Electrical Design Manual
Electrical Design Manual
Electrical Design Manual
Facilities Management
Electrical
design manual
December 1, 2019
PG 18-10 – ELECTRICAL DESIGN MANUAL December 1, 2019
TABLE OF CONTENTS
CHAPTER 1: GENERAL REQUIREMENTS ....................................................................................... 1-1
1.1 PURPOSE ................................................................................................................... 1-5
1.2 RESPONSIBILITY ......................................................................................................... 1-5
1.3 AUTHORITY HAVING JURISDICTION .......................................................................... 1-6
1.4 COORDINATION ........................................................................................................ 1-6
1.5 VA DESIGN CRITERIA ................................................................................................. 1-7
1.5.1 MASTER SPECIFICATIONS (PG-18-1) ......................................................................... 1-7
1.5.2 DESIGN AND CONSTRUCTION PROCEDURES (PG-18-3) ........................................... 1-7
1.5.3 NATIONAL CAD STANDARD, VHA APPLICATION GUIDE &
STANDARD DETAILS (PG-18-4) .................................................................................. 1-7
1.5.4 EQUIPMENT GUIDE LIST (PG-18-5) ........................................................................... 1-8
1.5.5 DESIGN MANUALS (PG-18-10) .................................................................................. 1-8
1.5.6 DESIGN GUIDES (PG-18-12) ...................................................................................... 1-8
1.5.7 DESIGN SUBMISSION INSTRUCTIONS (PG-18-15) ..................................................... 1-9
1.5.8 DESIGN REVIEW CHECKLISTS .................................................................................... 1-9
1.5.9 DESIGN ALERTS ......................................................................................................... 1-9
1.5.10 STANDARDS ALERTS ................................................................................................ 1-10
1.5.11 PHYSICAL SECURITY DESIGN MANUAL.................................................................... 1-10
1.5.12 COST ESTIMATING MANUAL ................................................................................... 1-10
1.5.13 SUSTAINABLE DESIGN MANUAL ............................................................................. 1-10
1.5.14 SEISMIC DESIGN REQUIREMENTS (H-18-8)............................................................. 1-11
1.5.15 FIRE PROTECTION DESIGN MANUAL....................................................................... 1-11
1.5.16 VA HOSPITAL BUILDING SYSTEM ............................................................................ 1-11
1.5.17 COMPUTER AIDED FACILITIES MANAGEMENT REQUIREMENTS (CAFM) ............... 1-12
1.6 VA BIM STANDARD ................................................................................................. 1-12
1.7 APPLICABLE CODES AND STANDARDS .................................................................... 1-12
1.7.1 GENERAL ................................................................................................................. 1-12
1.7.2 LOCAL CODES AND CONDITIONS ............................................................................ 1-13
1.7.3 LOCAL UTILITY ......................................................................................................... 1-13
1.8 DESIGN REQUIREMENTS ......................................................................................... 1-13
1.9 CRITERIA UNIQUE TO VA......................................................................................... 1-14
1.9.1 DRAWINGS .............................................................................................................. 1-14
1.9.2 SEQUENCE OF ELECTRICAL DRAWINGS .................................................................. 1-15
1.9.3 ABBREVIATIONS AND SYMBOLS ............................................................................. 1-15
1.9.4 PROPRIETARY ITEMS ............................................................................................... 1-16
1.10 CALCULATIONS ........................................................................................................ 1-16
Table of Contents i
PG 18-10 – ELECTRICAL DESIGN MANUAL December 1, 2019
Table of Contents ii
PG 18-10 – ELECTRICAL DESIGN MANUAL December 1, 2019
Table of Contents iv
PG 18-10 – ELECTRICAL DESIGN MANUAL December 1, 2019
Table of Contents v
PG 18-10 – ELECTRICAL DESIGN MANUAL December 1, 2019
1.1 PURPOSE
This manual is intended as a guide for electrical engineers and designers (hereafter referred as
the A/E) for the planning and design of the electrical power distribution and related systems
(hereinafter referred to as systems) at Department of Veterans Affairs (VA) facilities which are
designed and constructed with VA construction budget, as well as owned, operated and
maintained by VA.
VA requires the A/E to read, understand, and use this manual in the planning and design of the
systems in VA owned construction projects – major, minor and non-recurring-maintenance
(NRM).
