CFMS code SoR Ref Description Quantity Rate (Rs.) Unit
(Rs.)
Random Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using hard other than granite stones carted from approved quarry
including cost and conveyance of all materials like cement, screened sand, water, stones etc., from approved quarry, to site, including labour for
cutting stones to required size and shape, mixing, of cement, mortar, construction, curing etc.,and overheads & contractors profit complete for
finished item of work in foundation and basement. (APSS No. 601 & 615)
Unit = 1 cum
A.MATERIALS
Cement 59.40 Kgs 3680.00 1000 Kgs 218.59
MAT-00405 CSoR 1 Rough stone (OTG) 1.10 Cum 472.16 1 Cum 519.38
MAT-00029 CSoR 28 Fine aggregate(sand) 0.33 Cum 1022.37 1 Cum 337.38
B) LABOUR
LAB-00011 CSoR I -11 1st class mason 1.20 Nos. 585.00 1 Each 702.00
LAB-00120,
LAB-00121 CSoR III - 3,4 Mazdoor (unskilled) 2.00 Nos. 490.00 1 Each 980.00
Add for MAA @ 25% 0.25 1682.00 420.50
3177.85
Add water charges 0.01 3177.85 31.78
Rate per 1 cum 3209.63
Overheads&Contractors Profit @13.615% 0.13615 3209.63 436.99
Rate per 1 cum 3646.62
Say 3647