Bridge Deck Design
Bridge Deck Design
Bridge Deck Design
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Disclaimer: This example has been prepared to illustrate the design principles for a reinforced concrete bridge deck on
reinforced concrete abutments and pier to suit a hypothetical set of conditions. Users of this example should verify for
themselves the appropriateness of any parts of the example which they use for their own bridge designs and their own
particular conditions, and should check for themselves the correctness of any calculations that they copy. David Childs
has prepared this document to assist designers, but he takes no responsibility for how the example is used.
Geometry
2 No 19m spans centre to centre of bearings.
20o Skew.
7.3m wide carriageway with 2 No 2m wide footways.
125mm thick surfacing, which includes waterproofing.
Minimum headroom = 5.3m + S (See DMRB TD 27/05)
National speed limit 60mph (100kph) across deck.
The bridge will carry an Urban All-Purpose Single Carriageway
road and is located in York, North Yorkshire, England.
______________________________________________________________________________________
1
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Materials
Concrete to BS 8500:2006 (See Tables A.1 and A.5)
Deck concrete : C40/50 for exposure condition XD1 fcu=50N/mm2
Note: condition XC3 is allowed under waterproofing but maintain XD1 for the deck.
Parapet cantilever conc. : C40/50 for exposure condition XD3 fcu=50N/mm2
Pier concrete : C40/50 for exposure condition XD3 fcu=50N/mm2
Abutment and wing wall conc. : C32/40 for exp. condition XD2 fcu=40N/mm2
Steel reinforcement : Grade B500B to BS 4449:2005 fy=500N/mm2
BS 5400 Pt 2 Loading
Cl. 5.1.1 Dead: Reinforced Concrete density = 25 kN/m3 γconc = 25 kN/m3
Cl.5.2.1 Mastic Asphalt Road Surfacing Density = 22 kN/m3 γsurf = 22 kN/m3
Footway infill say = 22 kN/m3 γinfill = 22 kN/m3
Cl. 4.3.1.2 Differential Settlement:
The soil investigation report estimates that there will be 20 to
25mm settlement at the abutments and 5 to 10mm settlement at
the pier. Therefore allow for 15mm differential settlement. Diff.Set. = 15mm
Cl.6.1 Live:
Cl. 3.2.9.1 Carriageway width = 7.3m
Cl. 3.2.9.3.1 Number of notional lanes = 2
Notional Lane width wl = 3.65m
______________________________________________________________________________________
2
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Cl. 6.5 Footway Loading
Cl. 6.5.1.1 a) For one span loaded L = 19m Hence w = 5.0 kN/m2
b) For two spans loaded L = 38m
Hence w = 5.0 x [(29.4 x 10) / (38 + 270)] = 4.8 kN/m2
______________________________________________________________________________________
3
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Influence Lines (Use spreadsheet "Infline.xls")
For maximum sagging moment in deck apply HA UDL in one span with KEL
at 8.2m from end of deck.
For maximum hogging moment in deck apply HA UDL in both spans with
KEL at 10.9m from end of deck,
The KEL needs to positioned adjacent to the supports to obtain the critical
loading cases for shear effects.
A simple line beam analysis will provide guidance for the HB loading.
For critical loading positions of HB vehicle use spreadsheet MovinLd.xls
For maximum sagging moment position leading axle of HB vehicle at 15.067m
from abutment; the maximum moment occurs under the third axle at 7.267m
from the abutment. The HB vehicle with the 6m inner axle spacing will give
the critical sagging moment.
For maximum hogging moment over the centre support position the leading
axle in span 2 at 9.804m from the centre support. The HB vehicle with the
16m inner axle spacing will give the critical hogging moment.
______________________________________________________________________________________
4
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Preliminary Design
Use span to depth ratio about 20:1.
