SAP PM Enduser Manual
SAP PM Enduser Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Project Sarthak
Table of Content.
Last changed on: Last changed by: Version: Page:
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 1 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
1. Introduction
Introduction ............................................
..................................................................
............................................
..........................................
.................... 4
2. Getting Started ...........................................
.................................................................
............................................
......................................
................ 6
3. Master Data ............................................
..................................................................
............................................
........................................
.................. 18
3.1 Functional Location ..................................................................... .............................................. 18
3.2 Equipment ............................................................... ................................................................. .. 29
3.3 Equipment Bill of Material ................................................ ........................................................ 43
3.4 General maintenance Task
T ask lists .................................................................................................. 50
3.5 Work Permit
P ermit ............................................................ ................................................................. .. 59
3.6 Characteristic .......................................................................................... ................................... 67
3.7 Measuring Points ....................................................................................................................... 71
3.8 Work Center ............................................................ ................................................................. .. 80
3.9 Maintenance Planning ........................................................ ........................................................ 85
3.10 Maintenance Plan Scheduling ....................................................................................... ............. 92
4. Maintenance
Maintenance Processing
Processing ...........................................
.................................................................
.........................................
................... 102
4.1 Measuring documents ............................................................................. ................................. 102
4.2 Breakdown Maintenance Process: .................................... ....................................................... 123
4.3 Preventive Maintenance ................................................................................................ ........... 160
4.4 Regular Maintenance : ................................................................. ............................................ 203
4.5 Calibration Process: ................................................................................ ................................. 209
5. Plant Maintenance
Maintenance Information System ..........................................
..........................................................
................ 217
5.1 Standard Reports ................................................................................................ ...................... 217
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 2 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 3 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
1. Introduction
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 4 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Master data maintenance and transaction processes are explained with the help of
SAP screen Shots. This will help you in executing the same perfectly.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
2. Getting Started
LOG ON:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Sap R/3 systems are client systems. The client enables you to run
several business operations at the same time in one SAP R/3 system.
Client is, in organizational terms, an independent unit in the system.
Clients have their own data environment and therefore their own user
master and transaction data, assigned user master records and chart
off accounts and specific customizing parameters.
So that you log on to SAP R/3 system, you must have a master record
created for you for corresponding client. For reasons of access
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
protection, you must enter a password when you log onto the sap
system. The system does not display the password you enter.
SAP R/3 system is available in several languages. Use the language
input field to select the logon language for each session.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
cursor on a push button for a while the system displays a quick info text
that explains the push button function.
The Application Tool bar : shows which functions are available in the
current application.
A Tab page: provides a clearer overview of several information screens
Status bar: the status bar displays information on the current system
status, for example. Warning or error messages
Menu bar: the menus shown here depend on which application you are
working in.
Title bar : the title bar displays the functions that are available for the
user.
Checkboxes: checkboxes enable you to select several options
simultaneously within a group.
Radio Buttons: allow you to choose exactly one item form a selection.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Menu
Standard
Title bar
Command
Application
toolbar
Tab Page
Input Fields
Check
boxes,
Status
Sap easy access is the standard entry screen displayed after the logon.
You navigate through the system using the tree structure.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Selecting Functions
You can call functions in the system as follows
o Menu Option
o Favourites
o Entry in the SAP easy Access menu
“/n” ends the current session
“/i” delets the current session
“/oCV01N” opens a new session and branches out to the transaction
specified (CV01N)
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Command Field
Menu
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
F1 Help
Use F4 to display possible inputs . you can also access F4 help for a
selected field using the button immediately to the right of that field.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
F4 help
User – Specific Personalization
The end user has many possibilities for personalizing the system. For
example as shown in the screen below.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
SAP – Symbols or icons
Keyboard Keyboard
Button Description Button Description
Shortcut Shortcut
Save to
Ctrl + S Page Up Previous page
database
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Next page
F3 Back Page Down
Create New
F12 Cancel None session
Create shortcut
Ctrl + P Print None
on Desktop
F1 Help
Ctrl + F Find F1
Customize Local
Ctrl + G Find next Alt + F12
Layout
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
3. Master Data
3.1 Functional Location
Functional locations are elements of a technical structure (for example, functional
units within a system). Functional locations can be created according to the
hierarchy, and can be structured based on the f ollowing criteria:
Functional
Process-related
Spatial
Collect and evaluate data over a long period of time for the object
Trigger:
Functional locations need to be structured according to functional, process-related or
spatial criteria. Whenever any new location identified we need to create Functional
location.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
Functional location created
Procedural Steps
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Description:
Use this transaction for creating structured location
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Instructions
In the initial screen, enter the values in the following fields:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Optional
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Optional
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Optional
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Optional
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Optional
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Through transaction code IL02, required functional location can be opened for
editing
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
First dismantle the already existing installation and then input / select new
3.2 Equipment
A piece of equipment is an individual object that is to be maintained independently.
