Appendix D Quantites & Cost Estimate
Appendix D Quantites & Cost Estimate
Appendix D Quantites & Cost Estimate
Item No. Item Code Item Description Unit Quantity Unit Price Total
Project Name Rumsey Bridge - Replacement on New Tangent Algnment Project. No. Y01-500
Item No. Item Code Item Description Unit Quantity Unit Price Total
Project Name Rumsey Bridge - Replacement on New Tangent Algnment Project. No. Y01-500
Item No. Item Code Item Description Unit Quantity Unit Price Total
Table of Contents
Repair Spalled Surface Area [SF] ................................................................................................................................................ 3
Remove Unsound Concrete [SF] ................................................................................................................................................. 7
Fiber Wrap [SF] ........................................................................................................................................................................... 8
Reconstruct Bridge Railing [LF] .............................................................................................................................................. 13
Furnish Polyester Concrete Overlay (1”) [CY] ......................................................................................................................... 14
Place Polyester Concrete Overlay [SF] .................................................................................................................................... 15
Clean Bridge Deck [SF] ........................................................................................................................................................... 16
Structure Excavation (Type D) [CY] ........................................................................................................................................ 17
Structure Backfill (Bridge) [CY] .............................................................................................................................................. 20
60” Cast-in-Drilled-Hole Concrete Piling [LF] ........................................................................................................................ 22
84” Cast-in-Drilled-Hole Concrete Piling [EA] ....................................................................................................................... 23
Structure Concrete, Bridge Footing [CY] ................................................................................................................................. 24
Structure Concrete, Bridge [CY] ............................................................................................................................................... 25
Bar Reinforcing Steel (Bridge) [LB] ........................................................................................................................................ 26
Joint Seal (Type B) [LF] ........................................................................................................................................................... 28
Rehabilitation of Existing RSP [LS] ......................................................................................................................................... 29
Prestressing Cast-In-Place Concrete [LS] ................................................................................................................................. 30
Approach Roadway Rehabilitation [LF] ................................................................................................................................... 30
Temporary Bridge [LS] ............................................................................................................................................................ 30
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 3 of 30
Average vertical hanger length = (14.3’ + 18.7’ + 20.8’ + 20.8’ + 18.7’ 14.3’) / 6 = 18’
Stevenson Bridge –Area of Repair Required is much smaller than Rumsey Bridge:
In 2007, the Stevenson Bridge unit price for Repair Spalled Surface Area is $200/SF, the estimated area of repair is
100SF. As shown in the Stevenson photos below, the concrete is in much better condition than that of the Rumsey
Bridge, which totals to $20k for the Stevenson Bridge. (Compared to $285k for the Rumsey Bridge)
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 7 of 30
Stevenson Bridge – Remove Unsound Concrete is much smaller than Rumsey Bridge:
As shown in the Stevenson photos previously, the concrete is in much better condition than that of the Rumsey Bridge.
In 2007, the Stevenson Bridge unit price for Repair Spalled Surface was $100/SF. The estimated area of repair was
100SF, which totals to $10k. (Compared to $12.5k for the Rumsey Bridge)
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 8 of 30
Based on the preliminary feasibility analysis performed for this study, the following FRP sizes are estimated: On the
top and bottom (strong axis fibers) of the arch, approximately 5 Layers of 0.04” of the Fyfe’s Fyfo SCH-41 Carbon FRP
system (Total 0.08”) will be applied to limit FRP strain demand. Though, in the strong axis FRP for strengthening
improvement is not required, per the manufacturer’s FRP elongation limits, the calculated deformation base on stress
strain requires 2 layers of FRP on the strong axis.
On the side faces (inside and outside faces / weak axis fibers) of the arch, approximately 8 Layers of 0.04” FRP (Total
0.32”) will be applied to increase the arch’s minor axis flexural capacity. The strain and stress limit based on
manufacturer’s design limit are met. At the spring line outside face (exterior of bridge), the FRP must bonded to the Tie
Girder and lapped with the Tie Girder FRP to develop the FRP strength.
At the spring line inside face (interior of bridge), the FRP must to be fed through a drilled hole on the deck and make
bonded to the Tie Girder. Lastly, 2 layers of FRP will be bonded in the perpendicular direction and wrap around the arch
section to provide additional confinement and continuity. The red block above indicates the approximate location of
where the Arch will be retrofitted.
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 9 of 30
The Vertical Hanger Retrofit entails applying FRP on the exterior of the Hangers for flexural and shear strength. On the
top and bottom (strong axis fibers) of the arch, 6 Layers of 0.04” FRP (Total 0.24”) is required to increase the hanger’s
major axis flexural capacity. On the side faces (inside and outside / weak axis fibers) of the Hanger, 3 Layers of 0.04”
FRP (Total 0.12”) will be applied to increase the hanger’s minor axis flexural capacity. Additionally, 2 layers of FRP
will be bonded in the perpendicular direction and wrap around the Arch section.