D = 19000 / 20 = 950 mm
Check maximum moment over centre pier using a line beam analysis:
Permanent Loads
For 3.65m (notional lane width) width of deck:
Weight of concrete = 3.65 x 0.95 x 25 = 86.7 kN/m
Weight of surfacing = 3.65 x 0.125 x 22 = 10.0 kN/m
Apply load factors for ultimate limit state from Table 1 then
UDL = (86.7 x 1.15) + (10.0 x 1.75) = 117.2 kN/m
Moment = wL2/8 = 117.2 x 192 / 8 = 5290 kNm
Differential settlement:
BS 5400 Pt 4
BS 8500 Pt 1
Table A5 Deck concrete is grade C40/50 with Class designation XD1 requires a
cover to reinforcement of 35 + ∆c = 35 + 15 = 50mm
BS 5400 Pt 4
Cl. 5.3.2.3 Assume 40mm dia. reinforcement then d = 950 - 50 - 20 = 880mm
Bars at 125 to 150mm c/c will generally meet crack control requirements so
try 40mm bars at 150 c/c then
As = (π x 402 / 4) x (3.65 x 1000 / 150) = 30580mm2
fcu = 50 N/mm2
fy = 500N/mm2
z = [1 - (1.1 x 500 x 30580) / (50 x 3650 x 880)]d = 0.895d
Mu = 0.87 x 500 x 30580 x 0.895 x 880 x 10-6 = 10480 kNm
10480 > 9625 kNm therefore continue with 950mm deck depth D = 950mm
Check for the additional load effects caused by the skew by using a
grillage analysis.
______________________________________________________________________________________
5
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Grillage Analysis
As the skew angle is relatively small (20o < 35o) then a skew mesh will give
sufficient accuracy. The maximum length to breadth ratio of the mesh
should be limited to about 2:1. Dividing the deck into suitable members to
coincide with critical positions we get:
______________________________________________________________________________________
6
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Load Cases:
Dead Load - Apply as UDL to longitudinal members
Concrete:
UDL on A = 5.07E+05 x 25 x 10E-06 = 12.68 kN/m
UDL on B = 8.04E+05 x 25 x 10E-06 = 20.10 kN/m
UDL on C = 8.67E+05 x 25 x 10E-06 = 21.68 kN/m
Surfacing:
UDL on C1 = 0.5 x 0.913 x 0.125 x 22 = 1.26 kN/m
UDL on C2 = 0.913 x 0.125 x 22 = 2.51 kN/m
Footway:
UDL on A = 0.375 x 0.25 x 22 = 2.06 kN/m
UDL on B = 1.125 x 0.25 x 22 = 6.19 kN/m
UDL on C1 = 0.50 x 0.25 x 22 = 2.75 kN/m
Parapet:
UDL on A = say 1kN/m (steel parapet with infill mesh)
Live Load
Some grillage models allow patch loads to be applied for uniform distributed
loads otherwise the UDL may be divided as for the Dead Load cases above.
The Knife Edge Loads may be applied as uniformly distributed loads on the
transverse members. The loads should be applied along the grillage
transverse member closest to the critical position determined from the
influence line diagram.
The KEL needs to positioned adjacent to the supports to obtain the critical
loading cases for shear effects.
The KEL should also be positioned on transverse members adjacent to the
estimated critical positions to ensure the skew effects are included.
The loads in a slab deck will tend to take the shortest path to the supports,
the shortest path between the pier and abutment being at right angles to
the centre-line of the bearings. The obtuse corner of a skewed deck will
therefore attract more load so the HB vehicle needs to be positioned in the
lane as shown above to check for the worst sagging moment.
A few positions adjacent to the critical line beam result should again be
checked to cover the effects of skew.
______________________________________________________________________________________
7
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
The footway UDL is included with the HA and HB load cases, although if the
accidental wheel load can load the footway then this load case will
generally govern the design of the cantilever members.
No other live loads are considered on the deck with the accidental wheel
load unless the parapet is required to be high containment (see Cl. 6.7.2.2)
______________________________________________________________________________________
8
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Grillage Analysis Results
The program 'SuperSTRESS was used to obtain the following results from a
grillage analysis of the permanent and live load cases described above.
We can compare these results with the analysis using no torsional stiffness
in the grillage members.
______________________________________________________________________________________
9
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Adjacent to Pier
Dead Load + Settlement + HA + Footway 445 Member 89 (C19)
Dead Load + Settlement + HB + Footway 449 Member 92 (C20)
Combination 3 loading:
Restraint to expansion and contraction will induce axial loads in the deck.