Each piece of equipment is managed independently in the system, so that you can:
Collect and evaluate data over a long period of time for the object
Trigger:
Maintenance history needs to be captured for a physical technical object.Whenever
any new Machine/Computer etc. Purchased we need to create Equipment Master.
Correct Equipment Type has to be choosen always for proper functioning.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Description:
Use this transaction for creating & maintaining Equipment
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Instructions
In the initial screen, enter the values in the following fields:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
REFERENCE
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Press Enter key or click on Enter / Continue icon to reach the following
screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 35 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 36 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Indicator Strategy
A Critical
B Important
C Non-critical
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 37 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Cost center R All the costs incurred at the equipment level are
collected at these cost centers level.
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 38 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
The field in the Function location blank, so it is to be selected for the Hierarchy
Icon.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
First dismantle the already existing installation and then input / select new
If you select the Superior Equipment Instead of Functional Location then that
Equipment will be called SubEquipment.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
WARRANTY
END DATE
Whenever we try to create a notification or order, SAP system will alert with a
warning message with warranty details if the equipment is still under warranty [period
Last changed on: Last changed by: Version: Page:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Structure description
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
A piece of maintenance equipment requires a bill of material for maintenance
purposes.Whenever any Equipment created we can create its BOM for Structuring.
But Before creating Equipment BOM we need to create Material Master.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Description:
Use this transaction for creating & maintaining Equipment bill of material
Press Enter key or use mouse double click to get following screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Equipment no
Plant
BOM
USAGE
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Task list is defined as the set of work instructions that will help a maintenance
planner schedule his day-to-day job in a predefined manner
Task lists can be grouped, for example in to two groups - "Inspection" and
"Mechanical Repairs".
The individual maintenance task lists within the group "Mechanical Repairs" and are
identified by the task list counter numbers 01 and 02 as shown in following fig.
This type of task list is generic in nature i.e. the same general task list can be
used both for equipment and functional location and also for more than one
equipment or functional location of the same type or different types.
Similar general task lists can be grouped and several individual general maintenance
task lists can be created.
General task lists can be used to reduce the time spent creating individual functional
location/equipment task lists.
Trigger:
Need to prepare a sequence of activities that must be repeatedly performed within a
company.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
General Task List created
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Description:
Use this transaction for creating & maintaining General task list
Press Enter Key to get the following screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Profile R PDIL
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Status
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Select components tab for allotting spares required for that acti vity.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Maintenance orders
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
A regulation or condition needing to be observed when maintenance work is being
performed.
Output – Results Comments
Permit master created Master record can be viewed again by selecting row
and choosing details.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
AND THEN ON
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click on
If you want to write some more thing about the permit. You can use the
Long Text.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
3.6 Characteristic
The pre-requisite for creating a Measuring Point is characteristic.
Creation of a Characteristic:
The Pre-requisite for creating a characteristic is “Unit of Measurement”, and almost
all standard “units of measurement” are available in the system. If a standard Unit of
Measurement is not available, contact administrator for creation of the same.
Trigger:
Format need for characteristic values and the need to display characteristics when
classifying master data
Output – Results Comments
List of characteristics Used to classify and identify objects
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
If the values are of standard type , values can be entered e.g., Speed of pumps
1500 RPM, 3000 RPM, 1000 RPM, 750 RPM etc.,
OR
Click on
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Measuring Points:
Measuring points in MY SAP ERP System describe the physical and/or logical
locations at which a condition is described (for example, the feed water temperature
of a boiler, or the number of run hours of a machine)
Measuring points
Counters
Counter is a provision in my SAP ERP to represent the wear and tear of an object,
consumption, or the reduction of an object‟s useful life
Counters can be used to accumulate the readings like equipment run hours,
Energy
Trigger:
A measurement or counter reading for any Equipment/ Functional location to capture
its current condition.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
Measurement Point created
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
If measuring point is normal measuring point and if data like max. and min. range is
to be given then click on Additional data tab. This data will determine for automatic
generation of notification whenever entered reading is beyond extreme limits.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click on
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
C a s e 2 : M ea s u r i n g P o i n t a s Co u n t e r
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Annual Estimate
Note : This is required for
Counter based planning
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click on
The Measuring Point (Counter) is saved.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Work centers contain default values that are copied or referenced in operations at the
time of task list creation. They also contain costing, scheduling and capacity data
required for leadtime scheduling and capacity planning.
