Project Management
Project Management
Project Management
Project Management
Project Management
Management increases the productivity through technological innovation taking into account
human factors involved in these advances.
Project Planning
Project Scheduling
Project Controlling
Project Planning
It involves defining objectives of the project, listing of tasks or jobs that must be performed,
determining gross requirements for materials, equipment and manpower and preparing estimates of
costs and durations for the various jobs or activities to bring about the satisfactory completion of the
project.
It is the most important phase of project management.
Why??
i. It provides direction
ii. It provides unifying framework
iii. It helps to reveal future opportunities and threats
iv. It provides performance standards
In the planning phase, plan is made and strategies are set, taking into consideration the company’s policies,
procedures and rules.
1. Plan – It is the statement of intent, i.e. what is to be done. It is interpreted in terms of what has to be
done to resources to achieve the intent.
2. Strategies – It is one important type of plan. It specifies the central concept or purpose of the
enterprise as well as the means by which it intend to carry that purpose.
3. Policies, procedures and rules – They differ in degree of specificity.
Policies usually set broad guide-lines for the enterprise. Procedure specify how to proceed in some
situation. A rule is even more specific guide for action.
Project Planning
4. EVALUATE : organization’s resources – financial, managerial and operational – to carry out activities and to
determine what is feasible and what is not.
5. DETERMINE : alternatives – individual courses of action that will allow to accomplish goals.
7. CHOOSE : an alternative which is not only consistent with its goals and concept but also one that can be
accomplished with the evaluated resources.
8. DECIDE : on a plan
During the planning phase, the information needed is about all those operations and activities, which have to be carried
out before the project is completed, their sequence and their logical inter relationship.
Resources:
i. Material resources (what)
Resources are the starting point of many problems
ii. Equipment resources (how)
that have to be solved by the manager in the
iii. Space resources (where)
planning phase, before proceeding for scheduling
iv. Effort or manpower resources (who)
phase of the project.
v. Time resources (when)
Project Scheduling
Scheduling is the allocation of resources. These resources, in conceptual sense, are time and energy, but
in practical sense are time, space, equipment and effort applied to material.
Scheduling is the mechanical process of formalizing the planned functions, assigning the starting and
completion dates to each part (or activity) of the work in such a manner that the whole work (or project)
proceeds in a logical sequence and in an orderly and systematic manner.
In other words, it is the laying out of the actual activities of the project in time order in which they are to
be performed, and calculating the manpower and material requirements needed at each stage of
production, along with the expected completion time of each activity.
As told earlier, the planning and scheduling phase of the project are undertaken before the actual project
starts while the controlling phase is undertaken during the actual project operations.
Controlling consists of reviewing the difference between the schedule and actual performance once
the project has begun.
Project control is the formal mechanism established to determine deviations from the basic plan, to
determine the precise effect of these deviations on the plan, and to replan and reschedule to compensate for
the deviations.
1. ESTABLISH : standards or targets. These targets are generally expressed in terms of time.
2. MEASURE : performance against the standards set down in the first step.
3. IDENTIFY : the deviations from the standards.
4. SUGGEST AND SELECT : correcting measures. This will involve all the problems-identifying,
decision-making and organizing and leadership skill of the decision-maker.
Operation Research
Generally we have several alternatives, and it is essential to evaluate them before we can choose best out
of these. This can be successfully done through operation research.
The term operation research generally refers to a set of mathematical techniques through which a variety
of organizational problems can be analyzed and solved.
Various complex research and development projects can be managed effectively if project managers have
the means to plan and control the schedules and costs of the work required to achieve their technical
performance objectives.
The answer to all these questions can be found by following the modern techniques of project
management.
Bar Charts:
Bar charts represent pictorial representation in two dimensions of a project by breaking it down into a
number of manageable units or activities for planning and control shown on one dimension or axis and the
durations assigned to these activities on the other dimensions or axes.
While the bar chart represents activities, a milestone chart represents the events which mark either the
beginning or the end of an activity.