The restraint will be provided by friction or shear stiffness of the bearings
and/or the flexure of the substructure, both of which are insignificant
compared with the axial stiffness of the deck. This effect may be generally
ignored in the design of the deck but will be considered later in the bearing
BS 5400 Pt 2 and substructure design.
Cl. 5.4.1(b) Temperature differences between the top and bottom of the deck will
cause the deck to deflect and these effects need to be considered.
______________________________________________________________________________________
10
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Differential Temperature (Use spreadsheet "TempDiff5400.xls" contained in "105.zip")
Vertical Temperature Differences Using Non-Linear Effects
BS 5400-2:2006 Clause 5.4.5
h
For force equilibrium σbzdz = 0
0
h
For moment equilibriuσbzzdz = 0
0
Positive Reverse
Axial strain ε0 = -1.3E-05 Axial strain ε0 = -2E-05
Curvature y = 7.3E-08 Curvature y = -3E-09
Centroid of Section = 475 mm Centroid of Section = 475 mm
2
EI about centroid = 2216672 kNm EI about centroid = 2216672 kNm2
EA for Section = 2.9E+07 kN EA for Section = 2.9E+07 kN
Releasing Moment M = -161.466 kNm Releasing Moment M = 6.35388 kNm
Releasing Force F = 627.093 kN Releasing Force F = -681.47 kN
______________________________________________________________________________________
11
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
The stresses due to a releasing force and releasing moment can now be calculated using
the values for ε0 and ψ.
______________________________________________________________________________________
12
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Reverse temperature release moment = 6.35kNm
When this is distributed then the reaction at the pier is 1 kN and the hogging Moment at Pier
moment = 9.5 kNm. 10 kNm
The reverse temperature effect will increase the dead and live load moments
and reactions at the pier and will therefore need to be considered in this
combination. Shear at Pier
Shear at Pier = 0.5 kN 1 kN
______________________________________________________________________________________
13
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Adjacent to Pier
Dead Load + Settlement + HA + Footway 445 Member 89
Dead Load + Settlement 351
Hence HA + Footway 94
Adjust Live Ld γfL from combination 1 to 3 78 (1.25/1.5)
Factored shear due to Diff. Temp. 1
Dead Load + HA + Footway + Diff. Temp. 430
______________________________________________________________________________________
14
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
BS 5400 Pt 2
Cl. 4.1.3 Load Effects to be used for design = γf3 x effects of design loads
BS 5400 Pt 4
Cl. 4.2.2 Serviceability Limit State : γf3 = 1.0
Cl. 4.2.3 Ultimate Limit State : γf3 = 1.1
______________________________________________________________________________________
15
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
BS 5400 Pt 4 Reinforced Concrete Slab Design
Cl. 5.1.2.1 Design the slab for Ultimate Limit State and Check for Serviceability
Limit State.
Cl. 5.8.8.1 Use 25mm aggregate then minimum distance between bars = 25 + 5 = 30mm
In practice this should be an absolute minimum as vibrating pokers will often
become jammed; spacings in excess of 50mm should be aimed at.
40mm bars at 125 c/c gives a spacing of 85mm which is satisfactory.