In order to provide the latitude needed to incorporate new technologies and concepts, or to
accommodate adverse existing construction conditions, technical deviations from the
stipulations of this manual may be made. Deviation request(s) may be made only if a safe,
reliable, and energy-efficient design shall result. Such deviation request(s) must be approved
by VA’s Contracting Officer (CO) and Authority Having Jurisdiction (AHJ). The A/E shall submit
deviation request(s) in writing to CO and AHJ, through VA’s Project Manager (PM) and
Contracting Officer Representative (COR). Veterans Health Administration (VHA) may require
specific web-based procedure for this action; therefore, the A/E shall confirm specific
procedure to submit deviation request(s) with CO, PM and COR.
At the minimum, request for deviation(s) shall contain the following elements:
• Narrative detailing reasons for the deviations
• Narrative detailing the design and technical information relating to the deviations
• Statement affirming that deviations shall comply with all public laws, federal
regulations, executive orders, and latest applicable codes
• Design drawings of the deviations (if applicable)
• Engineering calculations (if applicable)
• Estimate of cost impact caused by the deviations
• Estimate of schedule impact caused by the deviations
• Supporting documents such as existing site survey photographs, drawings and
documents (if applicable)
Deviation request(s) shall be considered approved only after the A/E has received the written
approval with signature from CO and AHJ.
1.2 RESPONSIBILITY
The A/E shall provide all necessary professional services to perform planning and design of the
systems for the project. The A/E shall be responsible and liable for the professional design in
accordance with the contract, safe and practical engineering practices, applicable VA design
criteria, VA project-specific requirements (if any), and latest applicable codes. The A/E shall be
responsible and liable for the content of the construction contract document.
1.4 COORDINATION
(a) The A/E shall coordinate planning and design work with all disciplines such as architectural,
structural, civil, site utility & site work, telecommunications / data, HVAC, plumbing,
medical air, fire protection / alarm system, and LEED/Sustainable designs, as applicable.
The A/E shall carefully focus on concealed and underground construction areas, and site
utility coordination. The A/E shall coordinate and provide electrical design for all electrically
operated equipment shown on other disciplines’ drawings. For example, the A/E shall
provide adjustable frequency drives for motors as required on the mechanical drawings;
provide branch circuit power to terminal units, terminal unit fans, smoke dampers, control
panels and other auxiliaries; and provide branch circuit power to medical gas alarm panels.
(b) Utility Coordination:
(1) For projects requiring new electrical service, the A/E shall coordinate requirements with
the local utility service company. The Contractor’s scope of work, as it relates to the
service, shall be detailed in the Construction Documents. The A/E shall forward copies
of all correspondence and minutes of meetings with the utility company's
representatives to CO, PM and COR regarding negotiations for new services or making
changes to the existing services.
(2) For renovations of and/or additions to existing buildings, the A/E shall investigate and
confirm the existing electrical service/distribution system. The A/E shall determine
whether existing electrical power capacity is available to accommodate new loads. If
applicable, the A/E shall inform the electric utility company of the new service
requirements and additional loads.
(3) The A/E shall show on civil utility drawings, for coordination purposes, all -major site
electrical power distribution components, such as medium voltage and low voltage
electrical power feeders, ductbanks, and manholes.
(c) Pre-Design Site Survey: For renovation projects, the A/E shall perform the following tasks:
(1) Electrical Load Monitoring: Investigate the existing electrical service/distribution system
and determine whether existing electrical power capacity is available to accommodate
the new loads. Determining of existing loads shall be as required by the NFPA 70 -
National Electrical Code (NEC).
(2) Existing Electrical Installation: Investigate and record all existing field electrical
installations such as existing underground ductbanks, manholes, concealed conduit
runs, conduit types/sizes, cable types/sizes, panelboard types/sizes, electrical
equipment locations, etc., which potentially impact the new installation.
1.5.3 NATIONAL CAD STANDARD, VHA APPLICATION GUIDE & STANDARD DETAILS (PG-18-
4)
Located in Technical Information Library at https://www.cfm.va.gov/TIL/sDetail.asp
Purpose
VHA Application Guide adopts the NIBS National CAD Standard, establishes VA-specific drafting
standards for the preparation of design and construction documents, and provides utility and
sheet template files and standard construction details, organized by discipline, for use in design
and construction documents for VA projects.
