Createsap Projects Contracts
Createsap Projects Contracts
Table of Contents
1. Purpose ................................................................................................................................ 3
2. Applicability .......................................................................................................................... 3
3. Procedure ............................................................................................................................. 3
3.1 Working With Projects .................................................................................................. 3
3.1.1 Create Project Process Flow .......................................................................... 4
3.1.2 Create a Project .............................................................................................. 5
3.1.2.1 Complete Initial Screen .................................................................... 6
3.1.2.2 Create Project Definition .................................................................. 7
3.1.2.3 Complete User Fields..................................................................... 10
3.1.2.4 Create WBS Elements ................................................................... 13
3.1.2.5 Release Project and WBS Elements.............................................. 16
3.1.2.5.1 Release All WBS Elements .......................................... 16
3.1.2.5.2 Release WBS Elements Individually or in Sections...... 18
3.1.3 Change a Project .......................................................................................... 19
3.1.3.1 Change Project Process Flow........................................................ 19
3.1.3.2 Add a new WBS ............................................................................. 20
3.1.3.2.1 Check Your Changes ................................................... 24
3.1.3.2.2 Adding New WBS Element to a Contract ..................... 25
3.1.3.3 Changes to the Project Manager/CRM .......................................... 28
3.1.3.4 Additional Information .................................................................... 35
3.1.4 Close a Project.............................................................................................. 36
3.1.4.1 Status Closure (WBS Level) .......................................................... 36
3.1.4.2 Technically Close (Total Project Completion) ................................ 39
3.1.4.3 Reports To Be Run Before Project/WBS Closure .......................... 43
3.1.4.3.1 Order Overview Report (CNS45).................................. 43
3.1.4.3.2 Purchasing Documents per Project (ME2J) ................. 44
3.1.4.3.3 Time Recording Report (Y_T01_30000065) ................ 45
3.1.4.3.4 DPR Report (PS Project WBS Reporting) .................... 46
3.2 Working With Contracts .............................................................................................. 47
3.2.1 Create Contract Process Flow ..................................................................... 47
3.2.2 Create a Contract.......................................................................................... 48
3.2.2.1 Complete Overview Information..................................................... 49
3.2.2.2 Complete Header Information ........................................................ 50
3.2.2.3 Complete Line Item Information ..................................................... 52
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
2 of 87 DRAFT 1
2
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
3 of 87 DRAFT 1
1. PURPOSE
The purpose of creating a project/contract in SAP is to provide the Project Manager a
mechanism for tracking project costs and revenues.
2. APPLICABILITY
This procedure applies to all Revenue – Direct Billing projects.
3. PROCEDURE
3
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
4 of 87 DRAFT 1
Receive SAP
Project/Contract Create SAP Project/Contract
Input Information
Form
Tuesday, January 08, 2002
Create SAP
Project - CJ01
Copy/Paste WBS
Elements from SAP
Project
Create
Create SAP
Associated Yes
Contract - VA41
Contract?
No
Project Manager
Review Project/
Contract
Information
Status
4
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
5 of 87 DRAFT 1
5
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
6 of 87 DRAFT 1
6
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
7 of 87 DRAFT 1
All project definition data is entered on the “Basic Data” tab. The other tabs (Control
Data, Administration, etc.) contain default data – it is not necessary to enter data on
tabs other than the Basic Data tab.
7
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
8 of 87 DRAFT 1
8
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
9 of 87 DRAFT 1
7. Start Date:
Enter the project start date. Use MM/DD/YYYY format.
8. Finish Date:
Enter the project finish date. Always use 06/30/9999 to avoid “end-date”
problems.
9. Controlling Area and Company Code: (Default)
These fields are used for accounting purposes. The information defaults
from the project profile and cannot be changed.
9
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
10 of 87 DRAFT 1
10
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
11 of 87 DRAFT 1
The following window will appear to allow you to complete this information.
The Information you enter in these fields is used as the default information for WBS
elements and influences customer billing.
1. Customer: The customer that the project work is being done for. This
number is the “Sold-to” number on the project contract.
2. Application Code: The customer’s account that will be charged for project
work. This code corresponds to the City’s General Ledger.
3. Sales Contract: The project contract associated with the project, if it is a
revenue project. Leave this field blank for now. Enter the Sales Contract
information after the contract is created, using the Change Project menus.
4. Project Type: Numeric code representing the type of work. This is used to
filter report data.
5. Resource Manager: Employee ID number of the manager responsible for
coordinating the project staff resources.
11
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
12 of 87 DRAFT 1
Once this information is complete, use the WBS Element Overview icon to access
the WBS element overview screen and create the WBS element structure.