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 10 of 30
The Portal Retrofit entails applying FRP on the exterior of the Portal Bracing for flexural and shear strength. On the top
and bottom (strong axis fibers) of the Portal Bracing, 4 Layers of 0.04” FRP (Total 0.16”) applied to increase the Portal’s
major axis flexural capacity. On the side faces (inside and outside / weak axis fibers) of the Portal, 4 Layers of 0.04”
FRP (Total 0.16”) will be applied to increase the Portal’s minor axis flexural capacity. Additionally, 2 layers of FRP will
be bonded in the perpendicular direction and wrap around the arch section.
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 11 of 30
The Tie Girder Retrofit entails bolstering the interior of the Tie Girders and applying FRP on the exterior of the Tie
Girder for strength. The interior bolster will include drill and bond #5 dowels at 12” spacing (horizontally and
vertically) to create a composite section of the existing Tie Girder. A total of 7 #9 bars will be placed on the inside face
of the girder. The internal floor beams must be cored for the #9 bars to pass through the floor beam. On the out face of
the Tie Girder, 2 Layers of 0.04” FRP (Total 0.08”) will be applied to increase bending strength in the opposite direction.
This strategy allows the retrofit to be applied where is needed. The red sections above indicate the approximate location
of where the Tie Girder will be retrofitted.
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 12 of 30
Based on Caltrans bid history, there have been few FRP projects. The FRP bid item names also are different. The
average adjusted prices are listed below. The FRP unit costs obtained from Caltrans bid history are for information only.
GLASS FIBER REINFORCED POLYMER REPAIR (EPOXY INJECTION) Price $77/SF Qty 50 SF
WET LAY-UP GLASS FIBER REINFORCED POLYMER COMPOSITE Price $60/SF Qty 1650 SF
PREPARE FIBER REINFORCED POLYMER DECK SURFACE Price $2/SF Qty 8050 SF
FURNISH FIBER REINFORCED POLYMER DECK PANEL 5" THICK Price $116/SF Qty 8600 SF
Bridge Length = [(311’ of Total Bridge Length from Abut1 to Abut5) (2 EA) + (50’ Abut1 WW) (2 side) + (25’ Abut5
WW by scale) (2 EA) ] = 772 ft
Say 780 LF
Estimated price = $250/LF
Based on Caltrans bid history, the Reconstruct Bridge Railing is $100/LF. However, for the Rumsey project,
reconstructing the bridge railing to match the existing appearance requires specialized forms. Therefore, a higher unit
price is used. Note: Reconstruction of the bridge railing is required to fully wrap the FRP full height of the Vertical
Hanger.
Bridge Area = (313’ Total Bridge Length from Abut1 to Abut5) (20’ deck width) = 6,260 SF
x 1”/12 / 27CY
= 19.3 CY
Say 20 CY
Estimated price = $3,000/CY
Based on Caltrans bid history, the average adjusted Furnish Polyester Concrete Overlay is around $2,250. Accounting
for remote location, use $3,000/CY for Rumsey Bridge.
Abutment 1 location:
Pier 2 location:
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 18 of 30
Abut 1: [ (33’ tall from deck to bottom of Abut 1 footing) (22’ wide at Abut 1 face) (12’ length, longitudinally) ] /
27
= 330 CY
Pier 2: [(8’ high) (48’ long + 1’ +1’ ) (12’ wide + 8’ + 3’ for PS) ] / 27
= 340 CY
Pier 3: [(8’ high) (48’ long + 1’ +1’ ) (12’ wide + 8’ + 3’ for PS) ] / 27
= 340 CY
Pier 4: [(8’ high) (48’ long + 1’ +1’ ) (12’ wide + 8’ + 3’ for PS) ] / 27
= 340 CY
Abut 5: [ (26’ tall from deck to bottom of Abut 5 footing) (22’ wide at Abut 1 face) (12’ length, longitudinally) ] /
27
= 250 CY
∑ = 1,600 CY
Say 1,600 CY
Pier 2: [(8’ high) (48’ long + 1’ +1’ ) (12’ wide + 8’ + 3’ for PS) ] / 27
= 340 CY
Less two concrete footing retrofit
[ (8’ tall) (48’ wide) (12’ length) ] / 27
= 170 CY
= 170 CY
Pier 3: [(8’ high) (48’ long + 1’ +1’ ) (12’ wide + 8’ + 3’ for PS) ] / 27
= 340 CY
Less two concrete footing retrofit
[ (8’ tall) (48’ wide) (12’ length) ] / 27
= 170 CY
= 170 CY
Pier 4: [(8’ high) (48’ long + 1’ +1’ ) (12’ wide + 8’ + 3’ for PS) ] / 27
= 340 CY
Less two concrete footing retrofit
[ (8’ tall) (48’ wide) (12’ length) ] / 27
= 170 CY
= 170 CY
Abut 5: [ (26’ tall from deck to bottom of Abut 5 footing) (22’ wide at Abut 1 face) (12’ length, longitudinally) ] /
27
= 250 CY
Less two 60” CIDH Piles and concrete attachment.
