TM Transformer
TM Transformer
0 1
dseVsd@bZ@2005@Vh,Qih&bZ,e;w@1-0
CAMTECH/E/2005/TFP-EMU/1.0
vDVwcj 2005
October 2005
Centre
for
Advanced
Maintenance
Excellence in Maintenance
TECHnology
,lh bZ,e;w@,ebZ,e;w
e;w ds VªkUlQkeZj
ds
vuqj{k.k dh y?kq iqfLrdk
MAINTENANCE HANDBOOK
ON
TRANSFORMER OF AC EMU/MEMU
TARGET GROUP – TECHNICIANS & SUPERVISORS OF AC
EMU/MEMU CAR SHEDS, WORKSHOPS
FOREWORD
With increasing passenger traffic in Metropolitans & their connected cities, reliability of
AC EMU/ MEMUs has become very important. Proper maintenance of transformer is vital to
ensure trouble free operation of EMU/MEMUs.
CAMTECH has prepared this handbook to cover all essential aspects of maintenance and
overhauling of transformer of AC EMU/MEMUs. It describes technical details, description of
different parts, various maintenance schedules including POH, failures, causes and their
remedies. It also describes transformer oil purification and condition monitoring of transformer
by dissolved gas analysis (DGA).
I am sure the handbook will prove to be very useful to our maintenance staff in EMU car
sheds/ workshops.
PREFACE
The transformer is one of the most important equipment of AC EMU/ MEMU. Proper
maintenance of transformer is essential to ensure reliability of AC EMU/ MEMUs in service.
This handbook on maintenance of transformer has been prepared by CAMTECH with the
objective of making our maintenance personnel aware of correct maintenance and overhaul
techniques to be adopted in field.
It is clarified that this handbook does not supersede any existing provisions laid down by
RDSO or Railway Board. The handbook is for guidance only and it is not a statutory document.
I am sincerely thankful to Exe. Director/ EMU, RDSO/LKO for his valuable comments. I
am also thankful to all field personnel who helped us in preparing this handbook.
Technology upgradation and learning is a continuous process. Hence feel free to write to
us for any addition or modification in this handbook. We shall highly appreciate your contribution
in this direction.
CONTENTS
Foreword iv
Preface vi
Contents viii
Correction Slip xii
1. GENERAL DESCRIPTION 01
1.1 INTRODUCTION 01
1.2 TECHNICAL DETAILS 02
1.3 DIFFERENT PARTS OF TRANSFORMER 04
1.4 DESCRIPTION OF IMPORTANT FITTINGS 05
1.5 COOLING EQUIPMENT 08
1.6 FACTORS AFFECTING LIFE OF TRANSFORMER 09
2. MAINTENANCE 10
2.1 TRIP INSPECTION 10
2.2 IA SCHEDULE/ IB SCHEDULE 10
2.3 IC SCHEDULE 11
2.4 POH 14
2.4.1 GENERAL 14
2.4.2 INCOMING TESTS/ INSPECTION 14
2.4.3 TRANSFORMER OIL TESTING 16
2.4.4 PURIFICATION OF TRANSFORMER OIL 17
2.4.5 INTERNAL INSPECTION 17
2.4.6 INPECTION OF FITTINGS 19
2.4.7 FINAL FITMENT OF TRANSFORMER ON MOTOR COACH 21
2.4.8 FINAL CHECKING 21
3. TRANSFORMER FAILURES 22
3.1 COMMON FAILURES OF EMU TRANSFORMER 22
3.1.1 OIL LEAKAGE 22
3.1.2 LOW BDV 23
3.1.3 BUSHING FAILURE 23
3.1.4 FLEXIBLE (METALLIC) EXTENSION COUPLING FAILURE 23
3.1.5 WINDING FAILURE 24
3.1.6 TEMPERATURE RISE/ACTUATION OF THERMOSTAT 24
3.1.7 ACTUATION OF PRV 25
3.1.8 LOW IR VALUE 25
3.1.9 HUMMING SOUND 25
ANNEXURE-1
REFERENCES 32
The correction slips to be issued in future for this handbook will be numbered as follows:
Where “XX” is the serial number of the concerned correction slip (starting from 01
onwards).
Sr. No. Date of issue Page no. and Item no. Remarks
modified
CHAPTER 1
GENERAL DESCRIPTION
1.1 INTRODUCTION
Current at 25 kV is taken from OHE to its primary winding via the pantograph, the
vacuum circuit breaker and the high tension main bushing. The return path for this current is
via the earthing brushes mounted in the axle cap of each traction motor and the running
rails.
