at-your-service/electric-rates-and-rules/remsi.aspx .
TYPE OF REQUEST: NEW (will establish a new bill account & meter)
CHANGE (to an existing service & meter)
RELOCATION OF PPL FACILITES (Complete Pages 2 & 3 – top section)
In Service Date that the Permanent Service or Relocation is Requested for: / /
SUBMITTER INFORMATION
PPL Contractor ID#:
Submitted By: Date Submitted: / /
Title: Phone: ( ) - Ext.
Company: Cell Phone: ( ) -
Address: Fax: ( ) -
City/State/Zip: E-mail:
CUSTOMER INFORMATION
CUSTOMER NAME: PHONE: ( ) - Ext.
E-MAIL:
SERVICE ADDRESS: COUNTY:
CITY / STATE / ZIP: TWP:
MAILING/BILLING ADDRESS:
This form can be signed by the customer in order to complete the ratepayer confirmation that is required for NEW service.
By signing below, the customer is accepting responsibility for monthly electric service billing.
Signature of Ratepayer: Title:
CONSTRUCTION STATUS
IN PROGRESS COMPLETED NOT STARTED YET – WORK IS EXPECTED TO START / /
Party responsible for any PPL charges associated with providing electric service
CUSTOMER GENERAL CONTRACTOR ELECTRICAL CONTRACTOR
PROJECT CONTACT INFORMATION
Same as submitter See below
Name & Title: Phone: ( ) - Ext.
Company: Fax: ( ) -
Address: Cell Phone: ( ) -
2
City/State/Zip: E-mail:
3
BUSINESS/BUILDING INFORMATION
TYPE OF BUSINESS (Description): # OF SHIFTS:
BUILDING SQ. FT.: # OF STORIES IN BUILDING:
Will there be an addition to the building? YES NO
Will the existing point of delivery (meter location) remain the same? YES NO
Existing Building Sq. Ft: Sq. Ft. being added: Total Sq. Ft.:
**REQUIRED** CONNECTED ELECTRICAL LOAD **REQUIRED**
Our facilities will be designed and installed to provide for the customer’s requirements based on the load information provided;
therefore, accuracy is essential. Costs will be incurred from PPL EU for equipment requested that is not required to meet the customer’s
immediate load. Please indicate connected loads in terms of kW, HP and Tons. If this information is missing or incomplete, your
application will not be processed and could cause delays in providing service to your facility.
Removed
Added Equipment Description
(Upgrade Only)
Lighting Indoor kW kW
Outdoor kW kW
1-Phase Miscellaneous kW kW
1-Phase Motors (excludes HVAC) HP HP
3-Phase Motors (excludes HVAC) HP HP
3-Phase Miscellaneous (*Specify
Equipment) kW kW
Cooking kW kW
Water Heating/ Tankless Water Heater kW kW
Process Heating kW kW
Refrigeration kW kW
Space Heating *Required Info Below* kW kW
Air Conditioning *Required Info
Below* TONS TONS
Welders *Supply Spec Sheets* kW kW
Other (*Specify Equipment) kW kW
EV Charging, Battery Charging i.e.
kW kW
Fork Lifts
LARGEST MOTOR INFORMATION *Required
Note: All HP motor loads must be included in the Connected Electrical Load section above.
Do not include redundant motors such as back up motors for sewage plants.
Secondary Voltage (120/208v, 120/240v, 277/480v): # OF MOTORS 50 HP OR HIGHER (A/C included):
12.47 kV Primary Voltage : # OF MOTORS 100 HP OR HIGHER (A/C included):
69 kV Transmission Voltage : # OF MOTORS 750 HP OR HIGHER (A/C included):
***Completion of the table below is required for all motors listed above***
Description of Equipment HP Quantity # Motor Starter Estimated Starting NEMA Code or Power Factor at
that the Motor Drives (VFD/RVS/ Frequency Nameplate Starting
NONE) Starts/hr. Starts/day
Are any of these motors started simultaneously? No Yes If yes, which ones?
If known, project any electric loads that will be added to this service in the next three years:
Equipment Type:
Horsepower or kW of proposed equipment to be added:
4
When will equipment be added? (month/year):
**REQUIRED** HEATING & AIR CONDITIONING INFORMATION **REQUIRED**
PRIMARY SPACE HEATING SYSTEM: None Electric Resistance Heat Pump Other:
TYPE OF AIR COND: None Chiller Split System/Rooftop
PRIMARY PROCESS HEATING: None Induction heat melting Arc Furnace Resistance Furnace
5
PHONE NUMBER: (888) 220-9991, Option 4
www.pplelectric.com/business
6
THREE-PHASE ELECTRIC SERVICE INSTALLATION
AREAS OF RESPONSIBILITY
Refer to PPL’s Rules for Electric Meter & Service Installation (REMSI) for detailed information (https://www.pplelectric.com/at-
your-service/electric-rates-and-rules/remsi.aspx). Specific guidelines for electrical equipment installation and trenching specifications
are in the Customer Reference Specifications (https://www.pplelectric.com/at-your-service/electric-rates-and-rules/remsi/customer-
reference-specifications.aspx).
General Customer Responsibilities: (must be provided to PPL Electric Utilities before construction)
Completed application for electric service
Two copies of site plans showing preferred service location
Two copies of detailed drawings for the switchgear showing dimensions for the termination and metering compartment, if
applicable
A plan of the electric equipment room indicating clearances, if applicable
In Service Date requested
Right of way - Easements
Underwriter’s inspection certificate (Electrical inspection cut-in card)
Payment of applicable charges such as underground service, relocation of PPL Electric Utilities facilities, inadequate load
for voltage requested, reengineering, line extensions, service extensions, and temporary service
All Underground Services: (customer responsibilities per PPL Electric Utilities Specs)
Dig and prepare the trench (before digging call PA One Call-811 or 1-800-242-1776)
Encase underground PVC in concrete or steel conduit
Notify PPL Electric Utilities when trenching requirements have been completed
Backfill the trench
Provide and install meter base for self-contained metering
Provide and install instrument transformer cabinet for secondary metering
Install CTs, VTs, meter base, and benelex mounting for secondary metering
Pay applicable charges