12
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
13 of 87 DRAFT 1
13
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
14 of 87 DRAFT 1
c. Description: (Optional)
A text description that provides clear and meaningful information about this
WBS element. This is a searchable field limited to 40 characters.
d. Short ID: (Defaults)
This field us automatically completed by SAP using a default value that is the
WBS element name. This field is used as a search tool.
e. Type: (Required)
The numeric code representing the type of work performed for the WBS
element, i.e., LAN install, maintenance, etc.
14
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
15 of 87 DRAFT 1
If the WBS
element is to
be assigned to
a contract
ensure the
Cont indicator
has a check-
mark.
15
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
16 of 87 DRAFT 1
16
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
17 of 87 DRAFT 1
To automatically release all new WBS elements by selecting the Edit -> Status ->
Release option from the Create Project : Project definition window.
NOTE:
Release all WBS
elements from
the Project
Definition Screen
17
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
18 of 87 DRAFT 1
NOTE:
Release individual
WBS elements
from the WBS
Element Overview
Screen.
a. Select the WBS element(s) to release and use the menu path Edit > Status >
Release.
b. Setting the system status of REL (Released) automatically sets a user status
of ACTV (Active).
c. Save the project by clicking the save icon .
Note: Set up sales contract now for Billable projects. Go to the Create a Contract
section for detailed instructions.
18
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
19 of 87 DRAFT 1
Change
Required
Project or
Contract?
Yes
Yes
Change Change
Associated Associated
Contract? Contract?
No No
Project Manager
Review Project/
Contract
Validation
Reports
19
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
20 of 87 DRAFT 1
20
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
21 of 87 DRAFT 1
Be sure to enter:
1. The appropriate level
2. A WBS element name that contains a common descriptor to aid in
sorting. This field is limited to 24 characters.
3. A text description that provides clear and meaningful information about
this WBS element. This is a searchable field limited to 40 characters.
21
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
22 of 87 DRAFT 1
22
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
23 of 87 DRAFT 1
!! Caution: You will not be able to add the WBS element(s) to a contract until
you have SAVED your changes,
23
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
24 of 87 DRAFT 1
Note: If the new WBS element(s) show Rel and Actv automatically, the
project was set up for automatic release of new WBS elements. Otherwise,
the project was set up using individual WBS element release provisions. This
means that all new WBS elements are required to be released by selecting
Edit>Status>Release from the Change project: WBS element Overview
window
24
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
25 of 87 DRAFT 1
!! Caution: At this point you must switch to the SAP Change a Contract
window and add the new WBS element(s) to the contract. If this
step is skipped, anything charged to this WBS element will not be
included in the billing.
Select the System -> New Session menu to open a new SAP session window to add
the new WBS element(s) to a contract.
25
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
26 of 87 DRAFT 1
When you have finished adding the new WBS element to the contract, you must also
enter the contract number to the WBS element.
a. Select the WBS elements that are connected to the contract
26
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
27 of 87 DRAFT 1
27
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
28 of 87 DRAFT 1
You may also locate the project name from the “drop-down” list.
28
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
29 of 87 DRAFT 1
Clicking the “drop-down” button provides you with the following search
window to allow you to search for the project name you want to change.
You can use the standard “*” wildcards to help you find your project. This will
result in a list that matches your search criteria.
Simply click on the project you need and press Enter to continue.
29
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
30 of 87 DRAFT 1
c. When the correct project is displayed in the Project def. window, click on the
Project Definition icon to open the Project Definition window.
30
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
31 of 87 DRAFT 1
d. The Project Definitions window allows you to make required changes to the
Project Manager (PM) and/or Client Relations Manager (CRM).
31
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
32 of 87 DRAFT 1
Hint:
This is a standard
SAP feature
available in all
windows.
Scroll down to the correct Project Manager and “double-click” to make the
selection. Changing the CRM/Sponsor is completed in the same manner.
Note: These changes do not affect any existing WBS elements, which must
be changed separately.
32
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
33 of 87 DRAFT 1
33
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
34 of 87 DRAFT 1
f. The WBS Element Overview window provides a listing of all existing WBS
elements for the current project. Select the Responsibilities tab to change the
Project Manager or Client Relations Manager for existing WBS elements.
h. When all changes have been completed, click on the Save button to
save your changes.
i. Note: All new WBS elements created in the future will use new PM or CRM.
34
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
35 of 87 DRAFT 1
1. Clicking the Project Definition icon on any screen and then select the
Administration tab to discover who and when the project was created, and
who and when the most recent change was completed.
2. Click on the WBS Element Overview icon and then select the WBS
Element you want information on. Then select the Information icon.
Next choose Extras->Change Documents -> All. To get more
information about an individual item, simply double-click on that item.
35
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
36 of 87 DRAFT 1
36
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
37 of 87 DRAFT 1
37
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
38 of 87 DRAFT 1
d. The Change Status window will display a list of the allowable User Statuses.
