Implementation Work Plan

The document outlines a Dynamics 365 Business Central implementation project scheduled from January 18th to March 1st. It includes planning, development, testing, training, and migration activities. Systems analysis and requirements documentation will be completed from January 18th to 24th. Development and customization will take place from January 25th to February 10th. User training will occur from February 14th to 22nd before data migration from February 23rd to 25th and the final system go-live on March 1st. Key resources include AC for requirements, training, and analysis and DC and DC2 for development and customization.

Uploaded by

Ruyonga Richard
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views1 page

Implementation Work Plan

The document outlines a Dynamics 365 Business Central implementation project scheduled from January 18th to March 1st. It includes planning, development, testing, training, and migration activities. Systems analysis and requirements documentation will be completed from January 18th to 24th. Development and customization will take place from January 25th to February 10th. User training will occur from February 14th to 22nd before data migration from February 23rd to 25th and the final system go-live on March 1st. Key resources include AC for requirements, training, and analysis and DC and DC2 for development and customization.

Uploaded by

Ruyonga Richard
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Start Date End Date Resource

Task Name Duration


Names
1 Dynamics 365 Business Central Implementation 18/01/2022 01/03/2022
32.5 days
Plan
1.1 Systems Analysis 6 days 18/01/2022 24/01/2022
• Financial Management (Includes General 18/01/2022 18/01/2022
Ledger, Bank Reconciliation, Budgeting,
Currencies, Dimensions (Projects, 1 day AC
Departments)

• Sales & Receivables 19/01/2022 19/01/2022


• Purchases and Payables (includes Accounts 1 Day AC
Payable)

• Project Management 20/01/2022 20/01/2022


• Fixed Assets Management 1 day

• Human Resources and self Service 21/01/2022 21/01/2022


• Payroll Management
• Reports 1 day AC
• System Security

Prepare Functional Requirements Document 22/01/2022 24/01/2022


3 Days AC
(FRD)
1.2 Development 18 days 25/01/2022 11/02/2022
Prepare Technical Design Document (TDD) 2 Days 25/01/2022 26/01/2022 DC
1.2.1 Development & Customization 16 days
Create development build plan 4 hrs. 26/01/2022 26/01/2022 DC
Setup development environment 2 hrs. 26/01/2022 26/01/2022 TC
Customization Budget 15 days 27/01/2022 10/02/2022 DC,DC2
Development Reviews 2 Hours 10/02/2022 10/02/2022 PM,DC
1.3 Testing System 4 hours 11/02/2022 11/02/2022
1.4 Conference Room Pilot 4 hours 11/02/2022 11/02/2022
1.5 User Training 5.5 days 14/02/2022 22/02/2022
Training Preparation: (Training plan, materials) 1 hr. 14/02/2022 14/02/2022 AC
General Ledger Including Budgets and Dimensions 1 day 15/02/2022 15/02/2022 AC
Cash Management 0.5 days 16/02/2022 16/02/2022 AC
Purchases and Payables 0.5 days 16/02/2022 16/02/2022 AC
Receivables 0.5 days 17/02/2022 17/02/2022 AC
Fixed Assets 0.5 days 17/02/2022 17/02/2022 AC
Human Resources and Payroll 1 day 18/02/2022 18/02/2022 AC
General Administration, Audit Trails, Security, 21/02/2022 21/02/2022
0.5 days AC
Archiving and Backups
Analysis and Reporting 1 day 22/02/2022 22/02/2022 AC
1.6 Data Migration 3 Days 23/02/2022 25/02/2022
1.7 System Go- live 1 days 01/03/2022 01/03/2022