Self Study

The document describes a transportation problem to minimize total transportation cost. There are 4 factories and 4 markets, with given supply and demand capacities. The objective is to determine the optimal quantities of materials shipped from each factory to each market to meet demand at minimum cost.

Uploaded by

Urbi Roy Barman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views3 pages

Self Study

The document describes a transportation problem to minimize total transportation cost. There are 4 factories and 4 markets, with given supply and demand capacities. The objective is to determine the optimal quantities of materials shipped from each factory to each market to meet demand at minimum cost.

Uploaded by

Urbi Roy Barman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

https://www.youtube.com/watch?

v=qjM_5RP-eJw&list=PLCifInnO-CBpozYOLiPLkGp8Pui8aCJ6t

Market 1 Market 2 Market 3 Market 4 Capacity


Factory 1 5 4 6 3 250 Objective: Minimise total transporattion cost
Factory 2 7 8 8 1 300 Decision Variable: Quantity of material shipped from factory
Factory 3 4 4 3 6 100 eg: Quantity of material shipped from factory 2 to market 3
Factory 4 8 7 6 8 200 Total decision variable : 4 factories X 4 Markets =16
Demand 200 200 200 200 Constraints: Total supply from factories are limited
Total demand from markets is limited

Market 1 Market 2 Market 3 Market 4 Capacity Capacity


Factory 1 50 200 0 0 250 250
Factory 2 100 0 0 200 300 300
Factory 3 100 0 0 0 100 100
Factory 4 0 0 200 0 200 200
Demand 250 200 200 200 850

Demand 250 200 200 200

Total 3550
porattion cost
material shipped from factory I to market j
d from factory 2 to market 3
ories X 4 Markets =16
factories are limited