STP Comparision of Process
STP Comparision of Process
1 Biological Processes
In these processes a mixture of wastewater and microorganisms (biomass) is
agitated and aerated. Certain microbes, mainly bacteria of specific kind, have the
capability to oxidize the dissolved organic matter in the waste water. Microbial growth
is accelerated and controlled in the process. Thus, reduction or removal of organic
matter in waste is brought about by microorganisms by oxidation. After oxidation, the
sludge is separated from wastewater. These, microbial induced processes are further
classified as Aerobic and Anaerobic.
a) Aerobic Processes- In presence of oxygen
b) Anaerobic Processes- In absence of oxygen
.1.1 Aerobic Processes- The following conventional methodologies are
examples of Aerobic Processesa)
Activated sludge process (ASP)
b) Trickling filters
c) Facultative aerated lagoons
d) Extended aeration process
e) Wet Lands
f) Oxidation ponds
g) Oxidation ditches
In modern nomenclature the aerobic processes are divided into Aerobic
Suspended and Attached Growth Processes and the Soil Biotechnology.
.1.1.1 Aerobic Suspended Growth Processes (SGP) The conventional
activated sludge process (ASP) is the best known suspended growth aerobic system
and is the process most commonly used in large, centralized WWTPs though it can
also be used in small plants. Some of the process varients of ASP area)
Sequencing Batch Reactor (SBR)
b) Extended Aeration
c) Membrane Bioreactors (MBR)
.1.1.2 Aerobic Attached Growth Processes (AGP) Under the AGP, two
proven and fairly known treatment processes are available as following:
a) Moving Bed Biological Reactor (MBBR) The Moving Bed Biological
Reactor may be known by different names as under, however the process remaining
same with free floating media of different shapes, sizes and materials (generally
plastic).
(i) Fluidised Bed Reactor (FBR)
(ii) Moving Bed Bio Reactor (MBBR)
(iii) Sequential Batch Reactor (SBR)
b) Fixed Bed Biological Reactor (FBBR) Similarly, the Fixed Bed
Biological Reactor may also be known by different names as under, but the technology
remains same as that of MBBR except that the media is fixed horizontally/ radially or
sloping (normally at 60º) in packed beds of different depths and of different sizes and
materials (generally plastics).
(i) Submerged Aerobic Fixed Film (SAFF)
(ii) Fixed Bed Reactor (FBR)
(iii) Fixed Media Reactor (FMR)
(iv) Fixed Media Biological Reactor(FMBR)
(v) Fixed Bed Biological Reactor(FBBR)
(vi) Bio Tower
(vii) Rotating Biological Contractors (RBC) (Also called Biodisks).
.1.1.3 Soil Biotechnology or Constructed Wetlands.
1.2 Anaerobic Units These can be generally grouped into the following:-
a) Anaerobic ponds/ stabilization ponds
b) Upflow Anaerobic Sludge Blanket (UASB) reactor followed by lagoons
etc (Suitable for large capacity plants say 20 mld or above).
2 Chemical unit processes
a) Chemical neutralization: to control or adjust pH.
b) Chemical coagulation: to remove colloidal particles by chemical
destabilization and flocculation.
c) Chemical precipitation: to enhance the removal of suspended solids,
Phosphorous, heavy metals, and BOD in the specific system conditions.
d) Chemical oxidation: to remove grease, ammonia, BOD, COD, and odour
control.
e) Chemical disinfection: to kill pathogens in influent and treatment
effluents.
3 Design of Process Flow Sheets
Upflow Activated
Moving Bed Sequencing Anaerobic Sludge Rotating
Bioreactor Batch Sludge Process Biological
Parameter
(MBBR - Reactor Blanket (ASP) - Contactors
FAB) (SBR) Reactor Extended (RBCs)
(UASB) aeration
This is strictly
anaerobic
process. BOD This is an
BOD reduction reduction attached
takes place takes place by BOD reduction growth process,
aerobically. converting takes much
Type of BOD reduction organic matter similar to
Suspended place
Process takes place to methane trickling filters.
growth aerobically.
aerobically. Fixed / carbon di- The biomass is
process. Suspended
film process oxide and attached
Improvised growth
Activated other gases, process. to rotating
Sludge Process through media.
bacterial
systhesis.
Area Very small area Area required is Area required is Very large area Very large area
requirements required as higher than larger required for is
compared to MBBR but less than ASP and aeration required since
SBR, then ASP. other tank as well as the
ASP, UASB, processes. for loading rates on
RBC secondary the disc
clarifiers. are limited by
the
surface area
available.
Power Power Power required Power Large power is Low power than
requirement requirement is more than requirement is required ASP,
is lower than MBBR or equal lower than most for aeration, higher than
MBR. to activated of the return UASB.
sludge processes. sludge pumping
process However etc.
UASB alone
cannot
produce desired
outlet
quality.
Additional
ASP /
ponds must be
provided,
thereby
increasing the
power
requirement.
Moving parts No moving part in Moving parts in No moving Depending on Main moving
biological biological parts within the part is the
process process. UASB. aeration system, central shaft
Decanter However there and drive,
mechanism is downstream can be moving which come
mechanically ASP has parts under
activated and typical such as surface continuous
hence maintenance aerators, brush stress
needs Requirements. rotors
continuous etc, which need
maintenance. Maintenance.
Without
decanter, SBR
does not
function at all.
Very high level
of
instrumentation
is required.
