Distribution System Planning With Distributed Thermal and Wind Generation
Distribution System Planning With Distributed Thermal and Wind Generation
Abstract—This paper presents a new approach for distribution optimization approaches known as heuristic techniques have
systems planning with thermal and wind distributed generation been developed. Among this sort of methods, there are genetic
(DG). This approach determines the optimal placement of bio- algorithm [6], [7], evolutionary programming [8], differential
mass-based thermal and wind distributed generation aiming at evolution [9] and particle swarm optimization (PSO) [10].
minimizing the energy loss, emissions and the total investment
and operation costs, as well as improving the voltage regulation. Reference [11] proposes a PSO-based approach for optim-
The costs for the purchased energy from grid and thermal gen- al allocation of renewable DGs including wind power incorpo-
eration based on biomass resource are considered. The wind rating the DG reactive capability. PSO is also used in [12] to
power is given by pre-established nominal power and capacity select the proper installation sites for wind turbines consider-
factor. To solve the mixed integer nonlinear problem, a genetic ing pre-specified range for the power output and power factor,
algorithm (GA) with embedded optimal power flow (OPF) tool and in [13] to place the DG at optimal location with optimal
is proposed. The OPF is used to determine the size of the ther- size and unity power factor. In [14] and [15], genetic algo-
mal generators. Results are presented for well-known systems rithm and PSO are applied to define the optimal size of wind
from literature. turbines taking into account the investment costs.
Index Terms—biomass-based power, distributed generation, Genetic algorithms have recently been proposed for DG
genetic algorithm, wind power. placement in [6], [16]. According to [5], the choice of the ob-
jectives related with DG planning impacts the placement of
I. INTRODUCTION the distributed resources and the rule for this issue is still an
open question.
The penetration of distributed generation in power distri-
bution systems has been increased due to some aspects as a Following the lines of research on the aforementioned
response to the growing load demand. Moreover, other aspects question, the present paper proposes an approach for optimal
have been contributed to the distributed generation capability allocation of distributed generation based on thermal and wind
as the deregulation of power systems, technological advances power, considering biomass resources for the thermal power.
that lead to small generating units with high efficiency and This approach combines a genetic algorithm to place the DG
system loss reduction [1]-[4]. The economical and environ- with an optimal power flow [17] tool for sizing the thermal
mental constraints over the construction of new transmission units. The size and capacity factors of the wind generators are
lines for long distance power delivery also favor the spread of pre-specified values. The objectives are to minimize the net-
DG. The environmental benefits increase when the DG uses work energy losses, emissions and the total investment and
renewable resources, as the biomass and wind power. operation costs, while improving the system voltage regula-
tion. The cost for purchased energy from grid is included in
The potential advantages of DG depend on its proper the total operation cost. Two radial distribution test systems of
placement in the distribution system [1], [5]. If non-optimal 33 and 69 nodes are used for presenting the results.
placements are chosen for the DG penetration, these advan-
tages can be low, null, or the DG can even negatively affect II. PROPOSED MODELING
the system. As example, the DG can increase the system
losses if it is not optimally placed [5]. The optimization problem for optimal distribution systems
planning aims at minimizing the energy loss, emissions and
If the distribution system planning considers the possibility the total investment and operation costs, while improving the
of installation of multiple DGs, the optimal placement be- voltage levels subjected to the network constraints. The objec-
comes a mixed integer, nonlinear and non-convex optimiza- tive function of the problem is based on [11] and formulated
tion problem [1]. To solve this kind of problem, a class of as
Where NTh and NWd are the number of thermal and wind Vfb, Vtb ≥ Vmin , (11)
generators, respectively; cth and cwd are the cost factors
($/kVA) for calculating capital costs for thermal and wind xth,k + xwd,k < 2 , (12)
generator, respectively; Sth and Swd are the installed capacity
(kVA) of thermal and wind generator, respectively; OCth and NTh + NWd ≤ NDGmax . (13)
OCwd are the operation costs ($) for thermal and wind genera-
tion, respectively; Lpl is the total active power loss (kW) and Where xth,k and xwd,k are integer values associated with the
cpl is the respective cost ($/kWh); T is the total hours of opera- decisions of thermal and wind generation, respectively, at
tion; cgr is the cost factor ($/kWh) for the purchased energy busbar k (‘0’ for no allocation and ‘1’ for allocation); Pth,k and
from grid and Pgr is the respective power (kW); cem is the cost Pwd,k are the active power outputs (kW) of the thermal and
factor ($/kg) for emissions and egr is the emission factor wind generator at busbar k, respectively; Qth,k and Qwd,k are the
(kg/kWh) associated with Pgr. reactive power outputs (kVAr) at busbar k from thermal and
The operation and maintenance cost for wind generation wind generators, respectively; PLk and QLk are the active
(OCwd) is given by cow·T·Pwd, where cow is the cost factor (kW) and reactive (kVAr) power loads at busbar k, respective-
($/kW) and Pwd is the active power output (kW) of the wind ly; Ωk is the set of busbars directly connected to busbar k; Pkm
generator. The operation cost for thermal generation compris- and Qkm are the active (kW) and reactive (kVAr) power flows,
es a term associated with the operation and maintenance, respectively, through the branch that connects busbars k and
which includes the fuel cost, and another term associated with m; cfwd is the capacity factor of wind-based DG units; pfth and
emissions, as in pfwd are the power factors for thermal and wind-based DG
units, respectively; Sth,max is the maximum allowable thermal
DG capacity (kVA); Vmin is the lower limit for the system
OC th = cot ⋅ T ⋅ Pth + cem ⋅ efu ⋅ T ⋅ Pth . (2) voltage (V); NDGmax is the maximum number of DG units.
