Critical Path Question

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Activity Predecessor Duration (days)

A 3
B A 4
C A 2
D B 5
E C 1
F C 2
G D,E 4
H F,G 3