38
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
39 of 87 DRAFT 1
g. Click the green arrow Back button to return to the Change Project: WBS
Elements Overview screen.
39
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
40 of 87 DRAFT 1
b. Enter Name of Project and press the key to open the Change
Project:Project Definition window.
40
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
41 of 87 DRAFT 1
d. At the Status section of the screen, press the button to check that the
project has been marked completed.
41
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
42 of 87 DRAFT 1
42
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
43 of 87 DRAFT 1
43
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
44 of 87 DRAFT 1
44
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
45 of 87 DRAFT 1
45
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
46 of 87 DRAFT 1
p. Execute
d. Execute
Note: If your intention was to close down the project on June 30,2002, then
this report should report zero dollars in cost and revenue.
46
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
47 of 87 DRAFT 1
Receive SAP
Project/Contract Create SAP Project/Contract
Input Information
Form
Tuesday, January 08, 2002
Create SAP
Project - CJ01
Copy/Paste WBS
Elements from SAP
Project
Create
Create SAP
Associated Yes
Contract - VA41
Contract?
No
Project Manager
Review Project/
Contract
Information
Status
47
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
48 of 87 DRAFT 1
48
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
49 of 87 DRAFT 1
49
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
50 of 87 DRAFT 1
The following field definitions will help you create an accurate contract:
a. Project Contract: (Default # after save)
Leave blank.
b. Sold-to Party: (Required)
Customer number. – this corresponds to the customer number on the project.
Note: If your project has WBS elements that have different customer
numbers you will need to have a Project Sales Contract for each customer.
c. Ship-to Party: (Required)
Select the Ship-to # which is the same as the Sold-to #.
50
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
51 of 87 DRAFT 1
Note: The prompt to select an Application Code will only appear if this customer
has more than one Application Code. If no prompt appears, the default
Application Code for this customer will automatically be entered.
51
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
52 of 87 DRAFT 1
Hit <Enter> again, as often as necessary, to clear the SAP prompts and return to the
following Create Project Contract: Overview window so you can enter the
individual line items.
52
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
53 of 87 DRAFT 1
The following field definitions will assist you in entering the contract line items
correctly:
h. Item: Do not enter a value here.
This represents the line item in the contract and uses self-assigned default
values.
i. Material: (Required)
7. Material Code 900 is used for revenue-related billing. Enter a 900 for
every WBS you are connecting.
8. Material Code 901 is used for milestone billing. If your project requires
milestone billing you will need to request specific additional guidance from
the Project Management Office before continuing.
Note: At this point, switch to your SAP Project session and count the total
number of Level 1 WBS elements that require entry into this contract. The listing
of WBS elements used on the project is available on the Responsibilities tab of
the Change Project: WBS element Overview window.
53
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
54 of 87 DRAFT 1
j. Next, switch back to the Create Contract (VA41) SAP session and add a
900 or a 901 for each qualifying WBS element from the Change Project
(CJ02) SAP session.
k. Enter a 900 or 901 in the Material field and press <Enter> to be able to input
your WBS element(s). The Item and Description fields will automatically be
completed with default data and the WBS element field will be opened to
allow you to “paste” a WBS element from your other SAP Project Session.
"" Caution: If your project requires milestone billing you will need to
request specific additional guidance from the Project
Management Office before entering any Material Code
901 WBS elements.
54
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
55 of 87 DRAFT 1
55
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
56 of 87 DRAFT 1
10. Return to the Contract SAP session to “paste” the WBS element into the
4th column – WBS element.
Continue “copying and pasting” until you have added all required project
WBS elements into the project contract.
56
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
57 of 87 DRAFT 1
57
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
58 of 87 DRAFT 1
The Create Project Contract: Incompletion Log window provides a listing of data
items that need to be completed.
58
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
59 of 87 DRAFT 1
If the document is complete, a message appears in the bottom left corner saying
“The Document is Complete.” Save the contract and note the number that appears in
the bottom left corner. This contract number must be entered into the project. See
Section 3.1.2 Change a Project for more information on how to enter a contract
number into a project.
If the document is incomplete, the system displays a list of the incomplete item(s).
Complete any items by checking the box next to the item and clicking the “complete
data” button. Return to the contract overview by using the green back arrow.
Save the contract and note the number. This contract number must be entered into
the project. See Section 3.1.2 Change a Project for more information on how to enter
a contract number into a project.
Note: DON’T panic when the screen “whites” out . . . your data is already
saved. Look to bottom of the screen for the Contract number.
59
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
60 of 87 DRAFT 1
Change
Required
Project or
Contract?
Yes
Yes
Change Change
Associated Associated
Contract? Contract?
