DATE APPROVED QR NUMBER
INSPECTION CHECKLIST
Pipes and Fittings Material Receiving PIPING
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
AKRO2
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT
NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & QUANTITY INSP. MH's TRAVEL
TIME SPENT TIME
TIP NUMBER ACTIVITY NUMBER WORK PERMIT
REQUIRED?
INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
RE-
ITEM
ACCEPTANCE CRITERIA PASS FAIL N/A INSP
No.
DATE
Delivered equipment/material shall be free of damage and shall
conform to all applicable requirements, including contractor's
A1
inspection release, when applicable, with verified material test
reports (MTR)
Receipt handling, lifting, unloading and transport shall be
A2
performed in accordance with manufacturer procedures.
Joining kits (adhesive bonds, lubricants, etc.) shall be inspected for
A3 conformance to the manufacturer installation manual and the
Engineering Design, and for evidence of damage or tempering.
The ends shall be checked for missing or broken end protectors. All
threads should be protected with thread protectors. The
manufacturer shall apply external and internal closed end thread
A4 protectors to protect the ends and all exposed threads of the pipe,
coupling, and fitting from damage under normal handling and
transportation. Pipe and fittings shall be sealed and protected with
plastic end caps.
Manufacturers shall apply flange face protectors to all flange faces
A5
in accordance with standard industry practice.
All pipe and fittings shall be inspected for conformance to the
A6
Purchase Order specification requirements.
As a minimum, the label shall confirm the pipe manufacturer, size,
material, and pressure rating and product code for each pipe and
A7
fitting shall be verified to be traceable to the material certificate
prior to installation.
Pipes and fittings shall be inspected for evidence of damage or
A8 distortion.(See Appendix A –Visual Inspection Acceptance Criteria -
SAES-L-650)
Pipe edges shall be coated with resin and inspected to be smooth,
A9
not prone to cutting skin on contact.
Threads type and size shall be inspected to be in accordance with
A10
API 15HR.
Pipes and fittings which do not pass receipt inspection, shall be
A11
marked and quarantined pending disposition.
Pipe and fittings shall be examined for evidence of
A12
blisters,burns,cracks,chemical attack and surface resin.
Pipe and fittings shall be examined for evidence of loose fibers or
A13
excessive UV-induced fiber blooming.
REMARKS:
Contractor / Third-Party JV
Construction Representative* JV Representative
Work is Complete and Ready for Inspection: Name, Work
Name, Initials and QC Record
Initials Verifie
Date: Reviewed
and Date: d
Name,
Name, Initials and
Initials
Date:
and Date:
QC Supervisor Others
Quality Record Approved: Name, Work
QC Record
Organizat Verifie
Reviewed
Name, Sign and Date: ion, d
Initials
and Date: