Method Statement For Road and Paving Work
Method Statement For Road and Paving Work
Method Statement For Road and Paving Work
Owner’s Engineer
Contractor
Project
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
(2 X 600 MW)
Title
(Housing Complex)
Method Statement for Road and Paving Work
3 RESPONSIBILITIES: ....................................................................................................... 1
4 REFERENCE ................................................................................................................... 1
2 SCOPE OF WORK
This method statement covers the works which related to road and paving work at site. It also
describes details of EHS requirement, equipment, manpower.
3 RESPONSIBILITIES:
It is overall responsibility of project manager to organize resources to perform paving work
activities as per project specification in with schedule and safety requirements.
EHS Manager will ensure coordination with Site Manager and Site Supervisor that all measure
taken shall be maintained until completion of job.
It is the responsibility of Construction Manager/Site engineer that construction activities are
executed according to the relevant project specification in compliance with quality, schedule
and safety requirements.
Supervisor will ensure that the work is carried out in accordance with this method statement
and project specification.
The QC inspector will ensure that the work is executed according to the requirements of quality
are fulfilled.
4 REFERENCE
TCVN 9436:2012 – Highway embankments and cuttings – Construction and quality control
TCVN 8859:2011 – Graded Aggregate Bases and Subbases Pavement – Specification for
Construction and Acceptance
AASHTO M147-2005 – Material for Aggregate and Soil-Aggregate Subbase, Base and
Surface Courses
TCVN 8817-1:2011 – TCVN 8817-1:2011 – Cationic Emulsified Asphalt
TCVN 8819:2011 – Specification for Construction of Hot Mix Asphalt Concrete Pavement
and Acceptance
NS2-VW00-P0UYK-761401 Road Plan
NS2-VW00-P0UYK-761402 Road Section
NS2-VW00-P0UYK-761403 Road Detail
NS2-VW00-P0UYK-761404 Overall Layout Drawing
NS2-DD09-P0ZEN-169027 MS for General Concreting works
NS2-VE04-P0UYK-750029 Calculation for Road and Paving
5.1.3. SUB-BASE COURSE 5.2.3. BASE COURSE 5.3.3. INSTALL P.E FILM
Before commencement of common work, Contractor shall take a trial compaction test of
subbase & subgrade on a 80 m in length of road.
Grading of base and subbase material consists in Table 1 – AASHTO M147-65, and shall
be complied with supplier’s announcement.
5.1.2 Sub-grade
Check underground systems by drawings, to ensure underground systems have been
completed and not to damage underground systems during sub-grade is under
construction.
Proper barricade should be installed before commencement work.
Cut surface by bulldozer/grader or backhoe to replace soft soil or to get the required level
for the sub-grade material considering the finish compacted surface by roller compactor.
Below frequency shall be tested:
Density K ≥ 95% shall be taken every 300 m2.
During construction work, the input material must be under control of physical properties
by being frequent tested: 1000 m3 (TCVN 8859:2011).
After finishing compaction work, the following tests should be conducted:
CBR test ≥ 30%
Compaction density: K ≥ 95% (frequency: 800m2/point) (TCVN 8859:2011)
Geometric properties check:
Criteria
Tested properties Frequency
Sub-base
1 section/ 50 m in length
Level - 10 mm
for straight line
Slope 1 section/ 25 m in length
± 0.5%
for curve line
Thickness ± 10 mm
Cross length - 50 mm
Criteria
Tested properties Frequency
Base
1 section/ 50 m in length
Level - 5 mm
for straight line
Slope 1 section/ 25 m in length
± 0.3%
for curve line
Thickness ± 5 mm
Cross length - 50 mm
Where:
γtn: Average volumetric weight of asphalt specimen taken on site after constructing.
γ0: Average volumetric weight of asphalt specimen taken on batching plan.
Frequency: 3 bored samples for 2500 m2 of road area ( or 330 m in length for
road with 2 lanes), also use these bored samples for checking thickness of Blinder
course.
Surface roughness: 5 points/1km/1 lanes.
DRYING ( IF REQUIRED)
ROAD MARKING
5.2.2 Sub-grade
Refer to Section 5.1.2
Concrete spacer must be put properly to keep WWF at design position. The spacer is
casted by same grade with paving concrete
Take properly cleaning work for WWF
5.3 Sidewalk
5.3.2 Sub-grade
Refer to Section 5.1.2
List of All Job Steps List of All Known Hazards How to Eliminate Hazards
2.Survey Works. Instrument falling down and hit Area where the instrument is to be set must
workmen. be well compacted.
Instrument dropping to ground Focus and concentrate all the time during
by accident working execution.
Fall down into the excavated Provide armed excavation barricade and
area ladders with hand rails for access way.
Reflecting tape shall be added to the
barricade.
6.Placement emulsion The emulsion flew into the eyes. Wearing full needed PPEs at all time.
(Prime coat, Tack Coat).
8.Rebar, formwork & Laceration/cuts and pinch Ensure close monitoring of the Task
Concrete work. point. supervisor shall be performed before and
Eye injury due to install rebar & after installation of formwork.
concrete materials. Ensure hand tools are inspected and color
Incorrect position of body when coded as of the present with color
manual lifting of rebar, inspection.
formworks... etc. No defective and damage tools shall be
Slips, trip and fall due to unsafe used at work areas.
access. Remove defective and damage tools at
Slip & trip. work area.