The bar of the bar chart are broken into a number of pieces, each one of which represent an identifiable
major event.
It should be noted that each event is a point in time which the management has identified as important
reference point during the completion of the project.
Tools of Project Management
Bar charts represent pictorial representation in two dimensions of a project by breaking it down into a
number of manageable units or activities for planning and control shown on one dimension or axis and the
durations assigned to these activities on the other dimensions or axes.
While the bar chart represents activities, a milestone chart represents the events which mark either the
beginning or the end of an activity.
The bar of the bar chart are broken into a number of pieces, each one of which represent an identifiable
major event.
It should be noted that each event is a point in time which the management has identified as important
reference point during the completion of the project.
Bar Charts
Bar Chart
A project generally consists of a number of well defined manageable units or activities which should be
performed or completed in a definite sequence, for a successful completion of the project.
These activities or jobs are those operations of the project plan which take time to carry out and on which
resources are expanded.
Out of the various tools or techniques or project management, bar charts technique was probably one of
the earliest one.
A bar chart consists of two co-ordinate axes, one usually (the horizontal axis) representing the time
elapsed and the other (the vertical axis) represent the jobs and activities to be performed. Each bar
represent one specific job or activity of the project.
The beginning and end of each bar represent the time of start and time of finish of that activity ; the length
of bar, therefore, represents that time required for the completion of that job or activity.
Bar Charts
R
Activities or jobs
0 5 10 15 20 25
Time (Unit Days)
Bar Charts
This figure shows the bar chart for a project which has seven distinct jobs or activities (P,Q,R,S,T,U,V) to
be performed for its completion.
The time durations required for the completion of these activities are 10, 5, 10, 7, 5, 8 and 15 unit days
respectively.
i. Activity P and Q can start simultaneously, at zero time. Both the activities are independent. However,
activity Q is completed much earlier than activity P.
iii. However, activity S is independent of activity R. It starts earlier than R and is completed earlier.
vi. Activity V can start when activity P and S are complete. End of activity V marks the completion of
the project.
Bar Charts
Illustrative examples:
1. Draw a bar chart for ‘finalization of designs and work order’ for a building project.
In the above project, activities A and B can start concurrently, since some parts of the architectural and
structural designs can be done even if complete survey data is not available. Similarly, drawing work
can also be started, as soon as survey work is over, though all the designs are still not complete.
Specifications can be finalized when once the designs are complete. Activity E can be started only when
activity D is complete. Activities E,F and G are to be completed in sequential order.
The bar chart representing the above sequence of activities is shown in next slide. From the figure, we
conclude that the total time required for this phase in 14 weeks.
Bar Charts
B. Designs
C. Drawings
Activity
E. N.I.T
F. Selection of Contractor
BAR CHART FOR FINALIZATION OF DESIGNS AND WORK ORDER FOR A BUILDING PROJECT
Bar Charts
2. The activity breakdown for a certain project is as under :
Activity 2 and activity 3 can be done concurrently, and both must follow activity 1.
Activity 2 must precede activity 4.
Activity 5 cannot begin until both activities 2 and 3 are completed.
Activity 6 can be started only after activities 4 and 5 are complete.
Activity 7 is the last activity which can be started only after completion of activity 5.
3
Activity Number
7
0 1 2 3 4 5 6 7 8 9 10
Time (Weeks)
Bar Charts
3. A typical small house construction project consists of the following operations along with the time set for its
completion.
S. No Operation Time (in days)
1. Survey, design and layout 3
2. Construction of foundations 5
3. Construction of superstructure 11
4. Roofing 5
5. Fixing doors and window frames 2
6. Plumbing and house drainage 3
7. Electric fitting 3
8. Plastering 4
9. Flooring 4
10. Carpentry work 4
11. Construction of boundary wall and other minor items 3
12. Landscaping and clearing 2
13. Whitewashing of walls and painting of doors 3
14. Inauguration 1
The project commences on Wednesday, 14th October. Assuming five working days in a week, prepare
bar chart of the project. State the assumptions made. Also determine (a) total time, and date of
completion of the project (b) expected progress by 10th November.