2
Concrete Strength fcu = 50 N/mm Concrete Section
2
Steel Strength fy = 500 N/mm Breadth Depth
2
Cl. 4.3.2.2 Young's Modulus for Steel Es = 200000 N/mm 913 950
Table 13 Environment Conditions for nominal cover: Moderate
Reinforcement controlling crack width : Steel Reinforcement
Cover from notional surface = 25 mm Area Depth
Bar diameter (φ)= 40 Comp. 0 0
Spacing (s) = 125 Ten. 9178 880
______________________________________________________________________________________
16
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
2
Table 3 Young's Modulus for Concrete Ec = 34 kN/mm
2
Cl. 4.3.2.1b) Modified Ec = Ec(1-0.5Mg/(Mg+Mq)) = 21.02 kN/mm
Modular ratio αe = Es/Ec = 9.574
x/dt = αe(Ast/(bdt)+Asc/(bdt)+[(αe2{Ast/(bdt)+Asc/(bdt)}2+2αe{Ast/(bdt)+Ascdc/(bdt2)]0.5
x/dt = 0.370
x = 0.370 x 880 = 325.622 mm
3 2 2
Second Mom of Area of Cracked Section = Ixx = bx /3+αeAsc(x-dc) +αeAst(dt-x)
4
Ixx = 3.734E+10 mm
2
Steel stress = σs = αe(Mg+Mq)(dt-x)/Ixx = 300.122 N/mm
Steel strain = εs = σs/Es = 0.00150
Stress Limitations
2
Cl 4.1.1.3 Compressive stress in concrete = 18.53 N/mm
2
Compressive stress due to Temperature Difference = 0 N/mm
2
Total Compressive stress in concrete = 18.53 N/mm
2
Table 2 Allowable compressive stress = 0.5fcu = 25 N/mm Hence OK
2
Tensile stress in steel = 300.122 N/mm
2
Tensile stress due to Temperature Difference = 5.56 N/mm
2
Total Tensile stress in steel = 305.68 N/mm Section
2
Table 2 Allowable tensile stress = 0.75fy = 375 N/mm Hence OK over pier
B40@125c/c
Transverse Reinforcement
Maximum ULS moment in deck at pier = 1236 kNm (Combination 12)
Cl. 5.4.2 Cl. 5.3.2.3 Mu = (0.87fy)Asz
Deck concrete : C40/50 for exposure condition XD1
Steel reinforcement : Grade B500B to BS 4449:2005
fcu = 50 N/mm2 fy = 500 N/mm2
Width of grillage member = b = 1.9m
try 25mm bars at 200 c/c then
d = 950 - 50 - 40 - 13 = 847mm
As = (π x 252 / 4) x (1.9 x 1000 / 200) = 4663mm2
z = [1 - (1.1 x 500 x 4663) / (50 x 1900 x 847)]d = 0.97d > 0.95d hence use 0.95d
Mu = 0.87 x 500 x 4663 x 0.95 x 847 x 10-6 = 1632 kNm > 1236 kNm Hence OK
Use B25 @ 200
over the Pier
______________________________________________________________________________________
17
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Cl 5.8.9 Shrinkage and temperature reinforcement.
This clause provides a method of determining the reinforcement required
which is considered unreliable and the method detailed in BD 28/87 should
be used.
BD 28/87 Results obtained using spreadsheet 'EarlyThermal.xls' contained in '302.zip'
Cl.6.3 Although the deck is only 950mm thick (less than 1m) there will still be a
large mass of concrete which will generate heat when the deck is poured
and it is worth considering the internal restraint.
Restrained Section Length L = 38000 mm
Restrained Section Thickness T = 950 mm
Reinforcement Strength fy = 500 N/mm2
Concrete Strength fcu = 50 N/mm2
BS 8500-1 Deck concrete : C40/50 for exposure condition XD1
Table A.5 Cement content = 360 kg/m3
BD 28/87 Assume 18mm ply formwork is used and deck is poured in Summer
Cl.5.8 Short term fall in temperature T1 = 35 +10 = 45o
Ac for outer 250mm of section for 1m length of section = 500000 mm2
Tensile strength of immature concrete fct = 0.12*fcu0.7= 1.8555 N/mm2
Hence minimum area from equation (2) governs = 1855.5 mm2/m Transverse
2
Minimum area As in each face = 927.75 mm /m distribution
B16 @ 200 c/c = 1005 > 928 mm2/m Hence OK B16 @ 200c/c
______________________________________________________________________________________
18
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Cl. 5.4.4 Shear Resistance
3 2
Cl. 5.4.4.1 Shear stress = v = V/bd = 494 x 10 / (913 x 880) = 0.61 N/mm
Table 9 ξs = (500/d)1/4 = (500 / 880)1/4 = 0.89
vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3
vc = (0.27/1.25)(100x9178/913/880)1/3(40)1/3
0.77 N/mm2
1/2 2
Cl. 5.3.3.1 Max. allowable shear stress = 0.75(fcu) or 4.75 N/mm
1/2
= 0.75(50) = 5.3 or 4.75 i.e. = 4.75 N/mm2
0.61 < 4.75 N/mm2 Hence OK
Cl. 5.4.4.1 Max. allowable shear stress without shear reinforcement = 0.89x0.77 = 0.69
0.61 < 0.69 Hence shear links not required.