Purpose
This manual identifies the seven sustainability goals outlined in the Federal Mandates, and
maps each goal to the appropriate LEED strategy for implementation. Possible methods to
achieve the goals, budget considerations, case studies, and checklists are also included.
The Manual accomplishes this by:
• Prescribing the use of integrated design practices
• Providing strategies for optimization of energy performance
• Providing strategies for protection and conservation of water resources
• Providing strategies for enhancement of indoor environmental quality
• Providing strategies for reduction of environmental impact of materials
1.7.1 GENERAL
The A/E shall use and comply with latest pertinent Codes, Standards and Executive Orders for
the design. Refer to PG-18-3, Topic 1, Codes, Standards and Executive Orders. Unless
otherwise indicated by VA criteria, use the latest Codes and Standards of the following
organizations:
(a) American National Standards Institute (ANSI)
(b) American Society for Testing Materials (ASTM)
(c) Illuminating Engineering Society of North America (IESNA)
(d) Institute of Electrical and Electronic Engineers (IEEE)
(e) International Organization for Standardization (ISO), Standards for Protocols and Interfaces
that include Open System Interconnections (OSI)
(f) Joint Commission on Accreditation of Healthcare Organizations (JCAHO), Environment of
Care Guidelines and Standards
(g) National Fire Protection Association (NFPA): the A/E shall pay particular attention to the
following publications:
• NFPA 20 - Standard for the Installation of Stationary Pumps for Fire Protection
• NFPA 70 - National Electrical Code
• NFPA 70 B - Recommended Practice for Electrical Equipment Maintenance
• NFPA 70 E - Standard for Electrical Safety in the Workplace
• NFPA 72 - National Fire Alarm and Signaling Code
1.9.1 DRAWINGS
(a) Refer to VA Design and Construction Procedures (PG-18-3), Topic 2 – Drawings, and the VA
NCS Application Guide, for general drawing requirements.
(b) Consolidate notes and place them on the right-hand side of the sheet.
(c) Show scale, compass point, orientation, key plan, title, column grids and numbers,
matchlines, room numbers, and titles corresponding to the Architectural drawings.
(d) Provide large-scale (minimum 1/4"=1') partial plans for areas such as Electrical Rooms,
Generator Rooms, Main Computer Room, Telephone Equipment Room,
Telecommunications Rooms, and Mechanical Equipment Rooms.
(e) It is mandatory to show the number of wires in each branch circuit conduit on the plans.
Include the number of wires in all interconnecting conduits for all wiring devices, fixtures,
and equipment.
(f) Provide 1/4-inch scale details of special equipment spaces, such as Laboratories, Radiology,
Dietetic Areas, Surgical Rooms, Electrical Rooms, and Telecommunications Rooms.
(g) Conduit runs for all feeder circuits shall be shown on plans as close to the location of final
installations as possible to avoid field installation conflicts which are likely to cause costly
construction change orders and delays. These conduit runs shall be shown to run in parallel
with the building outline and be coordinated with existing field conditions and new
installations of electrical and other systems. These conduit runs shall have the appropriate
1.10 CALCULATIONS
1.10.1 GENERAL
It is the responsibility of the A/E to prepare and submit, or specify calculations, study and
analysis as required by the type of design work performed. Calculations shall justify electrical
designs; size of each conductor, raceway, overcurrent protective device, equipment bus,
generator, transformer, etc.; setting of each overcurrent protective device with adjustable
characteristic; required personal protective equipment (PPE) to meet arc flash energy levels;
etc. It is the responsibility of the A/E to determine which calculations to perform and which
calculations to specify for the Contractor to perform. Not all calculation types shall be required
for all projects. CO, PM or COR reserves the right to request additional calculations to meet
project scope and requirements.
The selection of specific electrical power equipment manufacturer in the design phase is likely
to occur only in unusual circumstances with the intent to mitigate urgent VA needs. If specific
electrical power equipment manufacturer is selected during the design phase, the A/E shall
prepare and perform Fault Current, Protective Device Coordination, and Arc Flash calculations,
study and analysis. The A/E shall use the Master Specification Section 26 05 73, OVERCURRENT
PROTECTIVE DEVICE COORDINATION STUDY, as a basis to perform these tasks. The A/E shall
provide written reports of all calculations, study and analysis to CO, PM, COR and the
Contractor. The A/E shall coordinate and collaborate with CO, PM, COR, the Contractor, and
the selected equipment manufacturer in setting and adjusting the electrical power equipment
according to the results of the calculations, study and analysis. The purpose is to ensure that
the manufacturer’s equipment functions and operates safely as intended.
However, in a typical major and minor project, electrical power equipment manufacturer is not
selected during the design phase. Selection of electrical power equipment manufacturer occurs
during the construction phase, and this information is not available to the A/E during the design
phase. Due to the different electrical characteristics of different manufacturers of the same
equipment, not knowing the selected equipment manufacturer during the design phase
impedes the A/E’s ability to perform the Protective Device Selective Coordination and Arc Flash
calculations and analysis effectively. In order to mitigate this issue, the A/E shall include Master
Specification Section 26 05 73 in the construction contract document, and follow additional
guidance listed in Sections 1.10.2, 1.10.3 and 1.10.4.
Specification Section 26 05 73. The A/E shall inform CO, PM and COR of any deficiency in
calculations and reports shown in the submittals that potentially affect the safety and function
of the systems. The A/E shall recommend mitigating actions to CO, PM and COR. The A/E shall
coordinate and collaborate with CO, PM and COR, the Contractor and selected equipment
manufacturer in the process of finalizing information for arc flash calculation and analysis.
1.11.1 REFERENCES
Refer to H-18-8, "VA Seismic Design Requirements." Coordinate with the Structural Engineer
so that seismic bracing is provided as required.
1.11.2 DRAWINGS
Contract drawings shall show the detail methods of anchoring electrical equipment. Drawings
shall include the size, number, and type of anchors and fasteners to be used to secure the
equipment against the seismic forces and to meet codes. Calculations for equipment anchoring
shall be performed by a licensed structural engineer.
1.14.1 DRAWINGS
For renovation projects, separate demolition drawings are required for all areas involved in the
project. Specific detailing of interfaces between renovated and existing-to-remain conditions
shall be clearly indicated on the drawings. The A/E shall fully describe existing equipment
affected by a renovation project, including but not limited to existing equipment manufacturer,
model, voltage, amperage, and A/C ratings, description, new devices installed, new wires and
cables terminated, etc.
(b) Conduit and boxes in existing walls that are to remain shall be abandoned in place (if not
reused) and the boxes shall be provided with blank covers.
(c) Conduit not intended for reuse in existing or new ceilings shall be removed back to the
power, telecommunications, or signal system source from which it originates.
(d) Conduit run in the existing concrete slab shall be saw-cut off as it enters the slab, and then
sealed with approved sealant to prevent moisture access.
1.14.6 CONDUCTORS
(a) The A/E may provide requirement on the drawings to have the existing conductors
meggered to ensure insulation integrity. Existing conductors that visually have sign of
deteriorated or damaged insulation shall be replaced with new.
(b) All abandoned conductors or conductors shall be removed back to the nearest junction box.
Where the entire circuit is to be removed, the conductors shall be removed back to the
power, telecommunications, or signal system source from which they originate.
(c) New conductors shall not be installed in existing conduit with existing conductors.
1.14.9 PANELBOARDS
(a) Consider panelboards for reuse if physical condition, voltage, current and interrupting
ratings, and circuit capacity requirements are met.
(b) Panelboards shall be installed in new or existing electrical rooms and closets. Panelboards
shall not be installed in the corridor without written approval from CO, PM or COR. Refer to
other sections of this manual for requirements.
(c) In major secondary distribution renovation projects, existing panelboard backboxes may be
used as pullboxes for branch circuit transfer. All branch circuit conductors shall be tagged
to identify the circuit number to which they are being transferred in the new panel. Provide
clear requirements in the contract documents directing the Contractor to revise the circuit
numbers on all junction and device boxes, and wall plates for the entire run.
1.14.12 COMPATIBILITY
(a) New equipment installed shall be compatible with existing components and systems to
which it interfaces.
(b) Electrical sequence of phasing and frequency for 3-phase system shall be compatible and
consistent with the existing electrical power distribution system.