Bar Charts
10
11
12
13
14
Dates 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Days T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Months October November
Bar Charts
The bar chart shown here, prepared with the following assumptions regarding the sequence of various
items.
From the bar chart we find that the project will be completed on 30th November – 48 days after it starts.
For effective completion of the main activity, these sub activities should be scheduled properly. The above
information can be shown effectively by marking stages (called mile stones) on the activity bar, shown in
the next slide. Similarly, sub activities of other activities of each bar can be marked with stages or mile
stones 1, 2, 3 etc. A’, B’, C’ etc.
Bar Charts
Bar Charts
Activity C is dependent
on B and A, while
activity B is dependent
on activity A. If all the
activities are scheduled
serially, it will take a
very long time – 28
weeks for completion.
However the activities
can be staggered as
shown below.
Bar Charts
From the bar chart , we find that if activity B is started 4 weeks after activity A, activity B has 2 weeks
work left after completion of activity A. Similarly, activity C has 2 weeks works left after completion of
activity B. Now, if due to some circumstances, time of completion of activity A is delayed by 1 or 2
weeks, how will the activities B and C be affected?
This is not clearly portrayed by bar chart, since inter dependencies of the activities are not clearly indicated
by bar charts.
This difficulty can be partly overcome by breaking each activity into a number ofsections, so that the
corresponding sections of various activities are precisely depicted inter-dependently. For example, let the
jobs of figure below be divided into 4 sections. Since activity B is faster than activity A and C is still
faster, the shifting or staggering of these activities can be for more than 1 section. The modified bar chart
is shown by depicting the completion of each section by milestones 1,2,3 and 4
For activity A
(excavate), each
section will require
3 weeks time. For
activity B, each
section will require
2.5 weeks time
while for activity
C, each section will
require 1.5 weeks
time of completion.
Bar Charts
Time uncertainties:
Bar charts are not at all useful in those projects where there are uncertainties in determination or estimation
of time required for the completion of various activites. Such uncertainities are always there in research
and development projects and for space vehicle launch projects. Because of uncertainties in time
determination in these projects, some of the activites may require rescheduling. Such rescheduling
flexibility cannot be reflected in the bar chart diagrams. Hence bar chart diagrams are useful only for small
size conventional projects, especially construction and manufacturing projects, in which time estimates can
be made with fair degree of certainty.
Milestone Charts
Milestone Charts
Milestone chart is a modification over the original Gantt chart. Milestones are key events of a main
activity represented by a bar: these are specific points in time which mark the completion of certain
portions of the main activity. These points are those which can be easily identified over the main bar. We
have already seen that when a particular activity, represented by a bar on a bar chart is very long, the
details lack.
If however, the activity is broken or sub divided into a number of sub activites, each one of which can be
easlity recognized during the progress of the project, controlling can be easily done and inter relationships
between other similar activities can be easlity established.
The beginning and end of these sub divided activities or tasks are termed as milestones.
Milestone Charts
Figure on right in the previous slide shows some milestones on each bar. Each main task contains some
specific points in time which can be recognized, and through which controlling can be achieved. Each
milestone can be considered to be specific event along the main activity or job or task. The chart is,
therefore called the milestone chart. Each milestone is represented either by circle or by a square, and is
serially marked.
Shortcoming:
Though controlling can be better achieved with the help of milestone chart, it still posses the same
deficiency contained by the bar chart – it doesnot show the inter dependencies between the events. Within
a task, the relationship between two specific milestones is revealed, but the relationship between and
among milestones, contained in different task is not indicated on the chart.
For example fig on right does not indicate whether milestone 6 can be started before milestone 2 has been
completed, or whether milestones of task C are all dependent on milestones of task A.
What is a network?
A network is a flow diagram consisting of activities and events, connected logically and sequentially. In
the network diagram, an activity is represented by arrows while events are represented, usually by circles.