Cl. 5.8.8.1(a1) Bars in second row shall be in-line with the main steel and distance between
rows shall be greater than hagg. With 25mm aggregate then use 32mm φ bar
spacers.
Try B20 @ 250c/c Ast = π x 202 x 913 / (4 x 250) = 1147mm2
Effective depth = d = 880 - 20 - 32 - 10 = 818mm
Equivalent Ast at main steel level = 1147 x 818 / 880 = 1066 mm2 > 568mm2 Hence OK
______________________________________________________________________________________
19
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Cl. 5.4.4.2 Punching Shear
Maximum ULS reaction at pier bearing:
Combination 12, ULS reaction at node 221 = 1.1 x 3636 = 4000kN
The SLS reaction for this load combination = 3049kN (Combination 11)
Bearing dimensions are usually designed to achieve a bearing stress of about
20N/mm2 under nominal loading.
Say nominal reaction is about 3000kN then square bearing dimension is :
3 0.5
b = (3000 x 10 / 20) = 400mm
B40 @ 125 in longitudinal direction B25 @ 200 in transverse direction
Critical perimeter at 1.5d from loaded area:
Length in longitudinal direction = 2 x 1.5 x 880 + 400 = 3040 mm
Length in transverse direction = 2 x 1.5 x 847 + 400 = 2941 mm
As the spacing between the bearings = 1825 mm is less than 2941 mm then the
shear perimeter will not be formed around an isolated reaction and shear
will need to be considered across two failure lines either side of the pier.
Shear perimeter = 2 x 9.3 / cos20o = 19.8m
Maximum total reaction at pier (C 19) = 3550 + 1257 + 2371 + 1256 + 3551
= 11985 kN
Ultimate load = 1.1 x 11985 = 13184 kN
Dead load of deck between shear perimeters = Deck concrete + surfacing + fill
2
Cross sectional area of deck = (2x0.507+2x0.804+9x0.867) = 10.425 m
2
Cross sectional area of surfacing = 7.3 x 0.125 = 0.91 m
Cross sectional area of footway fill = 2 x 0.25 x 2.0 = 1.0 m2
Distance between shear perimeters = 3.040 m
Ultimate Dead load = 3.04x(1.15x10.425x25 + 1.75x0.91x22 + 1.2x1.0x22)
= 1098 kN
Live load on deck between shear perimeters = HA udl = 2 x 29.4 x 3.04 = 179 kN
Ultimate live load = 1.5x179 = 269 kN
______________________________________________________________________________________
21
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
2
Table 3 Young's Modulus for Concrete Ec = 34 kN/mm
2
Cl. 4.3.2.1b) Modified Ec = Ec(1-0.5Mg/(Mg+Mq)) = 25.25 kN/mm
Modular ratio αe = Es/Ec = 7.921
x/dt = αe(Ast/(bdt)+Asc/(bdt)+[(αe2{Ast/(bdt)+Asc/(bdt)}2+2αe{Ast/(bdt)+Ascdc/(bdt2)]0.5
x/dt = 0.287
x = 0.287 x 884 = 253.477 mm
3 2 2
Second Mom of Area of Cracked Section = Ixx = bx /3+αeAsc(x-dc) +αeAst(dt-x)
4
Ixx = 2.345E+10 mm
2
Steel stress = σs = αe(Mg+Mq)(dt-x)/Ixx = 288.099 N/mm
Steel strain = εs = σs/Es = 0.00144
2
Tensile stress in steel = 288.099 N/mm
2
Tensile stress due to Temperature Difference = 0 N/mm Mid Span
2
Total Tensile stress in steel = 288.099 N/mm section
2
Table 2 Allowable tensile stress = 0.75fy = 375 N/mm Hence OK B40@250c/c +
B32@250c/c
______________________________________________________________________________________
23
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Cl. 5.4.4 Shear adjacent to abutment
As there is only minimal bending in the longitudinal direction adjacent to the
abutment then the minimum steel area will be required.