Equations (4) and (5) consist of the active and reactive
Where cot is the cost factor ($/kWh) for the biomass-based power balance constraints, respectively, defined for each bus-
thermal generation, Pth is the respective active power output bar of the network. The active power output of wind-based
(kW) and efu is the emission factor (kg/kWh) for the power DG units is given by their capacity factor and rated power as
supplied by biomass generators. in (6). The capacity factor for thermal generators is assumed to
The total active power loss (Lpl) is given by be 1. The reactive power outputs of DGs are obtained from the
respective active power outputs and operating power factors as
in (7) and (8). These power factors may need to be regulated
Nbr
as in (9) [11].
L pl = ∑ g b ⋅ ⎡⎣ Vfb2 + Vtb2 − 2 ⋅ Vfb ⋅ Vtb ⋅ cos ( θfb − θtb ) ⎤⎦ .(3)
b =1 The DG capacity at each busbar is limited by constraint
(10) due to land space and network constraints [11]. The con-
Where Nbr is the total number of branches; gb is the is the straint formulated in (11) ensure that all busbars have their
conductance of branch b; Vfb and Vtb are the voltage magni- voltages above a minimum value and the constraint in (12)
tudes at the end busbars of branch b; θfb and θtb are the phase means that a same busbar cannot receive thermal and wind
angles at the end busbars of branch b. generators considering the land space limit [11]. The con-
The objective function formulated in (1) is subjected to the straint in (13) limits the DG penetration and has to be planned
following constraints in advance at the planning stage [11]. It can be highlighted
that the voltage limit constraint leads to an improvement of the
system voltage regulation.
x th,k ⋅ Pth,k + x wd,k ⋅ Pwd,k − PL k + ∑P
m∈Ωk
km = 0, (4)
III. PROPOSED METHODOLOGY
The proposed methodology for power distribution systems
x th,k ⋅ Q th,k + x wd,k ⋅ Q wd,k − QL k + ∑ Q km = 0 , (5) planning with distributed thermal and wind generation embeds
m∈Ωk an optimal power flow in a genetic algorithm. The genetic
algorithm handles the combinatorial feature of the problem
Pwd,k = cf wd ⋅ Pwdr , (6) due to the integer variables (xth,k , xwd,k) associated with the
decisions about the placements of the distributed resources.
Q th,k = pf th ⋅ Pth,k , (7) Every element of the GA (chromosome) encodes a candi-
date siting solution in a vector (Ind) that has Nbc positions,
Q wd,k = pf wd ⋅ Pwd,k , (8) where Nbc is the number of busbars candidate for DG sites.
Each position of the vector (gene) can receive an integer value
from ‘0’ to ‘2’. Equation (14) gives the codification where bc
is a busbar candidate for DG placement.