Output – Results Comments
New work center within a plant
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Single cycle plan allows only one cycle frequency, whereas strategy plan allows
multiple frequencies.
Trigger:
To plan maintenance events to occur in a regular, periodic manner, based on one
cycle parameter.
Output – Results Comments
Maintenance plan is created. The outputs of all three types of maintenance plans
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Select the transaction and Double click or press Enter Key to reach the
following screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
In item overview all the maintenance items that are considered in the current
plan are displayed.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
After entering all the planning data click on to save the plan
During a schedule run, system schedules the planned dates and the call dates
Call date is the advance date of order generation by the system (as defined in
maintenance scheduling parameters) to facilitate maintenance planner to arrange
for execution of maintenance activity on planned date.
The call date is the date on which a maintenance order is created in the system.
This is determined by the call horizon of the maintenance plan.
Trigger:
To schedule the maintenance plan and monitor its progress, including making
scheduling modifications as necessary.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Note:
The plan is constantly adjusting itself to keep consistent with the cycle lengths linked to
the items. Thus, each time a call is closed outside the cycle length and the associated
tolerances, the plan is adjusted accordingly. If this is a recurring practice, future
planned call dates will be fluctuate sporadically and could be difficult to keep track of.
Output – Results Comments
A view of the scheduled calls
for a maintenance plan
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Select the transaction and Double click or press Enter Key to reach the following
screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Press Enter key
Enter key or click on Enter / Continue icon to get the following screen
and then Click on the “Start” or the “start in cycle”
cycle” Push button as per Requirement.
Requirement.
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 95 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 96 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click on “Scheduling
Overview.
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 97 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
To list the scheduled calls for a maintenance plan or group of plans
Output –
Output – Results
Results Comments
List of scheduled calls for
review
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 98 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
For viewing plan / execution status select transaction IP24 and press Enter
key to reach the
Following screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Select by maint plan category as PM (or use the available fields for
different search criteria)
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
4. Maintenance Processing
4.1 Measuring documents
Measurement readings are to be taken at measuring points in particular
measurement units at particular intervals. (For example, the feed water temperature
in degrees Celsius of the boiler daily at 6.00 am)
An optimum value for a particular measuring point to which the device concerned is
calibrated can be maintained as a target value for the measuring point.
Trigger:
A measurement or counter reading from a measurement point needs to be entered
into the system.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
A measurement or counter reading from a measurement point needs to be entered
into the system.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Type entry list name & press Enter key or click on Enter / Continue icon
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click on
List
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Entry list R Enter the entry list number or select from the
drop down list
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Notifications
Trigger:
An internal problem or maintenance request needs to be logged for problem
reporting and technical resolution.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
Creation of a notification Refer to Business Process Procedure „Display PM
Notification', to verify this result.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
As technical objects like buildings are installed as Functional locations, all jobs that
are required to be carried for buildings are to be created on Functional Locations.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
IT Report (IT)
An IT report describes a malfunction of an object, which restricts the performance of
that object in some way. A user can use a malfunction report to inform the
maintenance department that a system is not functioning correctly, is not working at
all, or is producing poor results. Malfunction reports are intended to prompt the
maintenance department to carry out a maintenance task to restore the target
condition of the object.
After selecting the transaction, press Enter key or double click to reach the following
screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
In the Initial screen , you can select the type of Notification and press ENTER key or
Type Of Notification:
Maintenance Orders
To carry out internal maintenance jobs or external services as per the maintenance
requests or according to day to day observations and for preventive maintenance
activities, a maintenance order is to be prepared to plan for material, manpower
and services requirement.
On the basis of maintenance orders only, maintenance jobs costing, reservation for
material and manpower planning can be done.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Functional Locations
Equipments
The different types of Maintenance Orders configured in the system are as follows:
Type Description
Please use appropriate type of order, for capturing the data under various categories.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
As technical objects like buildings are installed as Functional locations, for jobs that
are required to be carried out, Maintenance orders are to be created on Functional
Locations.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
>Press ENTER
>WE find this screen which show last 3 activities status on that particular equipment
Notification Header
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click / Press
ENTER
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Notification Description
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Required End O Enter the date and time on which the job to be
completed
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
i i ) N o t i f i c at i o n Pr o c e s s i n g
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Notification – Put in process :
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
i i i ) No t i f i c a t i o n C o m p l e t i o n
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Enter the notification number in Notification box or select from the list
Press Enter key or click on “Notification” to reach the following screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click here
Or go to menu path PM Notification -> Order -> Create -> Direct as shown in the
following screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Enter / check Order Type, Main work center and click on Enter / Continue
icon
To reach the following screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
For planning in terms of manpower and material and for further processing of order,
After entering required details, save the order and following message will
appear on the screen.
