Bill of Quantities: Project: Two Storey High Residential Building (Single-Attached) QUANTITY: 118.7 Unit: SQ.M

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

BILL OF QUANTITIES

PROJECT: TWO STOREY HIGH RESIDENTIAL BUILDING (SINGLE-ATTACHED)


QUANTITY: 118.7
UNIT: SQ.M
ITEM DESCRIPTION & SCOPE OF WORK QUANTITY UNIT UNIT COST COST
1 EXCAVATION & DISPOSAL WORKS 61.94 cu.m
Footings & Septic Tank 61.94 cu.m
Labor
6 Laborer 3 days 365 6,570
Driver 1 day 510 510
Equipment
Truck 1 day 2,500 2,500
SUBTOTAL ₱9,580.00
UNIT COST ₱154.67
2 MASONRY WORKS 16.038 cu.m
Materials
FOOTINGS 2.205 cu.m
Cement 13 bags 273.21 3,552
Screened Sand 1.11 cu.m 1,550 1,720.50
Gravel 2.21 cu.m 1,590 3,513.90
COLUMNS 4.221 cu.m
Cement 61 bags 273.21 16,666
Screened Sand 2.11 cu.m 1,550 3,270.50
Gravel 4.22 cu.m 1,590 8,299.80
BEAMS 0.67 cu.m
Cement 10 bags 273.21 2,732.10
Screened Sand 0.34 cu.m 1,550 527
Gravel 0.67 cu.m 1,590 1,065.30
SLABS 8.492 cu.m
Cement 122 bags 273.21 33,332
Screened Sand 4.25 cu.m 1,550 6,587.50
Gravel 8.492 cu.m 1,590 13,502.28
Formworks and Scaffolding 1 lot 20,000 20,000
Labor
1 Foreman 10 days 750 7,500
2 Mason 10 days 550 11,000
4 Laborer 10 days 365 14,600
Equipment
One-Bagger Concrete Mixer 40 hrs. 480 19,200
SUBTOTAL ₱167,068.04
UNIT COST ₱10,417.01
3 CONCRETE WORKS 178.606 sq.m
Materials
Concrete Hollow Block (150 mm) 1,500 pcs 24.87 37,305.00
Concrete Hollow Block (100 mm) 895 pcs 11.71 10,480.45
RSB 12 mm Ø, @ 6m 125 pcs 221 27,625
RSB 10 mm Ø, @ 6m 45 pcs 156 7,020
Cement 183 bags 273.21 49,997.43
Screened Sand 15.77 cu.m 1,550 24,444
Tie Wire #12 24 kgs 76.78 1,842.72
Labor
1 Foreman 20 days 750 15,000
2 Mason 20 days 550 22,000
4 Laborer 20 days 365 29,200
Equipment
One-Bagger Concrete Mixer 80 hrs. 480 38,400
Concrete Vibrator 80 hrs. 402 32,160
SUBTOTAL ₱295,474.10
UNIT COST ₱1,654.33
4 STEEL WORKS 1 lot
Materials
RSB 16 mm Ø, @ 6m 177 pcs 392 69,384
RSB 12 mm Ø, @ 6m 87 pcs 221 19,227
RSB 10 mm Ø, @ 6m 403 pcs 156 62,868
Tie Wire #16 220 kgs 71.53 5,293.22
I-Beam, Wide Flange8 X 8 X 40# 7 lengths 19,957 139,699
Hollow Square Tube 1"Ø, @ 6m 2 lengths 940 1,880
Stainless Steel Pipe 2"Ø, @6m 4 lengths 2,038 8,152
Welding Rod 40 kgs 180 7,200
Labor
1 Foreman 10 days 750 7,500
2 Welder 10 days 560 11,200
4 Laborer 10 days 365 14,600
3 Steelman 10 days 550 16,500
Equipment
Welding Machine 20 hrs. 840 16,800
Bar Cutter 20 hrs. 300 6,000
Bar Bender 20 hrs. 390 7,800
SUBTOTAL ₱394,103.22
UNIT COST ₱394,103.22
5 ROOFING WORKS 1 lot
Materials
Roof Framing
C-Purlins 1.50mm (2" x 6" x 6m) 24 lengths 980 23,580
C-Purlins 1.1mm (2" x 3" x 6m) 20 lengths 485 9,700
Square Bar 2 lengths 1,427 2,854
Welding Rod 10 kgs 180 1,800
Roof
Ceramic Tile Roof 764 sq. ft. 150 114,600
Polycarbonate Roofing 3 sheets 1,175 3,525
2-1/2" Stainless Tile Roofing Nail 25 lb 554.67 13,866.75
Aluminum Gutter 19 ln. m 1142.1 21,699.90
Ceiling Works
4′ x 8′ x 9mm Gypsum Board 30 sheets 413 12,390
4′ x 8′ x 9mm Gypsum Board Moisture Resistant 10 sheets 528 5,280
Single Furring 25 pcs 107 2,675
Rod suspension hanger w/adjustment spring 80 set 65 5,200
Pre-formed wire clip 80 set 3.03 242.4
Wall Angle 10 pcs 38 380
Ficem Screw 1000 pcs 0.75 750
Labor
1 Foreman 10 days 750 7,500
3 Carpenter 10 days 600 18,000
2 Welder 10 days 560 11,200
4 Laborer 10 days 365 14,600