The secondary winding of the transformer is in two sections, one section having five
tapped sections, other being untapped. This arrangement gives a total twenty-two voltage
steps by various connections of transformer tappings and voltage dropping reactors. This
voltage, which is controlled by the tap-changing switchgroup, is applied to the silicon
rectifiers, the full wave output of which is fed to the traction motors via the smoothing
reactor.
Two tertiary windings, auxiliary I and II are provided. Auxiliary I, 266 V winding
feeds the single phase a.c. auxiliary machines. Auxiliary II, 141 V winding supplies power
to normal lights & fans, head lights stabilizer, the auxiliary rectifier for main compressor
motor.
The transformer is oil-immersed type and oil is forced circulated and cooled in
radiator by blower set.
T8
M12
OHE
PANTOGRAPH T9
OL6
M29
P1
T7
OL5
ABB/VCB
TL
LA
P2
EAS
T5
a8
TO RECTIFIER
T4 BLOCKS
CT a7
P3
0.05µF
T3
a6
LP2
LP1
T2
a5
OLP
T1
100A a4
M11
a12 T6
AUX.I M10
100A a11 266V a3
W2
PRIMARY
W1
0.05µF
TO RECTIFIER
G P4 BLOCKS
DL
a1
Make BHEL
Secondary winding
Cooling pump
Capacity 363.6 litres/minute at 70°C against a 7.32 meter head.
RPM 1430
Size of suction branch 76 mm
Size of delivery branch 73 mm
Pump motor
BHP 1.5
RPM 1430
Rating 240 ± 22.5%V, 1 phase, 50 Hz.
1.3.2 Windings
Figure 1.4
The H.V. (primary) line terminal is brought out to the H.V. turret through the cover
& connection is made to condenser bushing/ cable head bushing.
The L.V. (secondary) terminals, 8 in number each capable of carrying 1280 amperes,
are taken from the side of the tank through epoxy resinated terminal boards with copper bars
embedded into it.
Figure 1.5
Four terminals of two auxiliaries are taken through another epoxy resinated terminal
board in a similar fashion as in the case of L.V. The primary earthing terminal is taken
through a 6.6 KV porcelain bushing and is connected to earth.
1.3.4 Tank
1.4.2 Breather
Relay BIR trips permanently and the transformer is disconnected from the supply
through circuit breaker tripping if any of the following faults occurred:
a. Broken down core bolts.
b. Shorted laminations.
c. Bad contacts
d. Over heating of some part of the windings.
e. Falling of oil level arising from leakage.
f. Ingress of air, through defects in the oil circulating system.
g. Puncture of bushings.
h. Short circuit between phases.
i. Earth faults.
j. Winding short circuits.
k. Oil level falling below height of mounting position of the protector.
1.4.4 Thermostat
A major fault inside the transformer causes instantaneous vaporization of oil, leading
to extremely rapid build up of gaseous pressure. If this pressure is not released with in few
milliseconds, the transformer tank can rupture, spilling oil over a wide area. This relief vent
provides instantaneous releasing of such dangerous pressure and protects the transformer.
Figure 1.11
When pressure in the tank rises above predetermined safe limit, this valve operates
and performs following function:
a. Allows the pressure to drop by instantaneously opening a port of about 150mm dia.
b. Gives visual indication of valve operation by raising a flag.
c. Operates a micro switch which gives PRV trip indication by glowing LED and
ABB/VCB tripping in the faulty unit.
The valve restores its position as soon as the pressure in the tank drops below set
limit. The flag and switch remain operated until they are reset manually.
FILTER VALVES
GATE VALVES
TRANSFORMER
PUMP
CHOKE RADIATOR
Check the colour of silicagel in each inspection and if found pink, replace or
reactivate crystals at 150 to 200 degree C. Test transformer oil for electric strength and
water content in IC schedule & POH and carry out purification with high vacuum type
transformer oil filteration plant if required. Arrest the oil leakage if any.
CHAPTER 2
MAINTENANCE
Schedule Periodicity
2.3 IC SCHEDULE
3. Check colour of silica gel crystals and replace if found pink. Blue in colour
4. Check radiator and its pipe line connections for any oil No leakage
leakage.
5. Open the radiator protective net and blow the dust of radiator Clean
with compressed air and clean it with high pressure water jet.
Provide the radiator net.
9. Check terminal blocks for any oil leakage, flash mark etc. and No leakage,
also check intactness of each connection. intact.
10. Check main bushing visually for any damage and clean Clean, Intact
porcelain roof bushing insulator & complete bushing surface
thoroughly. Also check intactness of roof bushing connection.
