CAED101 - JucoMartinCarlo - Quiz 3
CAED101 - JucoMartinCarlo - Quiz 3
CAED101 - JucoMartinCarlo - Quiz 3
Management Science
ACN1Ar
Quiz 3
For Taylor III (2013, p.349), Critical Path Method (CPM) used a single activity time
estimate, and in the network, activities were nodes. Diagram below shows the
branches and nodes.
In CPM’s illustrations, the nodes represent the project activities while the branches with
arrows in between the nodes indicate the precedence relationships between activities.
This approach to constructing network is called activity on-nodes (AON).
About the network above: The branches or arrows simply show the precedence
relationships between the activities. Also, notice that there is no dummy activity (see
next question #2); dummy activities are not required in an AON network because no two
activities have the same start and ending nodes, so they will never be confused.
2. What is project evaluation and review technique?
According to Taylor III (2013, p.349), Project Evaluation and Review Technique
(PERT) used multiple activity time estimates, and in the network, activities were lines
between nodes.
In PERT’s illustration, the branches in between the nodes represent activities, and the
nodes reflect events or points in time such as the end of one activity and the start of
another. This approach is called activity-on-arrow (AOA), and the activities are identified
by the node numbers at the start and end of an activity.
About the network above: The precedence relationships are reflected in this network by
the arrangement of the arrowed (or directed) branches. The first activity in the project is
to design the house and obtain financing. This activity must be completed before any
subsequent activities can begin. Thus, activity laying the foundation, and activity
ordering and receiving materials, can start only when node 2 is realized, indicating that
activity has been completed. The number 3 above this branch signifies a time estimate
of 3 months for the completion of this activity. Activity 2→3 and activity 2→4 can occur
concurrently; neither depends on the other, and both depend only on the completion of
activity 1→2. A dummy activity (activity 3→4) shows a precedence relationship but no
passage of time.
3. Distinguish CPM from PERT.
BASIS FOR
PERT CPM
COMPARISON
According to Taylor III (2013, p.340), project management generally includes the
following basic elements:
Sources: