Precast Concrete Floor Slabs
Precast Concrete Floor Slabs
Precast Concrete Floor Slabs
1
INTRODUCTION
Part one of this booklet is intended as a quick
and general guide to precast concrete floor
slabs. In this book we will cover the features
and benefits of precast concrete floor slabs,
the general applications, some design
guidelines, on-site considerations and some
general information. Part two contains the
more technical information.
For more detailed information specifically
regarding design, you are referred to the
“Precast concrete floor slabs-design manual”
also published by the Concrete
Manufacturers Association.
2
PART ONE
1. FEATURES AND
BENEFITS
Figure 1: Erection of hollow core slabs
3
2. APPLICATIONS
All flooring applications can be executed us- The panel and topping and beam and block
ing precast components, from domestic solution is particularly useful if the building
housing to bridge decks. However, each sys- is irregular or has multiple cantilevers.
tem has its own specific area of usefulness,
where its advantages are best utilized. Sites where craneage is not possible lend
themselves to a beam and block solution,
For floors in buildings of cellular construc- though the narrow hollow core might be pos-
tion, up to four storeys, if speed and absence sible with short spans.
of propping are paramount, then hollow core
slabs with finished soffits are probably the
best choice.
4
Figure 4: Beam and block slab on irregular-shaped building
Building Types
Housing
Educational
Offices & Commercial
Industrial
Warehouses
Hospitals
Roofs
Car parks
Suspended ground slabs (heaving clays)
Hotels
5
3. PRICING
COMPARISON FOR
DIFFERENT SLABS
Precast slab systems have a number of
advantages over conventional cast in situ
concrete. Table 2 summarises areas where
costs are generated on site for a particular
item. Naturally the most important cost
saving is that of time. The use of precast
concrete allows for immediate access to the
floor below.
* Item needs pricing.** Price normally includes supply and erection. (*) This item may need pricing
6
PART TWO
4. QUALITY
In a controlled factory environment, quality casting-bed. Materials from suppliers are con-
checks are not only much easier to do, but also stantly monitored.
much easier to control, with the result that the
product may be expected to be of a more uni- Checks are carried out on a regular basis on
form or consistent standard. Cubes are taken all weigh batchers, prestressing jacks and cube
from concrete mixes on a daily basis and on crushing equipment.
prestress lines it is normal to take cubes from
each line and check for transfer strength be- Where dimensional accuracy is important,
fore release of prestress. Some manufacturers checks of "as built" site dimensions are
cure the cubes on the line with the precast performed. This applies to hollow core slabs.
units. After release or de-moulding the re- Quality control is easier to maintain in a
maining cubes are transferred to a normal cur- factory environment than on a site, so that the
ing tank. product will be of a more consistent standard
and perform more uniformly.
Records of concrete strengths are kept so that
any possible future problem can be traced back
to a particular casting. Units are regularly in-
spected as they are demoulded or lifted off the
7
5. SYSTEMS
AVAILABLE
There are three basic systems available in compared with a solid slab of the same depth.
South Africa For most applications, no propping is neces-
* Hollow core sary during construction, but crane access is
* Beam and block essential. An erection rate of up to 600 m² per
* Panel and topping day is possible.
8
Figure 10:
Manufacturing
hollow core slabs.
The wide units need a crane for erection, but prestressing force opposes the tendency to
spans up to 5 m (depending on the loading) downward deflection and causes an upward
do not necessarily need structural topping or camber in the units under no-load conditions.
temporary propping, although a levelling Hence, together with the high-strength con-
screed is required. Structural topping and tem- crete employed, larger span/depth ratios can
porary props are sometimes employed to in- be achieved than with reinforced concrete. In
crease the effective depth used in the design lightly loaded roof slabs, for instance, span/
calculation. depth ratios around 50 are not uncommon.
Prestressed hollow core slabs are manufac- Limited cantilever capacity to resist negative
tured in units 1200 mm wide with depths of moments may be achieved in slipformed (or
120,150, 200 and 250 mm. Units are made to extruded) slabs by opening the tops of a
order in lengths up to 12 m. The number and number of cores for the required length, in-
disposition of prestressing tendons varies ac- serting the reinforcement and filling with con-
cording to span and loading. crete. This is normally done immediately after
casting. Because the prestress force tends to
Occasionally, structural topping is applied to increase the cantilever moment and deflection,
increase the effective depth for superimposed cantilevers are generally limited to seven times
loads. Propping is not generally specified the overall depth of slab.
except when the slab is required to act
compositely with the structure above, eg.
where heavy walls are carried on the edge of
the slab.
b) Design guidelines
Reinforced hollow core slabs are designed
as simply supported ribbed slabs in the con-
ventional manner. However they are more
versatile than the prestressed slab, since lon-
gitudinal top reinforcement can be cast-in for
cantilever action.
9
Figure 12: Prestressed hollow core used as a suspended ground floor slab
c) Service holes
Small holes (up to the core width) can be to 400 mm wide (in the slab centre) or 250 mm
made on site in the core area of the slabs. wide (at the slab edge) can be accommodated
Holes should be formed from the underside easily without the need to add trimming steel.
of the slab to prevent spalling of soffit con- Cut-outs at the end of a slab may often be
crete. Larger holes, requiring ribs to be cut, wider. Very large holes for rooflights or stairs
can be formed during manufacture, depending can be accommodated at the design stage. In
on the system and the size and position of the this case the slabs interrupted by the hole are
hole. If holes need to be formed on site and supported by a steel bracket supplied by the
reinforcement needs to be cut, this must be manufacturer and carried to the edge of adja-
referred to the manufacturer, preferably at the cent units. This should always be shown on
design stage. In the wide slab systems, holes up the manufacturer's working drawings.
10
Figure 14: Hollow core slab for an hotel
d) Finishes
Hollow core slabs cast on steel soffits are suit- the finishing screed or topping over all joints.
able for decoration direct. The joints are fea- The same applies in any situation where ce-
tured unless the whole surface is plastered ramic tiles are to be used. Regular expansion
with a thin-coat plaster. Before plastering, a joints must be allowed for large areas (greater
bonding agent should be applied to the slab than 20 m² of ceramic tiles). As with all con-
surface and a light mesh must be placed in the crete roofs, the finished roof surface should
levelling screed on top of the slab. be lightcoloured and reflective, with thermal
insulation provided to reduce slab movement
Whenever hollow core slabs are used on an (eg a layer of coarse aggregate on top of the
exposed balcony or walkway, or on a roof, a light waterproofing membrane or a foam concrete
mesh reinforcement should be incorporated in finishing screed).
11
Figure 16: Hollow core slab on steel frame. Note omission of purlins for crane access.
Figure 17: Hollow core slabs used on seating areas of the Wanderers grandstand.
12
Levelling screed
External walls can be Holes for
250 mm deep slabs only required to
built immediately after downlights can
can be used for finish.
slab erection. be cut on site.
in the
staircases or skylight factory.
openings.
mately 1,5 m centres, but certain systems can
5.2 Beam and block also be designed to eliminate the need for
a) Description props.
Beam and block slabs are made up of precast The advantages of this type of slab are as fol-
concrete rectangular shaped beams. The most lows:
common beam spacings being 560, 600 and
650 mm. A non-structural hollow concrete
It provides an economical, versatile light-
weight monolithic slab system. Compo-
rebated filler block is placed between these
nents are relatively light and no mechani-
beams. The size of the block determines the
cal handling is necessary.
beam spacing and provides a flush soffit.
old pic
Figure 20: Prestressed beams in place with support. Figure 21: The soffit of a beam and block slab.
14
Typical construction details for beam and block slabs.
Double
Concrete hollow
beams
blocks for thermal
under
and acoustic
concentrated Rectangular
insulation provide
loads. concrete
permanent shuttering
beam.
for slab.
Beams stacked on
bearers vertically
aligned and placed at Bearing
less than 200 mm 35mm minimum or
from ends. use tie bars
15
Figure 22: Placing blocks into position.
c) Service holes
Holes can be made on site in the blocks be- Figure 23: Fixing of services.
tween beams to accommodate horizontal
services. For larger holes, whole blocks can be
omitted with shuttering fixed to adjacent
blocks to restrain the concrete topping at the
time of pouring. Holes larger than a single
block must be referred to the manufacturer
for approval, preferably at the initial design
stage.
d) Finishes
Beam and block floors have a good key on the Figure 24: Casting concrete topping to beam and
soffit for plastering. block slabs.
16
6. DESIGN GUIDELINES
FOR PRECAST SLABS
This is intended as a quick guide only and will be found that properly anchored links are
should detailed information be required it can required. Where the loading is very light or
be obtained by consulting the precast con- independent test evidence can be provided,
crete floor slabs1 design manual published projecting steel will not be required.
by the Concrete Manufacturers Association or
by approaching individual manufacturers. b) Punching shear
This may be a problem if there is an inad-
All suppliers provide a full design service for equate depth of structural concrete over wide
their products. If necessary “Engineer certifi- hollow cores or hollow blocks. A screed may
cates” can be supplied for submission to mu- be assumed to assist in load dispersion to the
nicipalities to obtain approval for submission loadbearing ribs.
of plan.
c) Bearings
Areas which require particular attention are: Simple bearings should comply with the
requirements of SABS 0100-1 2. The
a) Shear stress at interface maximum possible bearing area should be
Where a structural concrete topping is in- provided. Factors influencing bearing design
tended to act compositely with a precast ele- include bearing area, bearing material, the
ment, the horizontal shear stress at the inter- presence of continuity steel, site tolerances and
face needs to be checked. Where the contact severe loading conditions.
area is small compared to the flange width, it
Figure 26: Preparing and casting of a precast beam and block slab in progress.
17
7. COMPOSITE The term “composite” refers to structures
where precast concrete and in situ concrete
18
8. SUPPORT OVER
OPENINGS IN
LOAD BEARING
WALLS
Hollow core slabs require support over
openings. The amount of support will depend
on the width of the opening and the span of
the slabs. As a rule of thumb, two lintels plus
five courses of masonry above are sufficient
to support hollow core slabs over an opening
up to two metres wide. For openings larger
than two metres, some form of structural
steelwork will normally be required. Flooring
suppliers will be able to advise on the necessary
support requirements.
Beam and block systems may, in most slab soffit, if there is adequate topping depth
circumstances, be viewed in the same way or an in situ beam may be incorporated in the
as in situ construction. Thus window slab depth.
openings, etc., may be taken right up to the
19
9. ON SITE Access
The client must provide suitable access for
20
Stripping
9.2 Beam and block Temporary propping may be removed when
the in situ concrete has reached a crushing
slabs strength of 17 MPa, or according to supervis-
Handling Protection and Storage ing Engineers instructions.
On delivery it is the contractor’s responsibil-
ity to inspect the blocks and beams for any Note: No heaping of building materials on
breakages. Material should be off-loaded in a slab during construction.
safe place and on level ground. The blocks are
not to be placed on top of the beams during
storing. Do not stack the blocks more than two
pallets high. Beams must be supported at 1,5 m
centres.
Placing
Place beams from setting out point as indi-
cated on the drawing at approximate centres.
Figure 36: Setting out of beams.
Space accurately by placing one closed- end
hollow block at each end of span. In accord-
ance with SABS 0100, minimum bearing of
35mm onto load bearing masonry.
Inspection
Before placing any concrete all slabs are to be
inspected by the supervising engineer or ap-
Figure 38: Mesh placed over blocks.
pointed representative.
Concreting
Use a minimum 25 MPa strength concrete
at 28 days as the structural topping. Casting
must be continuous to create monolithic slab.
Heaping of concrete must be avoided. Con-
crete is to be mechanically vibrated.
Curing
Keep slab wet for 3 to 4 days after concreting.
Figure 39: Casting concrete.
21
10. CONSTRUCTION
REQUIREMENTS
10.1 Hollow core slabs
The following details are recommended for ment or control joints should be placed in the
use with hollow core precast concrete floor tiles every 5 metres maximum and at points
slabs. where the tile cross section changes.
22
Roof level NB A 110mm wide parapet wall is recom-
Waterproofing
mended, but a 230mm wide parapet wall can
taken over parapet
Screed to falls be used on the height of the parapet wall.
10mm thick
Ref 100 mesh
jointex
Hollow core slab
Waterproofing
taken over parapet
Load bearing wall Screed to falls
End of slab at roof level - 10mm thick
Ref 100 mesh
230mm wide parapet wall. jointex
Hollow core slab
230 Waterproofing
Wall taken over parapet
Screed to falls
End of slab at roof level.
-110mm wide parapet wall. 10mm thick Ref 100 mesh
jointex Hollow core slab
23
Joints on internal wall
Where two slabs rest on a 230 wall, two details where a wall is to be placed at first floor level
are available. With the first detail a joint should above the wall below or where the floor is to
be formed in the screed at the point where be carpeted.
the two slabs join. This detail is normally used
Levelling screed
Joint in screed
Hollow core slab
V-joint in plaster
230
Wall
V-joint in plaster
230
Wall
Balcony
At balconies or walkways a step in the slab should lower than the inner slab. The direction of span
be provided to prevent water penetration. This of the slabs may vary to that shown to suit the
is achieved by placing the outer slab one course position of the loadbearing walls.
Waterproofing
V-joint in plaster
230
Wall
24
Cantilevers
For a short cantilever up to seven times the depth rebar can be placed in a structural con-
slab depth, rebar can be cast into the cores. crete topping applied to the top of the hollow
For cantilevers larger than seven times the slab core slabs.
Levelling screed
Cantilever rebar to Engineers spec. cast in Hollow core slab
cores of hollow core slab by manufacturer.
Cantilever
V-joint in plaster
up to seven times
depth of slab
230
Wall
Cantilever rebar to Engineers spec. in topping
Structural topping Hollow core slab
2 layers
V-joint in plaster Malthoid
100 mm bearing
Levelling screed
10 mm thick jointex
230
Wall 25
140mm Masonry
NB: Great care must be taken when erecting Rule joints in the plaster at the top and bot-
floor slabs on 140 masonry as available toler- tom of slabs. To locate the ruled line posi-
ances are a lot smaller than when using 230 tions correctly, place a nail between the
masonry. Some useful tips on the use of slabs bottom of the slab and the top of the ma-
on 140 masonry are: sonry prior to plastering.
All buildings must be site measured and No horizontal chasing or DB boards shall
slabs manufactured to suit as built dimen- be built into structural walls supporting
sions. slabs.
Levelling screed
140
Wall
Levelling screed
140
Wall
26
Waterproofing taken Screed to falls
over parapet
Building paper
backing Ref 100 mesh
Hollow core slab
Ruled lines in
plaster filled with
silicone bead
Dry packed
concrete
Chicken
mesh 2 layers V-joint in plaster
Malthoid
120mm min Waterproofing taken
bearing over parapet Screed to falls
140
Wall
10mm thick
End of slab at roof level on jointex Ref 100 mesh
loadbearing wall Hollow core slab
Ruled lines in
plaster filled
with silicone
bead
Chicken
2 layers
mesh V-joint in plaster
Malthoid
Overlap varies
(100-140mm or 10-40mm)
140
wall
Side of slab at roof level on a
non-loadbearing wall.
Common bearing on same wall
at different heights.
Levelling screed
10mm thick jointex
2 layers Malthoid
V-joint in plaster
120mm bearing minimum
Levelling screed
2 layers Malthoid
V-joint in plaster
27
Levelling screed Levelling screed
V-joint in plaster
Jointex fill
V-joint in plaster
Structural steel
Slabs simply supported on top of steel section.
Levelling screed Hollow core slab
Joint in screed
75 min
bearing
Tops of cores No 2,5 & 8 opened up on Levelling screed
top for 600mm tie steel and in situ concrete
placed in open cores & joints. Hollow core slab
75 min
bearing
Shear stud
75 min
bearing
28
10.2 Beam and Block Slabs
180
2 Y10 bottom
min
Stiffener rib
Temporary support
by contractor
Beam reinforcement
to engineer’s details
Tie bar to
Strip beam engineer’s details
Beam reinforcement
to engineer’s details
Tie bar to
Upstand beam engineer’s details
Tie bar to
engineer’s details
Downstand beam
29
Tie bar to
engineer’s details
Temporary support
Span direction change by contractor
2 Y10 bottom
(Stiffener rib)
Beam reinforcement
to engineer’s details
Downstand beam
Top reinforcing
steel to engineer’s Weather step
spec
Anti-crack
weld mesh DPC on top of slab
V-joint in
external plaster
Precast beam
Approved
stretch paint V-joint in plaster Brickforce in
every course
Hollow block Slip joint above door/
2 layers DPC window height
or 2 ply Malthoid
Standard slab detail for load
bearing walls
30
Blocks for services
(conduits and piping)
Maximum of one
25 O conduit per
prestressed beam
Slab detail for services
V-joint in
external plaster
Brickforce in
every course
above door/
Roof slab parapet wall detail window height
31
11.REFERENCES: 12. FURTHER
1. Concrete Manufacturers Association,
Precast concrete floor slabs: design manual, READING:
Randburg: The Association, 1996. 1. Federation Internationale de la
Precontrainte, Precast prestressed hollow
2. SABS 0100-1:1992, Code of practice for core floors, London: Telford, 1988. (FIP rec-
the structural use of concrete. Part I : Design, ommendations).
Pretoria: South African Bureau of Standards,
1992. 2. Federation Internationale de la
Precontrainte, Principles for hollow core
3. SABS 0400:1990, Code of practice for the slabs, London: Telford, 1982. (FIP technical
application of the National Building Regula- report).
tions, Pretoria: South African Bureau of Stand-
ards, 1990. 3. Federation Internationale de la
Precontrainte, Quality assurance for hollow
4. National Building Regulations and core slabs floors, London: Telford, 1992. (FIP
Standards Act, Pretoria: Government guide to good practice).
Printer, 1977. (Act No 103 of 1977).
4. National Precast Concrete Association
5. SABS 0160: 1989, Code of practice for the of Australia, Hollow core floor: technical
general procedures and loadings to be adopted manual, North Sydney, The Association, 1992.
in the design of buildings, Pretoria: South Af-
rican Bureau of Standards, 1989.
32
AVAILABILITY OF THE VARIOUS SYSTEMS
Member Telephone Beam and Hollow core Panel Stairs
Number block Reinforced Prestressed Slabs
Grinaker
Precast (KZN) (031) 564-1304 *
33
CONCRETE MANUFACTURERS ASSOCIATION - MEMBERSHIP LIST
Other Producer Members
Company Name Telephone Product
Bafokeng Brick & Tile (014) 538-0842 MP
Bamburi Special Products Ltd (09254) 2530504 P
* Brickcast Industries cc (031) 507-7094 P
Cape Brick cc (021) 511-2006 M
CEL (021) 905-5998 P
*Columbia DCM (Pty) Ltd (021) 946-3290 M
*Concor Technicrete (Pty) Ltd (011) 495-2200 MPRT
*Corobrik (Pty) Ltd (031) 560-3911 MPR
*Coverland Roof Tiles (016) 421-4106 T
*Craig Concrete Products (Pty) Ltd (011) 914-1730 T
DBL Concrete Products (021) 905-1665 M
Eureka Brick & Block (021) 887-4692 M
Fairmile Homes (Pty) Ltd (021) 904-1620 M
False Bay Bricks (021) 904-1620 P
Fanie Visser Concrete (021) 904-1620 M
*Grinaker Precast (Pty) Ltd (012) 652-0000 MPR
*Inca Masonry Products (Pty) Ltd (043) 745-1215 MPRT
Klapmuts Concrete (Pty) Ltd (021) 875-5151 R
*Lategan’s Cement Works (021) 873-1154 M
*Marley Roofing (011) 316-2121 T
*Mimosa Brick (Pty) Ltd (0163) 620507 P
*Morula Brick & Sand (Pty) Ltd (012) 549-1727 M
Precast Concrete Industries (09264) 61-280-4103 MP
*Stanger Brick & Tile (Pty) Ltd (032) 4570237 MP
* Vanstone (012) 5412056 PR
*Vibro Bricks (Pty) Ltd (012) 374-2032 P
*Watson Tile & Concrete (Pty) Ltd (011) 740-0910 MRT
Zimtile (Pvt) Limited (09263) 4663511/5 T
34
Deranco (041) 463-3338