13. Collect oil sample of transformer oil and send it to the lab for
testing as per Annexure ‘A’. Confirm the report from lab
before releasing the rack for service.
Annexure ‘A’
As per RDSO SMI no. RDSO/ELRS/SMI/ 158 dt. 19.01.1995, following tests to be
carried out on the transformer oil during IC schedule.
i. Draw a sample of the oil from the transformer as per the method given in IS: 6855-
1973 or IS: 9434-1979 depending upon the characteristics to be evaluated. The
quantity of oil drawn should be 4 litres instead of 2 litres prescribed in these
standards.
ii. Check the oil characteristics for tests given in table given below.
iii. If the colour of the oil has became dark brown, which is indicative of presence of
dissolved copper, change the oil with new filtered oil meeting characteristics given in
Annexure I of SMI 158.
iv. For interpretation of results of dissolved gas analysis, follow the instructions given in
RDSO SMI No. 138.
v. If dielectric strength and water content are beyond the permissible limits given in
above table, the oil is likely to be cloudy with acrid smell and it should be filtered
under vacuum as per IS:10028 (III) 1981 & IS: 1866-1983.
vi. If the specific resistance is beyond permissible limit, replace the oil with new filtered
oil meeting characteristics given in Annexure 1 of SMI 158.
2.4 POH
2.4.1 General
First of all remove as much dirt as possible particularly around the transformer tank,
radiator protective net, terminal block covers & PRV etc. Open the radiator protective net
and blow the dust of transformer & radiator with compressed air.
Clean the body of the transformer and tightened all the bolts in the body of the
transformer.
Check the complete tank for any deformation and crack.
Check the oil leakage from transformer tank, radiator, the oil pipes, the flange joints,
flexible couplings, conservator, Buchholz device, drain plugs, vent plugs and both side
terminal blocks.
Check the thread condition of filter valve, drain plug and oil sample valve, air release
vents and replace all gaskets/washers.
Check the conservator for any bend and damage.
Check the under frame oil pipe lines, gate valves, tank etc. for any hitting mark,
damage etc.
Note all the defects and deficiencies.
2.4.2.2 Meggering
Apply 225 V a.c. to the primary winding of the transformer and measure the voltage
appearing at the following terminals of the terminal blocks.
The above tolerances are ± 0.5% of the stated voltage ratio of the transformer at no load.
Note:- For taps 7 upwards, it will be necessary to short terminals a2 & a3 with a piece of
insulated conductor.
As per RDSO SMI No.RDSO/ELRS/SMI/158 dtd. 19.01.95, following tests to be carried out
on the transformer oil during POH.
i. Draw a sample of the oil from the transformer as per the method given in IS: 6855-
1973 or IS: 9434-1979 depending upon the characteristics to be evaluated. The
quantity of oil drawn should be 4 litres instead of 2 litres prescribed in these
standards.
ii. Check the oil characteristics for tests given in table given below.
Compare the results with the result recorded earlier on the same oil. Any abrupt
change in the value of the parameters is indicative of the unhealthiness of the
transformer. The transformer should be opened for detailed internal inspection for any
incipient fault. However, if the flash point falls by 15 degree C from its initial value,
replace the oil with new filtered oil without opening the transformer.
iii. If the colour of the oil has became dark brown, which is indicative of presence of
dissolved copper, change the oil with new filtered oil meeting characteristics given in
Annexure I of SMI 158.
iv. For interpretation of results of dissolved gas analysis, follow the instructions given in
RDSO SMI No. 138.
v. If either of the parameters i.e. flash point, interfacial tension, specific resistance, total
acidity and dielectric dissipation factor are beyond the permissible limits, replace the
oil with new filtered oil.
vi. Measure and record the inhibitor content in the oil, if inhibited.
If transformer is not due for core lifting and other test results are satisfactory,
connect the transformer for oil purification. The oil should be purified under vacuum as per
IS: 10028 (III) 1981 & IS: 1866-1983.
In order to obtain optimum service life from the EMU transformer, it is suggested
that transformer is opened and core is lifted at an interval of 6 to 8 years of service. Core
should also be lifted during first POH after commissioning for tightening of the pressure
bolts.
Close all the gate valves of transformer and its pipes lines.
Drain oil from transformer pipe lines.
Disconnect all electrical connections of transformer.
Disconnect and remove main bushing.
Disconnect all pipe line connections to the transformer.
Open all base parts from transformer tank.
Provide hydraulic trolley below the transformer tank and lift the transformer by the
trolley.
Remove all the foundation bolts fixing transformer to the motor coach.
Remove the transformer with the help of hydraulic trolley.
Bring the transformer in transformer repairing section.
Clean thoroughly the transformer body.
Lower and raise the active part 4 to 5 times in a dry oil bath so as to remove the
sludge from the ducts in the core/ windings.
Place the active part (windings) in a large vessel vertically on wooden blocks and hose
down with clean dry oil. Do not impinge hot oil jet on the transformer windings.
Check all the core support bolts for any crack at the welded joint and replace them if
required.
Check the tightness of yoke bolts by torque wrench.
Check the spacers and wedges for proper position and thickness.
Check the lead paper insulation for any damage and reinsulated if necessary.
Check the distance between the bus bars and yoke.
Check the bushing stud and insulator for any damage and replace if necessary.
Check the tightness of bus bar leads and also crimping terminal joints.
Check the condition of insulating separators.
Tighten all pressure bolts until Belleville washers are flattened and then rotate by 1/6
turn in opposite direction.
Bake the active part (windings) in oven at a temperature of 60 degree C.
Check insulation resistance with 1 kV megger between end frame and core.
Clean the top cover (plate) thoroughly from the top-side, bottom side and turret area.
Check visually for any flash mark on bottom side and welding cracks of
channels/angles.
Check the vent plugs (3 nos.) and replace nylon/ copper washer with new one, if
required.
Top cover bottom side to be varnished properly with copal varnish and top side to be
painted with battleship grey paint.
Check active part holding suspension device for straightness and uniform ness.
Carry out the following tests on the transformer after re-tanking of active part in tank.
Meggering
Continuity test
Ratio test
2.4.6.3 Thermostat
2.4.6.5 Radiator
Clean the radiator tubes thoroughly by compressed air and high pressure water jet.
Check radiator tubes and fins for any damage.
Replace both side cover gasket of radiator with new one.
2.4.6.7 Conservator
Clean the roof bushing insulator, condenser sleeve and transformer bushing thoroughly.
Check visually roof bushing porcelain insulator for any crack, flash mark etc.
Check condenser sleeve for any damage, crack etc.
Remove oil from the condenser bushing if provided.
Check and record tan- delta of the bushings (without oil at 1,2 and 5 kV). If the value of
the tan delta is greater than 3%, replace the bushing.
Check flange to flange distance in the condenser bushing, it should be of 2200± 5 mm.
If this gap is found to be less, carry out modification as advised vide RDSO
modification sheet No. RDSO/WAU/3/ Dated 24-07-1981.
Note:- Replace the condenser bushing with cable head termination system as per RDSO
specification No. ELRS/SPEC/BL-0003 –May 99 and SMI No.193.
Fit the transformer on motor coach with the help of hydraulic trolley.
Fit all the fitting such as Buchholz device, main bushing, conservator, breather etc.
Connect all the pipe lines, flexible couplings and pipe lines support.
Connect all electrical connection, earthing leads etc.
If transformer oil has been replaced due to any reason, replace the oil of choke tank also.
Fill the transformer oil up to proper level.
Ensure open condition of all gate valves.
Connect the transformer to the oil purification plant for purification of transformer oil
and carry out purification as described under section 2.4.4.
Check the transformer, conservator, Buchholz device, pipe lines, couplings, gate valves,
radiator etc. visually for any defect or deficiency.
Check visually for any oil leakage from any point, coupling, joints etc.
Ensure the open condition of all the gate valves.
Check and ensure oil level in conservator, it should be minimum 15 degree C mark.
Release air from vent plugs.
Check the function of Buchholz relay.
Ensure connection of thermostat and oil in TT pocket.
Ensure operation of PRV plunger and its connections.
Check the transformer fuses.
Provide all terminal block covers.
CHAPTER 3
TRANSFORMER FAILURES
Low BDV
Bushing failure
Winding failures
Actuation of PRV
Low IR value
Humming sound
Note :
Actuation of PRV, BIR and OLR takes place during failure of transformer winding
and circuit breaker is tripped. Circuit breaker should not be reclosed as it might result in
additional internal damage and fire hazard.
Check transformer for any external mechanical or electrical damage to bushings,
terminal board connections and other parts. Take oil sample for DGA, BDV and other
tests. Check the transformer thoroughly and take corrective action according to
observations and oil test results.
3.1.6 Temperature Rise/ Actuation of Thermostat.
CHAPTER 4
The object of oil purification is to remove all contaminants such as water, carbon deposits,
dirt, sludge, dissolved moisture and gases. The most important quality to be preserved is the di-
electric strength, which is affected by the presence of moisture.
The insulating materials used in the winding are hygroscopic by nature and therefore
moisture is absorbed through defective breathers, gaskets and addition of untreated make up oil. It
is essential to remove these impurities by purifying the oil when the dielectric strength goes below
the permissible limits.