Minimum steel required to prevent early thermal cracking = B16@200c/c
Steel in longitudinal direction is at 125c/c hence check shear capacity of
B16 @ 125 c/c As = π x 162/4 x 913/125 = 1469 mm2 d = 950 - 50 - 8 = 892mm
Max. ULS flexural shear = 275 kN
3 2
Cl. 5.4.4.1 Shear stress = v = V/bd = 275 x 10 / (913 x 892) = 0.34 N/mm
Table 9 ξs = (500/d)1/4 = (500 / 892)1/4 = 0.865
vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3
vc = (0.27/1.25)(100x1469/913/892)1/3(40)1/3
0.42 N/mm2
1/2 2
Cl. 5.3.3.1 Max. allowable shear stress = 0.75(fcu) or 4.75 N/mm
1/2
= 0.75(50) = 5.3 or 4.75 i.e. = 4.75 N/mm2
0.42 < 4.75 N/mm2 Hence OK
Cl. 5.4.4.1 Max. allowable shear stress without shear reinforcement = 0.865x0.42 = 0.36 At Abutment
0.36 > 0.34 Hence shear links not required. B16@125c/c
Cl. 5.4.4.2 Punching Shear
Punching shear for wheel loads need only be checked for thin slabs, as in a
beam and slab deck. However the calculation will be carried out for
BS 5400 Pt. 2 completeness.
Cl.6.2.5 Nominal wheel load = 100 kN acting on a contact area 300x300mm.
Cl. 6.2.6 Dispersal through surfacing is 1:2 so area on top face of concrete = 425x425
Note: BS 5400 Pt 4 Clause 5.4.4.2 overwrites dispersal down to neutral axis.
BS 5400 Pt. 4 Using the minimum steel area provided near end of deck:
Longitudinal steel B16@125c/c (As = 1608mm2/m, d = 950 - 50 - 8 = 892mm)
Skew transverse steel B16@200c/c (As = 1005mm2/m, d = 892- 16 =876mm)
Transform skew steel into longitudinal and square transverse directions:
Longitudinal = 1005 x sin220o = 118mm2/m
Transverse = 1005 x cos220o = 887mm2/m (d = 876mm)
Σ Longitudinal steel = 1608 + 118 = 1726 mm2/m
d = [(1608x892)+(118x876)]/1726 = 891mm
Cl. 5.4.4.2 Critical perimeter at 1.5d from loaded area:
Length in longitudinal direction = 2 x 1.5 x 892 + 425 = 3101 mm
Length in transverse direction = 2 x 1.5 x 847 + 425 = 2966 mm
vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3
Longitudinal steel: vc = (0.27/1.25)(100x1726/1000/891)1/3(40)1/3
vc = 0.427 N/mm2
ξs = (500/d) = (500 / 891)1/4 = 0.866
1/4
An envelope of the bending moment results for all dead and live load cases
will show the extent that reinforcement is required. We can superimpose the
bending capacities for various bar sizes to determine where bars can be
reduced.
A useful spreadsheet for obtaining the moment and shear capacities for
various bar arrangements is 'reinfPt4.xls ' contained in '303.zip '.
Standard bar sizes in the UK are 12, 16, 25, 32 and 40mm diameter. It is
good practice when reducing bar sizes to not miss more than one bar size.
So the B25 bar is included in the layout above to avoid lapping a B40 bar to
a B16.
Also bar diameters less than 12mm are avoided as the reinforcement needs to
be robust to avoid being damaged on site.
______________________________________________________________________________________
25
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Cl. 5.8.6.7 Lap Lengths
Lap lengths are usually stated on drawings as being so many bar diameters
which simplifies the fixing on site.
The minimum lap length = anchorage length to Cl. 5.8.6.3
Maximum design stress in the bar = 0.87 x fy = 0.87 x 500 = 435 N/mm2
Maximum design force in the bar = 435 (π x φ2 / 4) …………..…………………(1)
2 2
Cl. 5.8.6.3 Allowable bond stress for (fcu of 50 N/mm )= 3.3 N/mm (Table 15)
Maximum force to achieve bond stress = 3.3 (Anchorage length x π x φ) ……(2)
The minimum lap length of 25 times the smaller bar φ + 150mm for a 12 mm
bar gives a lap length of (25 + 150 / 12) φ = 38 φ
Minimum lap
So generally a minimum lap length of 40 φ will be suitable for most instances. 40 φ
Care is needed in detailing to avoid the 1.4 or 2.0 enhancement factor
required for the conditions highlighted in (a), (b) and (c) of Cl. 5.8.6.7.