Trigger:
Internal work hours and costs need to be captured and transferred to other cost
objects for maintenance / service work.
Last changed on: Last changed by: Version: Page:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Header data :
Maint .work center R Default is copied from the Equipment, but it can
be changed , if required. This is required for
tracking purpose.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
First Operation
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Notes:
If the operations are more than one operation, use the operation tab strip,
and enter as many operations as required.
The work centers for different operations can be different. (If required).
Control Key PM01 Denotes – Work done by Own Employee & PM03 denotes
work done by External Vendor. For PM03 Purchase Requisition will be
created automatically. Which will go for Release Process & then Purchase
Last changed on: Last changed by: Version: Page:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Notes :
Item category - significance of „L‟ and „N‟ .
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
N – means Non-stockable, but coded item. – Even if stock is available , „N‟ can
be indicated.
The system will create a PR for the Items for which „N‟ is indicated.
Reservation Number Generated for Stock Item. Material Issue against Reservation
process can be viewd in MM End User Manual as it is MM Process.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
RELEASE
FLAG
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
v) COMPLETION CONFIRMATION
A.TIME CONFIRMATION
Trigger:
Actual hours worked and materials used need to be recorded and posted to the PM
order.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
Time confirmed to PM order Refer to Business Process Procedure 'Display PM
Order' (and view cost report) or 'Display PM Order
Confirmation' to verify results. The document flow on
the PM order will also show any time confirmations
posted.
Press Enter key or double click (with mouse Left key) to reach the following
screen;
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
ENTER ORDER NO OR
SELECT FROM LIST
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 149 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
FOR NEXT
OPERATION
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 150 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
Requirement for recording services performed by service provider
Output –
Output – Results
Results Comments
Service Entry Sheet
Menu Path
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 151 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
or use transaction
transaction code “ML81N” to reach the following
following screen
Click
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 152 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
SERVICE
SELECTION
TAB
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click here
Click to Select
line item
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
3. Click on this
flag for accepting
2. Service Entry
sheet Number
2. Confirm the
required quantity
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Click
Nov‟10 on Tech.
Completion flag
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
All data that refers to the reference object of the maintenance order is available and
correct
All relevant data in the operations and sub-operations is available and correct
The business completion function for an order defines the following information for
the order:
The order obtains the status Completed. It is indicated as fully completed.
The order cannot receive any more postings, even for posting of costs. It is locked for
all collective-processing changes.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
performance criteria.
Tcode :IA05
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Maintenance Planning:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
The maintenance planner also needs to identify the units for the maintenance plans -
time (weekly, monthly, yearly, etc.) or performance (every 100 running hours, every
10,000 shots etc.). For performance based maintenance plans, relevant measuring
counter needs to be defined for the technical object and measurement readings need
to be updated regularly.
The maintenance planner decides the maintenance call objects for the plan. The call
object can be maintenance order, notification or service entry sheet. Based on the
selection, system generates a call object for a maintenance plan, when a
maintenance call is due. The maintenance planner decides initially which call object
is required.
As mentioned earlier, maintenance plans can be single cycle, strategy based or
multiple counters, as per the requirement of each equipment / functional location.
Maintenance task lists shall be prepared for equipments / functional location, as per
the requirement. The task lists contains detailed sequence of activities to be
performed, spares and estimated time required for completing the job.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
For the activities, which are common amongst group of equipments, a general task
list may be prepared.
A maintenance plan includes the task list, maintenance strategy along with other
scheduling parameters.
Tcode :IP01
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Whenever a schedule falls due, the system creates a maintenance order, notification
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
or service entry sheet depending on definition of the call object of the plan.
The maintenance planner shall schedule the maintenance plan. Before the call
objects are created by the system, maintenance planner may manually call the job or
skip the job, depending on the situation.
If the call object is a maintenance order, then maintenance planner shall release it
manually after checking the order.
There is provision in the system to shift the next scheduled maintenance date of a
maintenance plan, if there is considerable delay in completing the order or the orders
are completed much ahead of the schedule. These tolerance ranges for shifting can
be decided while defining maintenance plan by the maintenance planner depending
on the nature of the job.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Tcode:IP10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Tcode : IW39
Add tasks (if required) in Task List attached in Preventive Maintenance Order
with detail regard to type, scope, dates and resources
Monitor the execution of tasks (operations)
Define rules for account assignment, settlement and budgets
Enter, assign and settle the costs which arise from tasks
Last changed on: Last changed by: Version: Page:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Order header
Object list
Operations
Material list
Settlement rule
Costs
Order Release
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Preventive Maintenance orders will be already released. If order has been released
and subsequently additional operations are entered for it, these are automatically
released.