2.1 RACEWAYS
Install all wiring such as feeders, and branch circuit wirings in raceways. Raceways shall be as
specified in PG-18-1, Master Construction Specifications, Division 26. Raceway shall comply
with the definition of the NEC Article 100.
(a) For new construction of large office areas, underfloor power, telecommunications, and
signal systems ducts can be considered only for the following areas:
• Personnel Division
• Registrar Division
• Fiscal Division
• Supply Division
• Other - Any large open office spaces where future flexibility is desirable
(b) Provide duplex receptacle and telecommunications outlet fittings on the underfloor duct to
suit the furniture layout.
(c) Space the underfloor ducts 1.5 M (5 ft) on centers. In structural steel frame buildings, use
trench header and utilize the cellular steel as the raceway. Coordinate with the structural
engineer to ensure that the proper cells are enclosed for raceway use.
• Imaging Equipment Wiring Schedule: the A/E shall show a schedule for all wiring tags
indicating wiring destinations and locations/sizes/types/quantities of all raceways and
wirings.
• Imaging Equipment Shop Drawings: the A/E shall confirm that the proposed imaging
equipment layout as shown on manufacturer’s shop drawings meets latest applicable
codes, regulations, and pre-existing building conditions. The A/E shall verity and
coordinate the design with Imaging Equipment Manufacturer’s representative to ensure
compliance with latest codes and regulations, and pre-existing building conditions.
2.2 GROUNDING
The grounding system shall be shown complete on the one-line diagram with all components
and descriptions from the medium- or low-voltage service to the low-voltage panels, as
applicable for each project. The grounding system shall be shown complete on the One-line
Diagram for the Normal, Standby, and/or Essential Electrical Systems, including but not limited
to generators, automatic transfer switches, electrical equipment, etc.
(d) A ground point shall consist of a driven ground rod and brazed connection to the building
sheath. A No. 6 AWG bare copper conductor shall be used to connect the sheath to the
ground rod.
(e) Where a lightning protection system is provided for the building, the sheath shall also be
bonded at each down conductor location.
3.1 GENERAL
(a) "Receptacle" refers to power duplex receptacles, except where single types are specifically
and clearly noted as single receptacles in the construction document. Provide receptacles,
ground fault current interrupter (GFCI) receptacles, or other special purpose receptacles, as
required by codes, project scope and requirements. All receptacles shall be duplex NEMA
5-20R unless otherwise noted. In patient care buildings, all receptacles shall be UL-listed as
Hospital Grade, in the size, type, and configuration required by codes, project scope and
requirements.
(b) The A/E shall refer to the appropriate Design Guide, where locations of most receptacle are
shown on floor plans.
procedure area as required and defined in the NFPA 99, the IPS design and installation is
optional. If such case occurs, the A/E shall obtain a written waiver from the VA
healthcare governing body and inform CO, PM and COR of the waiver in writing within
24 hours of the waiver receipt.
(c) Each receptacle shall be connected to an IPS on a dedicated circuit in a dedicated homerun
conduit, except for those receptacles mounted in the surgical booms or service columns,
which may be wired two to a circuit. Multiwire circuits are prohibited.
(d) GFCI receptacles are prohibited in surgical/operating rooms.
(e) Wall-mounted receptacles shall be 0.45 M (18 in) above the floor. Receptacles shall be
mounted in a combined power and ground modules. This module is a combination of
receptacles and ground jacks.
(f) The need for a dedicated IPS and special receptacles for surgical lasers or portable
equipment shall be determined on a project-by-project basis, and as required in the VA
Surgical Design Guide. The A/E shall confirm in writing the need of such equipment with
CO, PM and COR, in the design phase of the project.
3.4.8 CORRIDORS
Provide receptacles for general use at no more than 15 M (50 ft) spacing and within 7.62 M (25
ft) of corridor ends., except those in Nursing Unit corridors, where receptacles shall be a
maximum of 12 M (40 ft) spacing. Corridor receptacles shall have dedicated branch circuits.
One dedicated branch circuit shall feed a maximum of six corridor receptacles.
3.4.9 KITCHENS
(a) Coordinate requirements with kitchen equipment list. Provide appropriate receptacles for
each cord-connected piece of kitchen equipment. Other equipment shall be permanently
wired using liquid tight flexible conduit.
