ISPE Boston Chapter Webinar: ISPE Baseline Guide Volume 5, 2nd Edition
ISPE Boston Chapter Webinar: ISPE Baseline Guide Volume 5, 2nd Edition
ISPE Boston Chapter Webinar: ISPE Baseline Guide Volume 5, 2nd Edition
Webinar
ISPE Baseline Guide
Volume 5, 2nd Edition
Chip Bennett
Assistant Director, Global C&Q
CAI
Webinar
05 March 2020
Chip Bennett, PMP
Assistant Director, Global C&Q, CAI
Contact:
A Project Manager and Senior Validation Engineer, Chip is a PMI® Certified Project Management Professional
(PMP) with 20 years of experience in the pharmaceutical and regulated non-pharmaceutical industries and with
expertise in risk-based verification, aseptic manufacturing, cleaning validation, quality systems, and owner project
management. Chip is responsible for developing and implementing Quality Risk Management (QRM) based
Commissioning and Qualification programs and projects, with a focus on assessing and training clients regarding
development, implementation, and transition to risk-based approaches.
Caveats:
I am not a CoP steering committee member or an author/contributor to
the Guide
This is not, and does not replace, the official CoP Presentation
About This Presentation:
More than just the content of the revised Guide
Historical context and evolution
Practical implementation based on project experience
Start-Up Time
Efficiency (%)
Efficiency (%)
Goal
0
Problems Time
Problems
NORMAL
Efficiency (%)
Goal
0 0
Problems Time Time
Problems
Problems
Problems
NORMAL DESIRED
CQV Benchmarking
QRM Incorporation
Science- and Risk-Based Approach
Focus on Quality by Design (QbD)
Incorporates Industry Standards
Other Benefits
Consistent, Compliant Approach
Efficient Approach
Risk-Based Lifecycle Approach
Defined: Retired:
Commissioning Indirect Impact
Qualification Component Criticality Assessment
Commissioning and Qualification (C&Q) V-Model
Validation Enhanced Documentation
Verification Enhanced Commissioning
Enhanced Design Review
Leveraging
Qualification
For the purpose of this guide, a process to demonstrate and document that the critical
manufacturing facilities, systems, utilities, and equipment are suitable for the intended purpose.
Commissioning For the purposes of this Guide, the term Commissioning and Qualification (C&Q) is used to
and Qualification describe the process for establishing that facilities, systems, utilities, and equipment are
(C&Q) suitable for their intended purpose.
Establishing documented evidence which provides a high degree of assurance that a specific
Validation process will consistently produce a product meeting its predetermined specifications and quality
attributes (FDA Process Validation Guidance, 1987)
Verification
An activity that is performed within the C&Q process to document that the manufacturing
facilities, systems, utilities, and equipment are suitable for the intended purpose.
Defined: Retired:
Commissioning Indirect Impact
Qualification Component Criticality Assessment
Commissioning and Qualification (C&Q) V-Model
Validation Enhanced Documentation
Verification Enhanced Commissioning
Enhanced Design Review
Leveraging
Engineering
Role: system delivery
Focus: system fitness for use
Responsibility: verification (testing and documentation)
Quality
Role: product quality
Focus: PPK, risk control strategy, system design, and verification
Responsibility: oversight (approval)
Step Mixing
Process
System Tank, Agitator
CQAs Potency
PPK Mixing Speed
CPPs
Mixing Time
Risk Failure Failure to control Mixing Speed. CQA impact: Incorrect Potency
Assessment Modes Failure to control Mixing Time. CQA impact: Incorrect Potency
Control, Monitoring, and Alarming of Mixing Speed
CAs
Control, Monitoring, and Alarming of Mixing Time
Risk Control
Agitator Speed Controller, Agitator Speed Indicator, Agitator Speed Alarm Sensor
CDEs
Timer, Time Indicator, Time Alarm Sensor
RTM
Traceability
RTM
Traceability
Explicitly define/specify
CQAs, CPPs
RTM
Traceability
RTM
Traceability
RTM
Traceability
RTM
Traceability
Design of CDEs
Design Satisfied Quality URs
Satisfies CAs
QbD: Verifies that CQA/CPP based risk controls
Risk
have been incorporated into the design
Control
QbD: Verifies that Critical Aspects acceptably Strategy
mitigate risk to product quality (CAs,
CDEs)
Identified
RTM
Traceability
RTM
Traceability
RTM
Traceability
RTM
Traceability
System
Installation andSatisfies
Operation of CDEs are fit for intended use
Critical
System Meets Specification for Quality URs
Aspects
(CA)
Chip Bennett
Assistant Director, Global C&Q
CAI
[email protected]
Supporting Processes
Supporting processes and
enablers for the QRM-
based integrated C&Q
process
ISPE Baseline Guide Volume 5, 2nd Ed
Q1 Does the system contain CAs/CDEs or perform functions that serve to meet one or more process requirements (CQAs) including
CPPs?
Q2 Does the system have direct contact with the product or process stream and does such contact have the potential to impact the
final product quality or pose a risk to the patient?
Q3 Does the system provide an excipient or produce an ingredient or solvent (e.g., WFI) and could the quality (and compliance with
the required specifications thereof) of this substance impact the final product quality or pose a risk to the patient?.
Q4 Is the system used in cleaning, sanitizing, or sterilizing, and could malfunction of the system result in failure to adequately clean,
sanitize, or sterilize such that a risk to the patient would result?
Q5 Is the system used in cleaning, sanitizing, or sterilizing, and could malfunction of the system result in failure to adequately clean,
sanitize, or sterilize such that a risk to the patient would result?
Q6 Does the system use, produce, process, or store data used to accept or reject product, CPPs, or electronic records subject to 21
CFR Part 11 [20] and EU GMP Vol. 4, Annex 11 [21] or the local equivalent?
Q7 Does the system provide container closure or product protection, the failure of which would pose a risk to the patient or
degradation of product quality?.
Q8 Does the system provide product identification information (e.g., lot number, expiration date, counterfeit prevention features)
without independent verification or is the system used to verify this information?