[ (33’ tall from deck to bottom of Abut 1 footing) (14’ wide) (7’ length) ] / 27
= 120 CY
= 130 CY
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 21 of 30
∑ = 850 CY
Say 850 CY
Abut 1 Wingwall:
(60 CY) (100 lb / CY) = 6,000 lb
Abut 1 CIDH to Abut Stem attachment:
(33’ tall from deck to bottom of Abut 1 footing) (20’ wide at Abut 1 face) (4’ length,
longitudinally) (100 lb / CY) = 10,000 lb
Pier 2 Footing:
(108 CY) (180 lb / CY) = 20,000 lb
Pier 3 Footing:
(108 CY) (180 lb / CY) = 20,000 lb
Pier 4 Footing:
(108 CY) (180 lb / CY) = 20,000 lb
Abut 5 CIDH to Abut Stem attachment:
(26’ tall from deck to bottom of Abut 1 footing) (20’ wide at Abut 1 face) (4’ length,
longitudinally) (100 lb / CY) = 8,000 lb
Abut 1 CIDH:
(70 LF) (20 EA #11)(1.56 sq-in) (490 lb/CF) / (12 in)^(2) = 7,500 lb
2 pier = [(60” 3”x2 ) /12 ft] [pi] [0.31 sq-in / (12 in)^(2)] [490 lb/CF]
x [70’] / [9’/12] = 1,400 lb
Pier 2 CIDH:
(110 LF) (36 EA #11)(1.56 sq-in) (490 lb/CF) / (12 in)^(2) = 21,000 lb
2 pier = [(84” 3”x2 ) /12 ft] [pi] [0.31 sq-in / (12 in)^(2)] [490 lb/CF]
x [110’] / [9’/12] = 3,000 lb
Pier 3 CIDH:
(110 LF) (36 EA #11)(1.56 sq-in) (490 lb/CF) / (12 in)^(2) = 21,000 lb
2 pier = [(84” 3”x2 ) /12 ft] [pi] [0.31 sq-in / (12 in)^(2)] [490 lb/CF]
x [110’] / [9’/12] = 3,000 lb
Pier 4 CIDH:
(110 LF) (36 EA #11)(1.56 sq-in) (490 lb/CF) / (12 in)^(2) = 21,000 lb
2 pier = [(84” 3”x2 ) /12 ft] [pi] [0.31 sq-in / (12 in)^(2)] [490 lb/CF]
x [110’] / [9’/12] = 3,000 lb
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 6-10-2014
Subject: Quantities – Retrofit Rehab Alt
Page: Page 27 of 30
Abut 5 CIDH:
(70 LF) (20 EA #11)(1.56 sq-in) (490 lb/CF) / (12 in)^(2) = 7,500 lb
2 pier = [(70” 3”x2 ) /12 ft] [pi] [0.31 sq-in / (12 in)^(2)] [490 lb/CF]
x [70’] / [9’/12] = 1,400 lb
∑ = 174,000 LB
Say 174,000 LB
Table of Contents
Structure Excavation (Type D) [CY] .......................................................................................................................................... 3
Structure Backfill (Bridge) [CY] ................................................................................................................................................ 4
108” Cast-in-Drilled-Hole Concrete Piling [LF] ........................................................................................................................ 5
Structure Concrete, Bridge Footing [CY] ................................................................................................................................... 6
Structure Concrete, Bridge [CY] ................................................................................................................................................. 7
Bar Reinforcing Steel (Bridge) [LB] ......................................................................................................................................... 9
Joint Seal (Type B) [LF] ........................................................................................................................................................... 10
Concrete Barrier (Type 732) [LF] ............................................................................................................................................ 11
Rehabilitation of Existing RSP [LS] ......................................................................................................................................... 12
Prestressing Cast-In-Place Concrete [LS] ................................................................................................................................. 13
Bridge Removal ......................................................................................................................................................................... 13
Roadway Items .......................................................................................................................................................................... 13
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 5-19-2014
Subject: Quantities – New Replace Alt
Page: Page 3 of 13
Superstructure :
[ (115 SF) (17+17+21.5 SF hollow cells) ] (400 LF) / 27
= 881 CY
Superstructure Diaps:
[ (17+17+21.5 SF cells) ] (10 + 10 + 2.5 +2.5 LF) / 27
= 51 CY
Abut 1 seat: [(14’ tall) (3.5’ wide) (30’10” long) / 27
= 56 CY
Pier 2 & 3 column: [(20’ tall) (7’ diameter) ^(2) (pi) / (4) / 27 (2 columns)
= 60 CY
Abut 4 seat: [(14’ tall) (3.5’ wide) (30’10” long) / 27
= 56 CY
Wingwall’s: (161 SF wingwall back area)(1’ thick backfill) (4 WW’s) / 27
= 24 CY
∑ = 1128 CY
Say 1130 CY
Based on Caltrans Contract Cost Data,
Structure Concrete, Bridge has an average adjusted unit price of $1,000/CY,
Say $1,100 / CY for remote location.