No No
Project Manager
Review Project/
Contract
Validation
Reports
60
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
61 of 87 DRAFT 1
To change a contract in SAP, click on the SAP icon on your desktop and
login.
n. From the main SAP Access Window, enter transaction code: VA42
61
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
62 of 87 DRAFT 1
The Change Contract Information window will appear. Click on the green
check-mark to continue.
Select “Create Item” to add blank lines for more WBS elements.
62
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
63 of 87 DRAFT 1
63
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
64 of 87 DRAFT 1
c. Next, switch back to the Change Contract (VA42) SAP session and add a
900 or a 901 for each new qualifying WBS element from the Change Project
(CJ02) SAP session.
64
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
65 of 87 DRAFT 1
d. Enter a 900 or 901 in the Material field and press <Enter> to be able to input
your WBS element(s). The Item and Description fields will automatically be
completed with default data and the WBS element field will be opened to
allow you to “paste” a WBS element from your other SAP Project Session.
"" Caution: If your project requires milestone billing you will need to
request specific additional guidance from the Project
Management Office before entering any Material Code
901 WBS elements.
65
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
66 of 87 DRAFT 1
66
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
67 of 87 DRAFT 1
Continue “copying and pasting” until you have added all required project
WBS elements into the project contract.
67
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
68 of 87 DRAFT 1
The Change Project Contract: Incompletion Log window provides a listing of data
items that need to be completed.
68
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
69 of 87 DRAFT 1
If the document is complete, a message appears in the bottom left corner saying
“The Document is Complete.” Save the contract.
If the document is incomplete, the system displays a list of the incomplete item(s).
Complete any items by checking the box next to the item and clicking the “complete
data” button. Return to the contract overview by using the green back arrow.
Save the contract.
Make a hardcopy of each change by using the computer’s “print screen” capability
and save the copy in your files.
69
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
70 of 87 DRAFT 1
"" Caution:
Before
attempting to
close a contract,
or a contract
WBS element,
ensure you
have run the
reports
described in
Section 3.1.4.3.
70
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
71 of 87 DRAFT 1
The Change Contract Information window will appear. Click on the green
check-mark to continue.
71
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
72 of 87 DRAFT 1
Go to “RJ” column (7th column over) and use the drop-down arrow .
Save your changes by clicking on the Save icon. Then make a hardcopy for
your files and give one to the Project Manager.
72
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
73 of 87 DRAFT 1
73
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
74 of 87 DRAFT 1
74
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
75 of 87 DRAFT 1
To prevent further billing on the contract, set the contract status to CNCL by clicking
the radio button.
Note: The user status field should read CNCL when the contract is closed. BILL
indicates the contract is open.
Return to the previous screen by selecting the green Back arrow button and
then click the Save button to save the contract.
75
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
76 of 87 DRAFT 1
When you have completed creating, updating, or closing your project and/or contract,
you must verify the completeness and accuracy of your work. This is accomplished
by running a couple of SAP reports and creating a couple of screen-grabs. These
items, detailed below, are provided to the Project Manager for review and final
acceptance.
76
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
77 of 87 DRAFT 1
Step 2:
If this is the first time you have run the CNS41 report for the day, you will be
presented with the following window.
For this report, type 000000000004 directly in the window, or select it from
the drop-down menu.
77
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
78 of 87 DRAFT 1
Step 3:
The Project Info System:Structure Initial Screen will allow you select
different criteria to gain a variety of project information.
Note: If you have run the CNS41 report earlier in the day, you will by-
pass Step 2 and go directly to this window.
Enter the Project name in the Project field.
78
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
79 of 87 DRAFT 1
Step 4:
The Structure Overview Report will allow you to verify:
a. WBS structure,
b. Application codes,
c. Customer numbers,
d. Profit center and
e. Sales/Contract number.
Note: Please note that the app code and customer number in these fields do
NOT insure correct billing. You must also check the Project Sales/Contract to
verify correct information. See following report to verify Sales (billing)
information.
79
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
80 of 87 DRAFT 1
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
81 of 87 DRAFT 1
Step 3:
Click on the third option – ACTV PROJ ONLY
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
82 of 87 DRAFT 1
Step 5:
Remember: You “may” have several “Sold-To- Party(s)” within your project.
For example: You have a prorated Sold-to-Party of 899970 for SPLASH, with
one WBS only pointing to Sold-to 152. With this example you would look in
two places for SPLASH project Sales/Contract information – 899970 & 152.
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
83 of 87 DRAFT 1
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
84 of 87 DRAFT 1
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
85 of 87 DRAFT 1
4. NOTES
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
1 of 87 DRAFT 1
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02
Procedure Name: Effective Date: Identifier:
[Eff Date] PRO0005-07
CREATING, CHANGING, AND CLOSING
SAP PROJECTS/CONTRACTS Page: Revision:
2 of 87 DRAFT 1
Printed copies of this page are for reference only – see online file for controlled copy.
TEP0005A-02