The purification plant should be capable of removing dissolved air/ moisture in the form of
free and finely dispersed water vapour and moisture in solution, sludge and fibers, gases,
carbonaceous products formed due to arcing and drum scale or any other solid particles from
insulating oil.
The plant should be capable of purifying the rated capacity of transformer oil to the
following parameters in maximum three phases.
The switching ON & OFF of the heater groups should be thermostatically controlled
so that the temperature of the oil during treatment is not be permitted to rise above 60°C.
Operating vacuum should be better than 1 torr.
TEMPERATURE
TIME IN HOURS
B. Insulation resistance will continue to remain at a low level despite temperature being
maintained at a high level until most of the moisture from the windings and oil has
been driven out.
C. The insulation resistance will thereafter rise gradually and level off, indicating that all
moisture has been driven out and the drying out operation has been completed. At
this point oil circulation should be discontinued.
D. As the oil cools off, the insulation resistance will rise much above the leveling off
point at the end stage (C). This is because the insulation resistance value doubles for a
fall in temperature of about 10°C to 15°C.
*****
CHAPTER 5
5.1 INTRODUCTION
In order to detect incipient faults in the transformer and to arrest deterioration/
damage to the transformer insulation, gases dissolved in the transformer oil are detected,
analysed and preventive measures adopted.
Gas Chromatography method is used for detection of the dissolved gases and
identification of incipient faults. The most significant gases generated by decomposition of
oil and deterioration of paper insulation on the conductor are hydrogen, methane, ethane,
ethylene and acetylene. The quantities of these gases dissolved in transformer oil vary
depending upon the type and severity of the fault conditions.
Gas Less than 4 years in 4-10 years in service More than 10 years
service (ppm) (ppm) in service (ppm)
Hydrogen (H2) 100/150 200/300 200/300
Methane (CH4) 50/70 100/150 200/300
Acetylene (C2 H2) 20/30 30/50 100/150
Ethylene (C2 H4) 100/150 150/200 200/400
Ethane (C2 H6) 30/50 100/150 800/1000
Carbon dioxide (CO2) 3000/3500 4000/5000 9000/12000
Gases formed during the refining processes and not completely removed by oil
degassing.
Gases formed during drying and impregnating the transformer in sheds/ workshops.
Gases formed in the event of previous faults and not completely removed from the oil-
impregnated insulation before being refilled with degassed oil.
Gases formed during repairs by brazing, welding, etc.
CHAPTER 6
6.1 DO’S
1. Check the protection system of transformer periodically.
2. Always use transformer oil procured from RDSO approved suppliers.
3. Check silica gel regularly.
4. Check and thoroughly investigate the transformer whenever any alarm or protection
system is operated.
5. Examine the bushings for dirt deposit, coating and clean them periodically.
6. Attend any type of oil leakage at the earliest possible.
7. Clean conservator thoroughly before refilling.
8. Ensure proper functioning of Buchholz relay.
9. Ensure periodic testing of transformer oil.
10. Ensure that oil has been removed from the condenser bushing.
11. Ensure oil in TT pocket.
12. Maintain record of transformer and oil, transformer wise for future reference.
6.2 DON’TS
1. Don’t use under capacity lifting jacks.
2. Don’t leave any loose connection.
3. Don’t meddle with protection system.
4. Don’t allow conservator oil level to fall below 15 degree C. level.
5. Don’t over tight the nuts & bolts to stop any leakage.
6. Don’t use fuses higher than the prescribed ratings.
7. Don’t tamper with earthing connections.
8. Don’t keep the breather pipe open or exposed.
9. Don’t re-energize the faulty transformer unless the oil test report including DGA is
satisfactory.
10. Don’t impinge hot oil jet on the transformer windings for cleaning.
11. Don’t use reclaimed oil in transformer.
12. Don’t mix old & new transformer oils.
13. Do not mix EHV grade & inhibited transformer oil.
*****
ANNEXURE – I
List of Modifications and Special Maintenance Instructions issued by RDSO for Transformer
of AC EMU/MEMU.
REFERENCES
2. BHEL Maintenance Manual for 25 kV broad gauge AC and Main Line Electrical
Multiple unit (Electrical Equipment). Book Number : MM/AC-M/EMU/003, January,
2001.
4. IS: 10028 (Pt.III) - 1981, reaffirmed 1993 & 1998 –Code of Practice for Selection,
Installation and Maintenance of Transformers (Part– III Maintenance).
5. Field study and literature collected from various EMU car sheds/ workshops.
OUR OBJIVECTIVE