Work Sampling
Work Sampling
Work Sampling is the statistical technique for determining the proportion of time spent by
workers in various defined categories of activity (e.g. setting up a machine, assembling two
parts, idle…etc)[1]. It is as important as all other statistical techniques because it permits quick
analysis, recognition, and enhancement of job responsibilities, tasks, performance competencies,
and organizational work flows. Other names used for it are 'activity sampling', 'occurrence
sampling', and 'ratio delay study'[2].
In a work sampling study, a large number of observations are made of the workers over an
extended period of time. For statistical accuracy, the observations must be taken at random times
during the period of study, and the period must be representative of the types of activities
performed by the subjects.
One important usage of the work sampling technique is the determination of the standard time
for a manual manufacturing task. Similar techniques for calculating the standard time are time
study, standard data, and predetermined motion time systems.
Work sampling involves recording activities and fixed or random intervals, these activities may
or may not be rated. Work sampling is good for measuring things occuring over longer periods
like the working week (e.g. contingencies like small/infrequent delays). Time study is good for
measuring individual operations and operators to establish standard minute values. Work
sampling can also do this and is useful for measuring groups of operators / machines at a time.
The study of work sampling has some general characteristics related to the work condition. One
of them is the sufficient time available to perform the study. A work sampling study usually
requires a substantial period of time to complete. There must be enough time available (several
weeks or more) to conduct the study. Another characteristic is multiple workers. Work sampling
is commonly used to study the activities of multiple workers rather than one worker. The third
characteristic is long cycle time. The job covered in the study has relatively a long cycle time.
The last condition is the non-repetitive work cycles. The work is not highly repetitive. The jobs
consist of various tasks rather than a single repetitive task. However, it must be possible to
classify the work activities into a distinct number of categories.
There are several recommended steps when starting to prepare a work sampling study[1]:
1. Define the manufacturing tasks for which the standard time is to be
determined.
2. Define the task elements. These are the defined broken-down steps of the
task that will be observed during the study. Since a worker is going to be
observed, additional categories will likely be included as well, such as "idle",
"waiting for work", and "absent".
3. Design the study. This includes designing the forms that will be used to
record the observations, determining how many observations will be
required, deciding on the number of days or shifts to be included in the study,
scheduling the observations, and finally determining the number of observers
needed.
4. Identify the observers who will do the sampling.
5. Star the study. All those who are affected by the study should be informed
about it.
6. Make random visits to the plant and collect the observations.
7. After completing the study, analyze and present the results. This is done by
preparing a report that summarizes and analyzes all data and making
recommendations when required.
After the work elements are defined, the number of observations for the desired accuracy at the
desired confidence level must be determined. The formula used in this method is:
n = number of observations