1.Mobilization Driver Over speed/taking Traffic collision 4 4 U Truck is not to be o o M Injury/ fatality &
the equipment during transporting. with other overloaded. damage equipment
Pedestrian
to the site.
Equipment on the equipment and All equipment must be tied
trailer truck are not human. and wedged carefully.
secured. Equipment falling Truck shall move with low
down from the speed and do not overtake.
trailer truck.
2. Survey Surveyor & Holding survey Instrument falling 3 4 M Holding instrument o o T Near Miss
work Supervisor instrument un down and hit carefully.
carefully. workmen. Wearing full PPE & Full
Survey instrument set Fall from height. body safety harness.
up at un-safe location. Set up survey instruments
Un-safe survey at safe location.
making location.
Without fall protection
3. Excavation Operator. Non-compliance with Excavator 2 4 U Ensure safe access is o o M Injury/ Damage to
works. Method statement. toppled down provided to personnel, use equipment
Supervisor
Un-authorized access. deep hole hard barricades, sign
Flagman
excavation. boards.
Worker. Un-authorized entry
persons. Human caught All power tools and
between moving electrical equipment to be
Un-inspected the
parts of inspected and color coded.
equipment.
excavator. Flagman must be assigned
Without fall protection,
Excavator for each heavy equipment.
barricade and safe
collision with Suitable means of access
access
human & other and egress to be provided.
4. Concrete Worker Non-compliance with Laceration/cuts 3 2 T Wearing full needed PPEs. o o M Personal Injury.
works. PPEs requirements. and pinch point.
Supervisor Ensure close monitoring Pinch /caught in
Un-safe access. Eye injury due to of the Task supervisor shall between two
Practice improperly. install rebar & be performed before and objects /crashed
concrete after installation of fingers.
Poor materials
materials. formwork. .
arrangement.
In-correct Sufficient supports shall
Poor supervision.
position of body be provided (tie wires and
Without fire protection.
when manual bracing).
Un-inspection power lifting of rebar, Ensure hand tools are
tools. formworks... etc. inspected and color coded
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW) Page 19 of 29
Work Item : Infrastructure Works
(Housing Complex)Method Statement for Road and Paving Work
NS2-DD09-P0UYK-770021
Slips, trip and fall as of the present with color
due to unsafe inspection.
access. No defective and damage
Slip, trip & fall. tools shall be used at work
Skin irritation due areas.
to concrete Remove defective and
contact to skin. damage tools at work area.
Pedestrian No fabricated and home-
Incident/Injury. made tools shall be used at
Washing of mixer work area.
truck and Poured/ Water drainage measure,
Disposal of waste access ways shall free of
concrete. unwanted
Vehicle collision. Materials, keep good
Fire incident. materials arrangement.
(Housekeeping).
Electrocution
Task Supervisor shall
ensure authorized
personnel (Operator) shall
drive/operate the
equipment.
Barricade the working area.
Mobile equipment
(concrete mixer truck or
Pump car) shall be
provided with each trained
flagman
When pouring at night
sufficient lighting shall be
5. Spreading Supervisor Non-compliance with Eye injury due to 4 4 M Wearing full needed PPE. o o T Personal Injury.
base/subbase PPEs requirements. materials hitting
Worker Ensure close monitoring Injury/ Damage
using roller
compactor/ No signal Equipment of the Task supervisor. to equipment
grader Practice improperly. collide with each Flagman must be assigned
other due to no for each heavy
Poor materials
6. Asphalt Supervisor Equipment moving. Eye injury due to 4 4 M Wearing full needed PPE. o o T
spreading materials hitting
Worker Equipment (Diesel Ensure close monitoring
Engine) oil leakage Equipment of the Task supervisor
during operation. collide with each Flagman must be assigned
Dust/Air pollution. other due to no for each heavy
signal. equipment.
Equipment could Suitable means of access
fall down. and egress to be
Frequency Severity Risk Factor Number (RFN) Residual Risk Number (RRN)
1: Unlikely/Improbable 1: Negligible 1-2: Trivial/Acceptable 1-2: Trivial/Acceptable
2: Remote 2: Slight 3-5: Tolerable 3-5: Tolerable
3: Quite Possible/Occasional 3: Moderate 6-9: Moderate/Acceptable with review 6-9: Moderate/Acceptable with review
4: Likely/Probable 4: Critical/High 10-15: Substaintial 10-15: Substaintial
5: Very Likely/Frequent 5: Catastrophic/Very High 16-25: Intolerable/Unacceptable 16-25: Intolerable/Unacceptable
* Prepare Job Safety Analyis and Safety Verification
Check list when RRN is ≥ 6
** Prepare Safety Verification
Check list when RFN is ≥ 6
L1: Likelihood as is
L2: Likelihood with mitigating controls in place
S1: Severity as is
S2: Severity with mitigating controls in place
1 Total station 1
2 Auto level 2
3 Bulldozer 1 4D105
9 Excavator 1 0.69 m3
10 Dump truck 5
11 Tamping Rammer 3
γ kmax maximum dry density according to result of standard compaction test, g/cm3.
Kyc is requirement compaction ratio, %. Kyc ≥ 95% for base and subbase.
Compacting direction is from border to center (low point to high point) and follow long
axis.
Requirement for Compaction as below (section 7.2.4 of TCVN 8859:2011):
Preliminary compaction by
Step 1 Static Road Roller 8T (2~4
passes with max. velocity
Step 5
Conclusion
Compaction Plan