General Requirements
A building permit is required for all accessory buildings where:
Shoreline Residential (SR) lots under Zoning By-law 2014-21, the following would
apply:
Building Height: The maximum height for an accessory structure is 6.5 m (21.3 ft.)
Rural (RU) lots under Zoning By-law 2014-21, the following would apply:
Building Height: The maximum height for an accessory structure is 6.5 m (21.3 ft.)
Note: All accessory structures must comply with the Township of Perry’s
Zoning By-law. If you are unsure whether the accessory structure complies or
not, please contact the Building Services Department at 705-636-5941.
2
Application Requirements
• Completed building permit application forms.
• Two copies of the most recent survey or detailed site sketch for the property
showing dimensions of all existing buildings and structures, and their
setbacks, drawn to scale. The proposed garage or shed is to be plotted on the
site plan and setback dimensions to all property lines are to be shown. (See
attached sample site plan on page 5).
• The current permit fee, payable at time of application by cheque, cash, debit,
credit card (2% additional fee) or electronic payment. Cheques are made
payable to “The Township of Perry”. If choosing to make an online banking
payment, please contact the municipality to obtain the online banking number.
Create or modify a copy of your own survey or site plan. Include all the
dimensions and information as shown on the sample.
Create your own or modify the sample to show all of your openings and
structural information. Refer to page 11 for structural detail to assist you with
framing construction. If engineered roof trusses are to be used then label
‘Engineered Roof Trusses’ on the Floor Plan.
Create your own or modify the sample to show all of your openings. Note the
direction each elevation is facing in the title block under each elevation (i.e.
North, South, East, West). No openings are permitted in a wall within 4 feet of
a property line.
3
4. Building Section – Refer to the “Building Section” on page 8.
Create your own or modify the sample provided to show framing details and
building height. If a truss system is used please include the wording, “Trusses
as per attached” on the drawing and attach the engineered stamped truss
drawings to your application.
There are 4 foundation options to choose from based on site conditions, cost,
and use of the building. Select the foundation you wish to use for your building
and provide the construction detail with your drawing. ‘Pier Type’ foundations
with wood floors and ‘Mud Sill’ foundations are to be used for sheds only to
maximum size of 55 m2 (592 sq. ft.) and are not designed to support the
weight of motorized vehicles.
Electrical work requires a permit from Hydro One. A copy of the approved final
electrical report from ESA will be required by the Township at the time of final
inspection for your building. Contact numbers for Hydro One 1-888-664-9376
and ESA 1-877-372-7233.
Note: Please provide your own shed or garage plans if your shed or garage is
different from what is shown in this package (use the same concept and provide
the same information). You will also need to provide your own details if the
proposed construction methods differ from those provided.
4
Sample Site Plan Sketch
Dimension your own site plan similar to the one below and include the required
information as set out in ‘Site Information’ table.
SITE INFORMATION:
SITE FEATURES AREA (ft²/m²)
Area of lot:
Footprint of house:
Footprint of existing accessory buildings:
Footprint of proposed shed/garage:
Length of shoreline:
5
Sample Floor Plan
Draw a floor like the sample below and include building features such as truss/rafter direction/location and
spacing on centre, window and door openings with header/lintel sizes, stud wall sizes with spacing on
centre, eve overhang, etc.
6
Elevations
Label the building elevations (i.e. front, right, left and rear) or by indicating the
facing directions (North, South, East, West). Be sure to include building features
(i.e. window and door openings), size of openings and header/lintel sizes above the
openings.
Note: Refer to the Framing Tables on page 11 to assist you with the Framing
Structural Details.
7
Sample Building Section
Draw a building cross section and indicate overall building height, soffit overhang, wall and roof framing.
8
Sample Foundation Design
NOTES: NOTES:
1) Ensure pier footing base has proper footing 2) Mud Sill Foundations require earth anchorage.
(i.e. Bigfoot tube) 3) Maximum 55m2 (592 sq. ft.), one story wood
frame
9
Frost Wall Foundation Concrete Pad Type Foundation
(Single storey only, less than
55 sq. m. (592 sq. ft.)
NOTES:
1) Concrete pad larger than 55 sq. m. to be
designed by engineer
10
Framing Tables
10’ 18”Ø 22”Ø 24”Ø 28”Ø 2-2X6 2-2X8 2-2X10 2-2X12 2X8
12’ 20”Ø 24”Ø 28”Ø 30”Ø 2-2X6 2-2X8 2-2X10 2-2X12 2X10
• Use pressure treated lumber when in close proximity to finished grade (ground)
11
Cut Away Garage Diagram (for information purposes only)