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 5-19-2014
Subject: Quantities – New Replace Alt
Page: Page 8 of 13
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 5-19-2014
Subject: Quantities – New Replace Alt
Page: Page 9 of 13
Box Super: (133.33’ span length) => 185 lb/CY x 1.25 LDF to LRDF
(880 CF) (230 lb/CY) = 178,000 lb
108” CIDH pile: (9 ft)^(2) (pi) / (4) (120 LF) /27 (450 lbs/CY)(2col) = 255,000 lb
∑ = 922,000 LB
Say 920,000 LB
Say 62 LF
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 5-19-2014
Subject: Quantities – New Replace Alt
Page: Page 11 of 13
Say 880 LF
Project Name: Rumsey Bridge Retrofit
Project No . Y01-500
Engineer: J. Chou
Date: 5-19-2014
Subject: Quantities – New Replace Alt
Page: Page 12 of 13
Bridge Removal
Use a unit cost of $400,000 for removing the existing bridge.
Roadway Items
For approach roadway construction see roadway quantities.
Life Cycle Costs
Net Future Value adjusted to the proposed 2017 construction year (in 2017 dollars)
n
FV = PV * (1 + r )
years
Future Cost = Initial Cost * (1 + Annual % Increase)
Annual % increase in Construction Cost = 3%
Future Cost in 2017 to retrofit existing bridge = $11,801,000
Cost of a future bridge if constructed today = $4,500,000 (assumed cost for CIP Conc Box Girder in Alt 3)
n
FV = PV * (1 + r )
years
Future Cost = Initial Cost * (1 + Annual % Increase)
Annual % increase in Construction Cost = 3%
Future Cost in 2067 to construct a new bridge = $21,557,000
Prorated fraction cost to a common 75 year baseline timeframe analysis. (Prorate cost of new bridge to first 25 years of its life.)
Proration multiplier = (75-50)/75 = 25/75 = 0.333
$7,185,667
75 years
n
FV = PV * (1 + r )
years
Future Cost = Initial Cost * (1 + Annual % Increase)
Annual % increase in Construction Cost = 3%
Future Cost in 2017 to construct new bridge = $4,917,000
75 years
Year: 2017
Net Future Value Cost = $4,900,000 for Alternative 3 (rounded to nearst $100,000)
2012/13-2017/18 Highway Bridge Program
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts
programmed in the FTIP.
District: 04 County: Solano
Responsible Agency HBP-ID Project Description
Solano County 1498 BRIDGE NO. 23C0092, STEVENSON BR RD, OVER PUTAH CREEK, SOL/YOL CO LINE. Bridge rehabilitation. No adding lane capacity.
Phase Summary: Prior 12/13 13/14 14/15 15/16 16/17 17/18 Beyond Total Project #:
PE 900,000 400,000 1,300,000 5923(059)
Fund Source Summary: Prior 12/13 13/14 14/15 15/16 16/17 17/18 Beyond Total
Fed $ 720,000 320,000 442,650 5,641,132 7,123,782
Local Match 180,000 80,000 57,350 730,868 1,048,218
LSSRP Bond
Local AC
Total 900,000 400,000 500,000 6,372,000 8,172,000
PE Summary: Prior 12/13 13/14 14/15 15/16 16/17 17/18 Beyond Total
Fed $ 720,000 320,000 1,040,000
Local Match 180,000 80,000 260,000
LSSRP Bond
Local AC
Total 900,000 400,000 1,300,000
R/W Summary: Prior 12/13 13/14 14/15 15/16 16/17 17/18 Beyond Total
Fed $ 442,650 442,650
Local Match 57,350 57,350
LSSRP Bond
Local AC
Total 500,000 500,000
CON Summary: Prior 12/13 13/14 14/15 15/16 16/17 17/18 Beyond Total
Fed $ 5,641,132 5,641,132
Local Match 730,868 730,868
LSSRP Bond
Local AC
Total 6,372,000 6,372,000
Caltrans, Division of Local Assistance 11/15/2013, 11:10 AM Det2 FL4 SmlTxt brf Page 119