⎧0, if there is no DG at bc
⎪
Ind( bc) = ⎨1, if there is a thermal DG at bc . (14)
⎪ 2, if there is a wind DG at bc
⎩
Analysis 1: In the first analysis, the capacity factor of From Tables I and II, it can be observed that in Analysis 1
wind-based DG units is 18.8%, which is considered as a rela- there was no allocation of thermal distributed generation, whe-
tive high factor for this kind of generation [11]. Also accord- reas Analysis 2 gave as result the placement of one biomass-
ing to [11], a maximum of two nodes can be selected for in- based thermal unit at busbar 28. This is due to the more severe
stallation of DG units (NDGmax = 2) and the power factor con- voltage constraint considered in Analysis 2 that requires more
straint is relaxed by setting its lower limit as zero. The voltage investment in DG. As the capacity factor of biomass-based
limit is 0.90 pu. Table I presents the results for this analysis, thermal units are greater than that of wind generators and only
including all the related costs and the minimum voltage, for two units can be placed, one thermal unit is placed in Analysis
the base case, where there is no allocation, and for the solution 2 despite their high costs in relation to the wind generation due
obtained by the proposed method. The difference between the to the higher amount of DG power required in Analysis 2. As
total costs is equal to $ 5,561,000.00 and the proposed model a result, the total cost of Analysis 2 is greater than the cost in
leads to a better voltage profile. This model also gives a lower Analysis 1. However, as the emission factor of biomass-based
emission cost. units is smaller than that of the energy from the grid, the total
emission cost of Analysis 2, given by the summation of the
respective costs for the grid and the biomass unit, is smaller
than the emission cost of Analysis 1. This result shows the
environmental benefits provided by the penetration of renew-
able energy sources in power systems.
Analysis 3: As stated in the previous analysis, the capacity TABLE IV. RESULTS FOR 69-BUS TEST SYSTEM – ANALYSIS 1
factor of DG units is a parameter that affects the DG planning. Method Base Case Proposed Method
Therefore, Analysis 3 considers a lower capacity factor for Allocation -- Busbars 60, 62 (wind)
wind generation, 5.0%, to further evaluate this aspect. The low Investiment cost for
-- 5.66e05
capacity factor is due to supposed poor wind resources. The wind unit ($)
other planning conditions are the same of Analysis 2. Table III Operation cost for
-- 6.92e05
wind unit ($)
presents the results for Analysis 3. Investiment cost for
-- --
biomass-based unit ($)
TABLE III. RESULTS FOR 33-BUS TEST SYSTEM – ANALYSIS 3 Operation cost for
-- --
biomass-based unit ($)
Method Proposed Method Grid energy cost ($) 6.24e07 5.76e07
Busbar 16 (biomass) Loss Cost ($) 3.49e06 2.68e06
Allocation
Busbar 31 (biomass) Grid emission cost ($) 1.91e07 1.76e07
Investiment cost for wind unit ($) -- Biomass unit emission
-- --
Operation cost for wind unit ($) -- cost ($)
Investiment cost for biomass-based unit ($) 5.04e06 Total cost ($) 8.50e07 7.90e07
Operation cost for biomass-based unit ($) 2.92e08 Minimum Voltage (V) 0.909 0.922
Grid energy cost ($) 3.14e07
Loss Cost ($) 6.47e05
Grid emission cost ($) 9.58e06 For this system, when the capacity factor is considered as
Biomass unit emission cost ($) 2.73e04 5.0% there is no allocation of biomass or wind-based genera-
Total cost ($) 3.39e08 tion because the investment in both kinds of DG is not attrac-
800 (busbar 16) tive for this condition due to the relative high costs of bio-
Capacity of biomass-based unit (kVA)
1400 (busbar 31)
Minimum Voltage (V) 0.979
mass-based generation and the low capacity factor of wind
power.
Analysis 2: This analysis considers a maximum of one dis-
As it can be observed from Table III, there was no alloca-
tributed generator to be placed and continuous values for dis-
tion of wind-based generators in Analysis 3 because their ca-
tributed power as in [1]. The maximum capacity of biomass-
pacity factors are low and the requirement for DG power is
based thermal unit is 2300 kVA, only thermal distributed gen-
high due to the severe voltage constraint, 0.95 pu.
eration can be placed, the power factor constraint is relaxed
B. 69-Bus Test System and the voltage limit is 0.95 pu. For this limit, the system can-
not operate without DG allocation. Reference [1] presents a
The 12.66 kV test system is from [20], has one substation case for this system in similar conditions, in which continuous
(SE), a total load of 3802 kW and the topology pictured in Fig. real and reactive power can be allocated independently of each
3 [1], [21]. other, which means that the power factor constraint is relaxed.
SE
Table V presents the results for this analysis. Although the
objective function in [1] is given only by the power loss, the
data of Table V allows comparing the solutions in terms of
each term of the objective function modeled in the present
paper, equation (1), as well as the power loss considered in
[1]. The investment, operation and emission costs for [1] were
calculated in the present work considering the DG based on
biomass resources for comparison purposes.