2V VRLA Battery Rack Installation Guide
2V VRLA Battery Rack Installation Guide
2V VRLA Battery Rack Installation Guide
Installation preparation
Unpacking, inspecting and tallying the goods
Prepare installation tools (Wrench, box wrench, inner hexagon spanner )
Installation tools insulating treatment
Installation area
A passageway for Maintenance and inspection should be reserved
Safety precautions
Remove the watch, bracelets, bangles, finger rings and other metal objects.
Use insulated tools.
Wear goggles, rubber gloves.
Always keep the battery electrode facing upward when moving the battery. It is strictly
prohibited to keep it upside down.
Installation method
Battery can be installed in vertical or in horizontal. Recommend installation mode: OPzV series
vertical installation, DE/DEG series horizontal installation, SCG2V series horizontal and
vertical installation. Vertical Installation
Connector
Connector between the cell can be cable or copper bar, connector safety
current load for long duration as below,
2
Section area of connector (mm ) Current (A)
35 160 Cable Copper bar
50 200
70 250
1/3
2V VRLA Battery Rack Installation Guide
Horizontal Installation Diagram Top beam
Top beam
Bolt unit
Bolt unit
Back beam
Bolt unit
Middle beam
Output terminal
Tapping screw
M8*20 Bolt
Spring washer
Front block
Flat wash
Installation step
Place side frame of the rack on the ground,
Fix with front beam, middle beam and back beam tighten them with M8*40 bolt unit(use spring and normal washers),
Fix layer by layer using same pattern and complete the required layers according to installation drawing,
After complete the rack installation start install batteries in to the rack from first layer, Battery terminal
Install all the batteries layer by layer according to installation drawing,
Install front block with M4*8 tapping screw after battery installation,
Connect battery connector and output terminal.
2/3
2V VRLA Battery Rack Installation Guide
Vertical Installation Diagram
bolt unit
Beam
bolt unit
Beam
2V VRLA Battery rack installation sheet- 02-H-EN 2018. Subject to technical modification. E.&O.E.
Output terminal
M8*20 Bolt
Spring washer
Installation step
Place side frame of the rack on the ground,
Fix with beam tighten them with M8*35 bolt unit(use spring and normal washers),
Fix layer by layer using same pattern and complete the required layers according to installation drawing,
After complete the rack installation start install batteries into the rack from the first layer,
Install front bar after the first layer battery installation,
Install second layer battery and front bar, Battery terminal
Connect battery connector and output terminal.