(b) For equipment located on an island, provide island-mounted, waterproof, floor pedestal
type receptacles.
(c) Provide a means to disconnect electrical power to all equipment beneath Type I hoods if the
fire suppression is activated.
(b) Open Spaces and Large Rooms: Install receptacles for large administrative rooms in
underfloor raceways (if underfloor duck systems are considered in the design), or in
Tele/Power poles. Refer to SECTION 2.1.4, UNDERFLOOR DUCT SYSTEMS.
3.4.14 STAIRWELLS
Provide a receptacle for vacuum-cleaning on every other floor landing.
4.1 GENERAL
This section covers the Essential Electrical Systems (EES), and Standby Electrical Systems.
4.3 COMMISSIONING
(a) In addition to installation acceptance testing specified in NFPA 110, a commissioning plan
shall be developed, specified, documented, and executed to ensure proper operation of the
Essential Electrical System, both its individual components and the system, as a whole. The
commissioning plan shall include, but not be limited to, all sources of power, paralleling
switchgear, transfer switches, fueling systems, and tank leak detection, interconnections to
other systems, annunciators, load shedding, exercise functions, peak shaving, and
communications pathways between equipment.
(b) The A/E shall prepare control and operation drawing(s) or stipulate that the Contractor
prepare them, as part of system commissioning and operations and maintenance
documents. The drawings shall show all elements of the system and their
interrelationships, including both power and control interconnections and sequences of
operation. Physical locations of equipment shall be included.
4.4.1 GENERATORS
(a) Generator ratings shall comply with the definitions stated in the ISO 8528.
(b) Generators used for the Standby Electrical System shall be rated as shown below:
• Limited Time Running Power (LTP); or
• Emergency Standby Power (ESP) if the maximum power available, that the generating
set can deliver under test, utility power outage or other intentional power outage, is in
compliance with the hours of operation per year for ESP rating. The A/E shall confirm
and obtain written confirmation from CO, PM and COR in the design phase before
incorporating this option into the design.
(c) If separate from the Standby Electrical System generators, generators dedicated to the
Essential Electrical System (EES) shall be rated as Emergency Standby Power (ESP).
4.4.5 LOCATION
(a) Do not locate the first level of distribution of the Standby Electrical System or Essential
Electrical System, such as the generators and paralleling switchgear, in the same room with
other power systems.
(b) In the generator paralleling switchgear or distribution switchboard, Life Safety Branch
overcurrent protective devices shall occupy a dedicated section or sections.
(c) In certain projects where installation of outdoor generator(s) is the only practical, cost
effective, efficient and timely option to meet the demand of project scope and schedule,
the A/E may include outdoor generator(s) in the design providing that the following
conditions are complied with:
• The A/E shall submit a written waiver request to CO and AHJ through PM and COR in
accordance with the guideline provided in the Physical Security Design Manual. The A/E
shall proceed with the design only after receiving written approval from CO and AHJ.
• The A/E shall specify the generator(s) to have proper sound-proof outdoor enclosure(s)
to provide protection against engine noise, environment, fire hazard, as well as to
provide protection for physical security.
compromised. Such variations may particularly occur with certain wiring in separate or
common raceways, with certain functions connected to one or another system or branch,
or with certain provisions for automatically or manually delayed restoration of power from
the alternate (emergency) source of power.
(b) The A/E shall submit a narrative describing the existing conditions and how the new design
best meets the intent of applicable codes and provides an equivalent degree of
performance and reliability.
(c) When adding new ATS to an existing Essential Electrical System, the A/E shall match the
existing pole switching configuration in terms of equipment and design, i.e., 3-pole or 4-
pole transfer switches.
4.7 ESSENTIAL ELECTRICAL SYSTEM FOR NURSING HOMES AND LIMITED CARE FACILITIES
The Essential Electrical System for nursing homes and limited care facilities shall comply with
NFPA 70 and 99.