Operation & No scum The entire plant Gas hoods Relatively Prone to lot of
Maintenance formation operation is need to be simpler maintenance of
in the process & cyclic cleaned every maintenance of shaft /
less moving parts in nature & 06 months mechanical drive parts. In
in controlled by or so, to equipment few
the system. PLC remove scum such as cases, media
Hence only. The that aerators, discs
very low process accumulates at blowers, pumps have been seen
maintenance. requires very the etc. to be
Therefore the high level of top surface. Because of buckled under
manpower cost is instrumentation This is a shock biomass
low. All the & major loadings, weight, needing
components of sequencing operation, filamentous complete
the operation. The needing growth takes replacement.
system are entire to take the place and
indigenous & are instrumentation UASB out of makes the
readily available. & control service. sludge
Media for FAB equipment are Maintenance of particles to float
never needs usually other related in
replacement of imported. equipments secondary
cleaning. Media The entire plant in the clarifier.
life performance downstream Once formed, it
of more than 25 depends on ASP is is
years can be functioning of all also required. difficult to
guaranteed. the remove such
instruments & growth, making
sequence of operation more
operation. operator
Needs spares of dependent.
all the
imported
instruments in
stock for
repairing /
replacing so
that the
plant is in
operation within
a short
period.
Availability of
spares needs
to be checked.
The decanter
mechanism is
motorized and
hence high
degree of
maintenance
is required.
Spares must be
imported, Indian
spares are not
suitable.
Excess The excess Excess sludge Excess sludge Excess sludge Not much
sludge sludge must be must be must be control
control wasting is from removed removed with removed with required, since
secondary with manual manual manual sludge is
clarifier, intervention. intervention. intervention. not recycled
which is like any Any Any higher Any higher back to
other ASP higher withdrawal will withdrawal will aeration
system withdrawal will result in result in system.
and hence result in UASB operating ASP operating Sloughing is
simple. SBR operating at lower at lower automatic
No sludge at lower efficiency. efficiency. hence manual
recycle efficiency. intervention is
hence extent of Hence control of not
wastage does not process required.
affect becomes
performance. very sensitive
and instrument
dependent.
Power shut Prolonged power At power shut The At power shut Power failure
downs shutdowns does down, all the downstream down, all causes
not affect sludge ASP the sludge serious process
performance settles down process is settles down problems since
since and becomes severely and becomes top half
after power cut- septic affected during septic of the disc
off, within short power within short remains in
media floats at span of time. shut-downs. span of air, and
the Hence UASB itself time. Hence becomes dry.
top, keeping the quick restart is has little effect. quick The submerged
micro-organisms, not possible. restart is not portion
alive possible. remains in
sewage and
becomes
septic, hence
quick restart is
not
possible.
Sludge Sludge is fully Sludge is active Sludge is active Sludge is mostly Sludge is
properties digested hence hence and must digested and mostly
can anaerobic be further does not digested and
be dewatered (or aerobic) digested need further does not
directly without digester is a aerobically. treatment, need further
any must, for Because of similar to MBBR treatment,
further treatment complete presence of system. similar to MBBR
destruction of SRB, sludge Dewatering is system.
biomass. can smell very relatively easier. Dewatering is
This increases bad (rotten relatively
plant cost and egg smell). easier.
operator
attention.
Amount of Sludge age is Sludge age is Excess sludge Excess sludge Excess sludge
excess very low hence production production is production is
sludge high, and hence sludge of UASB itself is low, since low, since
sludge production production is low, Mean Cell Mean Cell
is about 0.1 – about 0.3 – 0.6 lower than most Residence Residence
0.15 kg / of the Time is high. Time is high.
kg / kg of BOD kg BOD processes.
destroyed, hence destroyed. However
very small Which means downstream
amount that the amount ASP sludge
of excess sludge of excess production is
is sludge high.
generated. generated is
about 200 to
400%
higher than
MBBR. This
calls for
large sludge
handling
system.
Expandability High. Higher Very low. Higher Very low. Low. Usually Low. Multiple
loads loads can not Overloading is extended modules
can be accepted be not possible. aeration need to be
with extra media accepted. Parallel units systems are installed.
filling. Modular However, must be added not suitable for Expansion
construction is Modular to expand expansion. within
possible. construction is capacity. Separate existing system
possible. parallel tanks is not
and possible.
clarifiers must
be built,
which can be
very
expensive.
Usage of No further Treated effluent Treated effluent Treated effluent Treated effluent
treated treatment "as-such" can "as-such" "assuch" "assuch"
effluent required be can not be used can not be used can not be used
for gardening & used for low for even for even low end for even low
horticulture. end purposes low end purposes such end
such as purposes such as purposes such
construction, as construction, as
floor washing construction, floor construction,
etc. floor washing etc. floor
For gardening washing etc. Tertiary washing etc.
or higher end Secondary treatment must Tertiary
uses, treatment in be treatment must
chlorination and form of ASP., provided even be
filtration are a followed by for low provided even
must. tertiary end uses. for low
treatment must end uses.
be
provided even
for low end
uses.
"SIZE-WISE" Suitable for any Suitable for any Suitable for any Suitable for any Suitable only for
suitability of size, no size, no size, no size, small
the process limitation. limitation. limitation. no limitation. sizes. Larger
Larger sizes Larger sizes Larger sizes
demand much demand much sizes demand demand much
higher higher much higher
space. space. higher space. space, and also
much
higher
maintenance.
1 Space (Sqm/ Avg. DWF 600 - 800 500 - 700 500 - 600
MLD) (say)
2 Capital Cost (Rs./ MLD) 65 50 70
3 Material of Construction open units o open units pen stainless steel
units container
7 Additions