Event Ac
vity tiv
Acti ity
Activity
Event Event Event
Ac
tivi
ty i vity
A ct
Event
NETWORK DIAGRAM
1. Event
2. Activity
Side Boards
Foundation
Foundation
Excavated
Concreted
Started
Project
Fixed
1 2 3 4
Excavate Fix Side Concrete
Foundation Boards Foundations
Elements of Network
Event
The commencement or completion of an activity is called an event. An event is that particular instant of
time at which some specific part of a plan has been or is to be achieved. More specifically an event is a
specific definable accomplishment in a project plan, recognizable at a particular instant of time.
Activity
An activity is the actual performance of a task. It is the work required to complete a specific event. An
activity is a recognizable part of a work project that requires time and resources for its completion.
Examples:
Design completed –
Prepare Budget-
Excavation completed-
Parts assembled-
Excavate Foundation-
Pipe line laid-
Excavate trench-
Mix concrete-
Elements of Network
1. Tail Event
A tail event is the one which marks the beginning of an activity. If a particular tail event represents the
commencement of the project, it is known as the initial event.
10 1
Type 1 Type 2
ty A
Activi
Activity B
30
Activit
yC
Type 3
Type 1 – Shows the tail event representing the beginning of certain activity
Type 2 – Shows the initial event
Type 3 – Shows the tail activity marking the beginning of 3 activities.
Suppose Activity A commences at 6 units of time, Activity B at 4 units and Activity C at 7 units.
Thus the earliest occurrence is 4 units of time. A tail event representing the beginning of more than one
activity, is said to occur when the first activity starts from it.
Elements of Network
2. Head Event
All activities have an ending i.e. again a specific point of time and is marked by an event. Such an event is
known as head event, because in a network diagram, it is connected to the head or barbed end of arrow. If
a particular head event marks the completion of the project it is known as the final or end event.
10 n
Type 1 Type 2
Activi
ty A
Activity B
30
yC
Activit
Type 3
Almost, most of the events serve dual function i.e., they are head events to some activity and tail event to
other activity. All events except initial and final events are dual role events.
Activity A Activity B
10
Activi ty P
ty A Activi
Activity B
30
yC
Activit Activit
yQ
Elements of Network
D
A
B E
1 3 5
4
Elements of Network
Interrelationship between
events
Successor events
The event or events that follow
another event are called 2
successor events to that event. E
Also, the event or events that A
immediately follow another
event without any intervening
ones are called immediate B F
successor events to that event. 1 3 5
Predecessor events
The event or events that occur C
before another event are called G
predecessor events to that
event. Also, the event or events
that immediately come before 4
another event without any
intervening ones are called
immediate predecessor events.
Elements of Network
Inter relationships
Parallel activities
Those activities which can be performed simultaneously and independently to each other are known as
parallel activities.
Serial activities
Serial activities are those which can be performed one after the other, in succession. These activities
cannot be performed independently to each other.
Predecessor activity
Activity or activities that are required to be performed before another job or activity can begin are called
predecessor activities to that activity. The activity or activities that are required to be performed
immediately before another activity, without an intervening activity are known as immediate predecessor
activities to activity.
Successor activity
Activity or activities that can be performed after the performance of other activity are known as successor
activities to that activity. The activity or activities that immediately follow another activity, without any
intervening activity are known as immediate successor activities to that activity.
Redundancy exists when among the number of predecessor activities of any given activity, one of the
activity is a predecessor to some other activity in the same set.
Elements of Network
C
A
B D
Elements of Network
Draw a network diagram for the project having 9 activities, with the following inter – relationships:
D
F G I
B H
D
F
A E I
Elements of Network
B C H
G
A E I
B C
H
F
G
A E I
Elements of Network
C
H
A
F
G
B E I
C
2 4
H
A
F
1 D 5 7
G
B E I
3 6
Elements of Network
The maintenance project of a building consists of 10 jobs. The predecessor relationships are identified by
their node numbers, as indicated below:
A building project consists of 11 activities as shown below. The normal duration required to perform
various activities is also given:
12
10
8
8 10 12
4 5 7 8
1
8
6
6
12
5
3 6