4.10.1 REQUIREMENTS
Standby Electrical System shall comply with the VA Physical Security Design Manual (PSDM),
and as described below:
(a) A Standby Electrical System may be required by the PSDM to provide full power backup for
Mission Critical facilities. The Standby Electrical System shall be sized for full load operation
of the entire electrical system. The Standby Electrical System must be capable of sustaining
operation of all electrical loads during the electric utility power outage for the duration
required in the PSDM. Additional sustainability time may be required for hurricane-prone
areas, arctic areas, high-seismic areas, areas vulnerable to other natural disasters,
Continuity of Operation (COOP) facilities, or for other locations as specified by CO, PM and
COR.
(b) The Standby Electrical System may be sized to provide power for other new or existing
buildings or loads in addition to the Mission Critical Facility. The A/E shall coordinate this
aspect of the project with CO, PM and COR during the planning phase, and incorporate it in
the design.
5.2.1 GENERAL
(a) Distribution topology shall be primary selective, secondary radial. Primary radial systems
are acceptable with written approval of CO, PM and COR for non-Mission Critical facilities.
(b) Refer to APPENDIX A, DRAWINGS for possible system topologies.
(c) Refer to the VA Physical Security Design Manual for more information.
(c) Primary switchgear for non-Mission Critical facilities may be located outdoors, and may be
pad-mounted fused-switch type.
5.3.1 GENERAL
Healthcare, Research, Clinical and Ambulatory Care Facilities, and Essential Buildings with
l000 kVA or Larger Demand Load: The total building load (calculated demand kVA plus future
growth) shall be served by multiple single-ended unit substations. Low-voltage feeders
between buildings shall be underground.
5.4.1 GENERAL
(a) Power monitoring and metering are in addition to utility metering.
(b) At a minimum, power monitoring and metering equipment shall be provided for both
normal and essential electrical systems: for medium-voltage switchgear on each main and
distribution feeder circuit breaker, unit substation transformer secondary low-voltage main
circuit breakers, generator paralleling switchboards, plug-in busways, and low-voltage
switchboards and major distribution panelboards. The power monitoring and metering
system shall have the capability of communication with a VA-centralized remote metering
station via a data backbone.
(c) At a minimum, power monitoring and metering equipment shall record, store, and trend
voltage, current, kW, kWh, kVA, kVAR, power factor, as well as voltage and current total
harmonic distortion.
5.5.1 GENERAL
(a) An electrical room is an area in a building or structure which contains the following
electrical equipment: medium-voltage switchgear, medium-to-low-voltage transformers,
low-voltage transformers, low-voltage distribution equipment and panelboards. An
electrical closet is an area in a building that contains the following electrical equipment:
low voltage transformers and low-voltage distribution and branch-circuit panelboards.
(b) The location, protection, and access to electrical room and closets shall comply with the
Physical Security Design Manual.
(c) Electrical rooms shall be located above the Base Flood Elevation. Electrical rooms shall not
be located beneath toilets, showers, laboratories, kitchens, sinks, open courtyards, planters,
roof drain leaders, or other areas where water service is provided.
(d) Electrical equipment spaces shall be designed to accommodate code-required working
clearance of electrical equipment, maintenance equipment access, and to facilitate
equipment replacement without significant demolition and reconstruction.
(e) Any pipe or duct system foreign to the electrical installation shall not enter or pass through
an electrical space. The A/E shall ensure that foreign piping such as water pipes, steam
pipes, medical gas pipes, sanitary waste pipes, roof drains, A/C ducts, and other unrelated
piping systems containing liquids or gases are not installed, nor pass through the electrical
rooms. Sprinkler piping shall not be routed through electrical rooms, unless it serves to
protect the electrical installation.
(f) Electrical spaces shall have the necessary mechanical ventilation or cooling system to
maintain the indoor temperature range required for proper operation of the equipment.
6.1 GENERAL
VA uses nonflammable anesthetics in Operating Rooms of Surgical Service and Medical
Research Service. Installations in these areas shall conform to the NFPA 99 that pertain to
nonflammable anesthetics.
monitor medical gas alarms provided that the alarm signals are programmed as a
supervisory signal and do not initiate the building fire alarm system.
APPENDIX A: DRAWINGS
The drawings show two possible topologies for normal and essential electrical system
equipment. The A/E shall follow these topologies for the electrical power distribution design.
Drawings A-1
PG 18-10 – ELECTRICAL DESIGN MANUAL December 1, 2019
Drawings A-2
PG 18-10 – ELECTRICAL DESIGN MANUAL December 1, 2019
Drawings A-3