Withdrawing material
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Tcode:IW32
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 177 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Notes :
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 178 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
N – means
– means Non-stockable, but coded item. –
item. – Even if stock is available , „N‟ can
be indicated.
The system will create a PR for the Items for which „N‟ is indicated.
Reservation Number Generated for Stock Item. Material Issue against Reservation
process can be viewd in MM End User Manual as it is MM Process.
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 179 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
(23/11/2010)
(23/11/2 010) RAVINDER KUMAR 1.0 180 of 241
End User Manual
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
Requirement for recording services performed by service provider
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
Service Entry Sheet
Menu Path
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
SERVICE
SELECTION
TAB
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click to Select
line item
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
1. Service Entry
sheet Number
2. Confirm the
required quantity
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
3. Save
Tcode ML85 or ML81n Can be used to release the Service Entry Sheet with proper
autherization.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
2. Release
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Released Saved
A.TIME CONFIRMATION
Trigger:
Actual hours worked and materials used need to be recorded and posted to the PM
order.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
Time confirmed to PM order Refer to Business Process Procedure 'Display PM
Order' (and view cost report) or 'Display PM Order
Confirmation' to verify results. The document flow on
the PM order will also show any time confirmations
posted.
Press Enter key or double click (with mouse Left key) to reach the following
screen;
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
ENTER ORDER NO OR
SELECT FROM LIST
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
FOR NEXT
OPERATION
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
All data that refers to the reference object of the maintenance order is available and
correct
All relevant data in the operations and sub-operations is available and correct
The business completion function for an order defines the following information for
the order:
The order obtains the status Completed. It is indicated as fully completed.
The order cannot receive any more postings, even for posting of costs. It is locked for
all collective-processing changes.
i) Notification Creation:
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
>Press ENTER
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Click / Press
ENTER
>WE find this screen which show last 3 activities status on that particular equipment
& then Save notification.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Select the Desired Notification & create the Regular maintenance Order
(Type:PM07).
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Test equipment is used for performing quality inspections. In order to ensure that the
test equipment used always fulfils the defined performance criteria, we have to
regularly test and calibrate these test equipment.
Using the functions in the component Test Equipment Management, we can manage
equipment data, plan and schedule inspections, and perform calibration inspections
for the equipment.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Transactio n c od e : IK17
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
Need to display measurement documents with similar characteristics.
Output – Results Comments
One or many measurement
documents selected for display
Input – Required Fields Field Value/Comments
Procedural Steps
Via Menus Logistics Plant Maintenance Maintenance
Processing Completion Confirmation
Measurement Document List Editing Display
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Input data for selection , you can get the report based on the input data like
Measuring points
Equipment
Functional location etc.,
to execute the transaction and you will get the following report
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
User wishes to search for material movements by material.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
Materials with the associated
movement types.
Procedural Steps
Via Menus (a) Logistics > Materials Management > Inventory
Management > Environment > List Displays >
Material Documents
Logistics > Materials Management > Physical
Inventory >Environment > Mat. Doc. For Material
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Enter required data like Plant, Storage Location, Movement type etc., as per your
report requirement
to execute the transaction and you will get the following report
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Selection screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Enter required selection filed values like Order no, Material, storage location as
per your requirement
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Selection screen
Enter Plant
Enter the selection screen values like Maint. Plants, Start & end dates,
Notification no., Equipment or Function locations and select required check
boxes according to the status.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
To review a list of maintenance orders and make any necessary changes
Output – Results Comments
A list of orders. Orders will be displayed based on the selection
criteria.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Procedural Steps
Selection screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Enter the selection screen values like Start & end dates, Notification no.,
Equipment aor Function locations and select required check boxes according to
the status.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Trigger:
To review a list of PM orders and associated documents and master records
Output – Results Comments
A list of orders with associated
documents and master records
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Procedural Steps
Selection Screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Select Required Order type, Enter period dates and select different parameters
for the multilevel display
Now click on to execute the transaction and you will get the
following report
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
List of Functional Locations
Procedural Steps
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Selection Screen
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Now click on to execute the transaction and you will get the
following report
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Equipment List
Transactio n cod e : IH08
Trigger:
To display a list of equipment by certain selection criteria.
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Output – Results Comments
A list of equipment records
Procedural Steps
Access transaction by:
Display
Title: SAP PM
Module: PLANT MAINTENANCE
Release: ECC 6.0
Created by: RAVINDER KUMAR
Created on: 23 Nov‟10
Selection Screen