Monte Carlo Simulation Assignment 3

This three sentence summary provides the key details from the document: The document presents a quantitative risk analysis assignment involving calculating duration metrics and critical indexes for a project model and simulation data using MS Project and Monte Carlo simulation in @Risk. Students are asked to calculate the median duration, mean duration, probability of completing the project in less than 50 days, critical indexes for each activity and path, based on a simulation data table and project model.

Uploaded by

dhoom234
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views2 pages

Monte Carlo Simulation Assignment 3

This three sentence summary provides the key details from the document: The document presents a quantitative risk analysis assignment involving calculating duration metrics and critical indexes for a project model and simulation data using MS Project and Monte Carlo simulation in @Risk. Students are asked to calculate the median duration, mean duration, probability of completing the project in less than 50 days, critical indexes for each activity and path, based on a simulation data table and project model.

Uploaded by

dhoom234
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

RRC PROJ-1196 Project Risk Management Assignment 3

Quantitative Risk Analysis


This assignment incorporates course content from Week 8 & 9

Simulation Model for Project Risk Management

Project Model using MS Project

(10marks)
Assignment 3: (5 marks)

Given the project model above, and the simulation data table on the next page:
Calculate and identify the:
a) median duration days (1 mark)
b) mean duration days (1 mark)
c) probability of completing the project in less than 50 days % (2
(1 marks)
mark)
(4 mark)
d) critical index for each activity (1 marks)

activity a b c d e f g h
critical index
(2mark)
e) critical index for each path (1 marks)

path abcf abdf abdgh abeh


critical index

Note: The assignment must be submitted in a printer-friendly manner; formatted to


one-page for a), b), c), d) and e); include a page title, your name, and date submitted
on each page. Submit the assignment as a single PDF file.

Page 1
RRC PROJ-1196 Project Risk Management Assignment 3

path path path path


Iteration a b c d e f g h
abcf abdf abdgh abeh
1 10 12 19 6 14 10 17 8 51 38 53 44
2 16 11 7 6 20 10 5 11 44 43 49 58
3 16 12 7 6 14 10 10 11 45 44 55 53
4 10 12 12 6 14 10 17 8 44 38 53 44
5 16 14 7 6 14 10 17 8 47 46 61 52
6 16 12 12 6 14 10 10 8 50 44 52 50
7 10 14 12 6 20 6 17 4 42 36 51 48
8 10 14 19 6 14 6 10 11 49 36 51 49
9 10 14 12 6 10 10 10 11 46 40 51 45
10 10 12 12 6 14 10 5 11 44 38 44 47
11 16 12 12 6 14 10 17 4 50 44 55 46
12 10 12 19 6 14 10 10 8 51 38 46 44
13 16 14 12 6 14 10 10 11 52 46 57 55
14 16 12 12 6 14 10 5 4 50 44 43 46
15 10 12 19 6 20 10 10 4 51 38 42 46
16 8 11 19 6 20 10 10 11 48 35 46 50
17 10 14 7 6 20 10 10 8 41 40 48 52
18 16 11 12 6 20 10 5 8 49 43 46 55
19 8 12 12 6 20 10 10 4 42 36 40 44
20 10 12 19 6 10 10 17 11 51 38 56 43
21 8 11 19 6 10 6 10 11 44 31 46 40
22 8 14 19 6 10 10 10 11 51 38 49 43
23 16 14 12 6 14 10 17 8 52 46 61 52
24 10 14 19 6 14 6 17 8 49 36 55 46
25 10 12 12 6 20 10 17 11 44 38 56 53

Monte Carlo Simulation using @Risk

Assumptions include:
- data table expressed in days, and a 7 day work week; and
- you are doing a manual calculation from the table above