Condition (b) is avoided by staggering bar laps in adjacent bars.
Although condition (a) applies to the 40mm bars in the top of the slab over
the pier, the stress in the bar where a 25mm bar is lapped is only :
435 x (252 / 402) = 0.4 x 435 N/mm2
So 1.4 x 0.4 = 0.56 < 1.0 is still less than the lap required for the 25 mm bar
______________________________________________________________________________________
26
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Parapet Cantilever
The maximum hogging moment in the
cantilever, from the grillage analysis, occurs
at the pier section. This load effect can be
reduced by constructing the cantilever and
parapet edge beam after the main deck
concrete has been poured and dead load
deflections have been allowed by releasing
the soffit falsework. This also helps to
achieve a uniform alignment to the edge beam.
Section Plan
Assuming the load effects from the outer wheels are dispersed at 45o back
to the root of the cantilever then the length of cantilever supporting these
wheels is 3.25m (assuming a 300 x 300mm contact area).
SLS Moment = [1.2x0.85x(100+75)] / 3.25 = 54.9 kNm/m
ULS Moment = [1.5x0.85x(100+75)] / 3.25 = 68.7 kNm/m
ULS Shear = 1.5(100+75) / 3.25 = 80.8 kN/m
BS 8500 Pt 1 Depth of section = 500mm
Table A5 Deck concrete is grade C40/50 with Class designation XD1 requires a
cover to reinforcement of 35 + ∆c = 35 + 15 = 50mm
Transverse bars in main deck are at 200mm c/c and will align with the bars
in the cantilever. The maximum cover to these bars will therefore be:
cover = 50 + 40(main longt'l bar dia.) = 90mm
Total SLS Moment = 30.8 + 54.9 = 85.7 kNm/m SLS M=85.7kNm
Design ULS Moment = 1.1x(35.6 + 68.7) = 114.7 kNm/m ULS M=114.7kNm
BS 5400 Pt 4 Design ULS Shear = 1.1x(29.4 + 80.8) = 121.7 kN/m ULS V=121.7kN
Cl.5.8.8.2 Mq / Mg = 54.9 / 30.8 = 1.78
Using spreadsheet 'reinfPt4.xls' contained in '303.zip' B20@200 c/c looks
satisfactory:
______________________________________________________________________________________
27
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
BS 8500 Pt 1 d = 500 - 50 - 40 - 10 = 400 (to align with main deck reinforcement)
Table A5 Cantilever concrete is grade C40/50 with Class designation XD3 requires a
cover to reinforcement of 45 + ∆c = 45 + 15 = 60mm
We will need to check later that this cover can be provided when the size of
the longitudinal and transverse steel has been determined.
As = (π x 202 / 4) x (1000 / 200) = 1571mm2
Cl. 5.3.2.3 z = [1 - (1.1 x 500 x 1571) / (50 x 1000 x 400)]d = 0.957d hence use 0.95d
Mu = (0.87fy)Asz = 0.87 x 500 x 1571 x 0.95 x 400 x 10-6 = 260 kNm > 114.7 kNm Hence OK
Note : With the wheel loads at the end of the deck the load distribution will
be truncated and the maximum length of cantilever supporting the wheel loads
ULS design moment = 114.7 x 3.25 / 2.25 = 166 < 260 Hence B20@200 c/c still OK
Max ULS M=166kNm
will be reduced from 3.25m to 2.25m.
