0% found this document useful (0 votes)
199 views2 pages

Tokenless Block Instrument - Single Line (Push Button Type) Maintenance Schedule New

This document outlines the periodicity schedules for maintenance and inspection of block instruments at railway stations. It lists 5 items to be checked for each block instrument type (PB1, PB2, PB3) and the frequency of checks by various roles. The new periodicity schedule increases inspection frequencies from quarterly or yearly to monthly or quarterly for technicians and sectional SSEs, with SSE(Signal) and in-charge engineers conducting checks half-yearly or yearly.

Uploaded by

Saurabh Moharir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
199 views2 pages

Tokenless Block Instrument - Single Line (Push Button Type) Maintenance Schedule New

This document outlines the periodicity schedules for maintenance and inspection of block instruments at railway stations. It lists 5 items to be checked for each block instrument type (PB1, PB2, PB3) and the frequency of checks by various roles. The new periodicity schedule increases inspection frequencies from quarterly or yearly to monthly or quarterly for technicians and sectional SSEs, with SSE(Signal) and in-charge engineers conducting checks half-yearly or yearly.

Uploaded by

Saurabh Moharir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Old Periodicity New Periodicity

Schedule Technicia Sectional SSE(Signal)/ Remark


Code Schedule
DSMG Incharge n SSE/JE(Signal Incharge:
SSE/SE (Signal):
1. Check that Block Instrument are free from mechanical
- Yearly Monthly Monthly Quarterly
damage/corrosion. Check tightness of all nuts/bolts.
2. Checking of Push Buttons, Indicators, relays, bell & buzzer. Half
Quarterly Monthly Monthly Quarterly
Yearly
PB1 3. Locking & sealing of all relays and counter. Monthly Quarterly Monthly Monthly Quarterly
4. All the relays are properly plugged in block & holding clips are
- - Monthly Monthly Quarterly New
intact and contacts are clean and free from pitting.
5. The telephone and telephone cord. Monthly Quarterly Monthly Monthly Quarterly
1. Checking the working of releasing of shunting key. - Yearly Quarterly Half Yearly
2. Measuring the line current and voltage. Half
Quarterly Quarterly Half Yearly
Yearly
3. Working of cancellation counter. - - Quarterly New
Half Yearly
PB2 4. Cross checking of Door lock keys & SM key of one instrument
- - Quarterly Half Yearly New
with other instrument.
5. Measuring the insulations between each individual insulated
- Yearly Quarterly Half Yearly
circuit and earth (shall not be < 10 M Ohm).
6. Measure the earth value. - - Quarterly New
Half Yearly
1. LSS cannot be taken OFF without line clear and is
automatically replaced to ON when train enters the Block - Yearly Half Yearly Yearly
section.
2. The Last Stop Signal at the sending station cannot be taken
‘OFF’ until the receiving station instrument is set to “Train
- Yearly Half Yearly Yearly
Coming From” condition and the sending station instrument
PB3 is sent to “Train Going To” condition.
3. The Line Clear can be granted only when reception signals
- Yearly Half Yearly Yearly
and the Last Stop Signal are proved at ‘ON’.
4. The opposing Last Stop Signals of the block section cannot be
- Yearly Half Yearly Yearly
taken ‘OFF’ at one and the same time.
5. The circuit for proving the arrival of a train is directional. - Yearly Half Yearly Yearly