Cl. 5.8.8.2 Maximum distance between bars for crack control:
Results obtained using spreadsheet 'CrackControl.xls' contained in '302.zip'
2
Concrete Strength fcu = 50 N/mm Concrete Section
2
Steel Strength fy = 500 N/mm Breadth Depth
2
Cl. 4.3.2.2 Young's Modulus for Steel Es = 200000 N/mm 1000 500
Table 13 Environment Conditions for nominal cover: Moderate
Reinforcement controlling crack width : Steel Reinforcement
Cover from notional surface = 25 mm Area Depth
Bar diameter (φ)= 20 Comp. 0 0
Spacing (s) = 200 Ten. 1571 400
2
Table 3 Young's Modulus for Concrete Ec = 34 kN/mm
2
Cl. 4.3.2.1b) Modified Ec = Ec(1-0.5Mg/(Mg+Mq)) = 27.89 kN/mm
x/d = 0.211
x= 84.334 mm
4
Second Mom of Area of Cracked Section = 1.32E+09 mm
2
Steel Stress = 146.687 N/mm
Steel Strain = 0.00073
______________________________________________________________________________________
28
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Stress Limitations
2
Cl. 4.1.1.3 Compressive stress in concrete = 5.47 N/mm
2
Compressive stress due to Temperature Difference = 0.00 N/mm
2
Total Compressive stress in concrete = 5.47 N/mm
2
Table 2 Allowable compressive stress = 0.5fcu = 25 N/mm Hence OK
2
Tensile stress in steel = 146.687 N/mm
2
Tensile stress due to Temperature Difference = 0.00 N/mm
2
Total Tensile stress in steel = 146.687 N/mm Main Cantilever
2
Table 2 Allowable tensile stress = 0.75fy = 375 N/mm Hence OK bar B20@200c/c
______________________________________________________________________________________
29
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Cl. 5.4.4 Shear Resistance
3 2
Cl. 5.4.4.1 Shear stress = v = V/bd = 121.7 x 10 / (1000 x 400) = 0.30 N/mm
Table 9 ξs = (500/d)1/4 = (500 / 400)1/4 = 1.057
vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3
vc = (0.27/1.25)(100x1571/1000/400)1/3(40)1/3
2
= 0.54 N/mm
Cl 5.3.3.1 Max allowable shear stress =0.75(fcu)1/2 or 4.75 N/mm2 i.e. 4.75 N/mm2
0.30 < 4.75 Hence shear links not required.
Secondary Reinforcement
Cl. 5.8.4.2 Minimum area of secondary reinforcement = 0.12% of btd
0.12% x 1000 x 400 = 480 mm2/m Use B12 @ 200 c/c (As=565)
We shall assume for the purpose of the design that the RRRAP indicates that
a parapet is required to be provided at the Normal Containment Level N2.
BS 5400 Pt2
CL. 6.7.1 Parapet is not high containment therefore only local effects need be
considered. For metal parapet the nominal collision load is:
a) The ultimate design moment of resistance (Mult) of the post
and
b) the lesser of:
i) Mult of post divided by the height of the lowest rail
or ii) Ultimate Shear Resistance (Vult) of parapet post
______________________________________________________________________________________
30
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
We now have to refer to parapet manufacturer's data sheets to obtain details
of the post strength and rail layout.
Corus manufacture a Protect 365TM N2 parapet and give the following data:
Post size = 100 x 100mm
Post Ultimate Moment Capacity = 19.8 kNm
Post Ultimate Shear Capacity = 164.9 kN
Height to centre-line of lowest rail = 275mm
ULS Dead Load Mom. = [(1.15 x 8.6) + (1.2 x 1)] x 0.4 x 0.99 = 4.4 kNm
ULS Live Load Mom. = 1.5 x (19.8 + 0.69 x 72) = 104.2 kNm
Total ULS Design Moment = 1.1 (4.4 + 104.2) = 119.5 kNm
BS 8500 Pt 1
Table A5 Cantilever concrete is grade C40/50 with Class designation XD3 requires a
cover to reinforcement of 45 + ∆c = 45 + 15 = 60mm
Cover provided to main bars = 90mm (see before).
d = 389 - 90 - 10 = 289 mm
Mq / Mg = 83.4 / 3.8 = 21.9
Using spreadsheet 'reinfPt4.xls' contained in '303.zip':
B20@200 c/c gives Mult = 184 kNm & Msls = 85 kNm
______________________________________________________________________________________
31
DAVID CHILDS Date: March 2009 Issue: 1003
B.Sc.,C.Eng.,MICE
Two Span Reinforced Concrete Bridge Deck Example to BS5400
Although the Msls moment is slightly less than required (85 < 87.2) the analysis
has been simplified. Sloping bars have been provided to the splay, these are
used to prevent cracking in the splay and also to stabilise the reinforcing bars
during concreting. These bars will also assist with the bending and shear Splay bars
capacity of the section. B12 @ 200 c/c
Reinforcement Layout
______________________________________________________________________________________
32