Equipment
Welding Machine 20 hrs. 840 16,800
Air Compressor 20 hrs. 350 7,000
SUBTOTAL ₱293,643.05
UNIT COST ₱293,643.05
6 PLUMBING WORKS 1 lot
Materials
Water Closet 2 sets 10,509 21,018
Bidet 2 sets 1,382 2,764
Lavatory 2 sets 2,209 4,418
Bathtub with Shower 1 set 19,829 19,829
Shower 1 set 10,362 10,362
Kitchen Sink 1 set 6,692 6,692
Utility Faucet 1 set 1,025 1,025
Septic Vault (Pipes and Fittings) 1 lot 1,250 1,250
Fittings & Accessories for Cold Water, Storm, & Sewer 1 lot 25,000 25,000
Labor
1 Foreman 10 days 750 7,500
2 Plumber 10 days 560 11,200
4 Laborer 10 days 365 14,600
SUBTOTAL ₱125,658.00
UNIT COST ₱125,658.00
7 ELECTRICAL WORKS 1 lot
Materials
Lighting Fixtures and Accessories 1 lot 65,000 65,000
Wires and Conduits 1 lot 50,000 50,000
Labor
1 Foreman 5 days 750 3,750
2 Electrician 5 days 560 5,600
2 Laborer 5 days 365 3,650
SUBTOTAL ₱128,000.00
UNIT COST ₱128,000.00
8 DOORS AND WINDOWS 1 lot
Materials
Doors
D1 - Narra Paneled Door (1.2m × 2.1 m) 2.52 sq.m 5,653 14,245.56
D2 - Glass Transom on Wood Door (0.9m × 2.1 m) 1.89 sq.m 2,048 3,870.72
D3 - Glass Transom on Wood Door (0.9m × 2.1 m) 1.89 sq.m 2,048 3,870.72
D4 - Flush Type Solid Core Door (0.7m × 2.1 m) 1.47 sq.m 1,821 2,676.87
D5 - Tanguile Paneled Door (0.8m × 2.1 m) 1.68 sq.m 4,886 8,208.48
D6 - Flush Type Solid Core Door (0.8m × 2.1 m) 1.68 sq.m 4,886 8,208.48
D7 - Flush Type Solid Core Door (0.8m × 2.1 m) 1.68 sq.m 4,886 8,208.48
D8 - Flush Type Solid Core Door (0.7m × 2.1 m) 1.47 sq.m 1,821 2,676.87
D9- Sliding Glass Door (1.5m × 2.0 m) 1 set 20,000 20,000
Stainless Lockset 1 set 4,999 4,999
Keyed Lever Lock 5 sets 749 3,745
Keyless Bathroom Lever Lock 2 sets 689 1,378
Sliding Lock with Handle 1 set 999 999
Hinges 8 sets 439 3,512
Windows
W1 - Aluminum Casement Window (1.2m x 1.2m) 4 sets 7,424.64 29,698.56
W2 - Fixed Glass Window on Metal Frame (1.0 m x 5.0 m) 5 sq.m 484 2,420
W3 - Awning Type Steel Casement Window (0.8 m x 0.6m) 2 sets 947 1,894
W4 - Sliding Aluminum Window (1.8m x 1.2m) 2.16 sq.m 5,889 12,720.24
Glazing
Railing with 12mm thk Clear Tempered Glass x 0.8m H 18 ln.m 1,008.50 18,153
Labor
1 Foreman 5 days 750 3,750
2 Glass Installer 5 days 700 7,000
2 Laborer 5 days 365 3,650
SUBTOTAL ₱165,884.98
UNIT COST ₱165,884.98
9 TILEWORKS 118.7 sq.m
Wood Plank Floor Tile (0.2m × 1.2 m, @ 5pcs per box) 67 boxes 1,300 87,100
Matte Floor Tile (0.6m × 0.6 m, @ 4pcs per box) 29 boxes 780 22,620
Tile Trim 10ft 7 pc. 75 525
Portland Cement Type 1 10 bags 275 2,750.00
Screened Sand 3 cu.m. 1,550.00 4,650.00
ABC Grout (2 kgs.) 12 packs 140 1,680.00
Labor
1 Foreman 3 days 750 2,250
2 Tiler 3 days 450 2,700
2 Laborer 3 days 365 2,190
Equipment
Electric Grinder 3 days 300 900
Tile Cutter 3 days 350 1,050
SUBTOTAL ₱128,415.00
UNIT COST ₱1,081.84
10 PAINTING WORKS 357.21 sq.m
Materials
Paint Latex Semi-Gloss 12 gals. 650 7,800
Paint Primer Solvent 12 gals. 635 7,620
Concrete neutralizer 1 gals. 422 422
Lacquer Putty 10 ltr 167 1,670
Masking Tape 3 rolls 55 165
No.120 Sand Paper 2 dozens 123 246
Brush Paint (101mm) 2 pcs 72 144
Brush Roller (152mm) 2 pcs 84 168
Labor
1 Foreman 5 days 750 3,750
4 Painter 5 days 560 11,200
4 Laborer 5 days 365 7,300
SUBTOTAL ₱40,485.00
UNIT COST ₱113.34

TOTAL COST ₱1,748,311.39


UNIT COST ₱147,728.82

Prepared by:
ENGR. JAN MARIE LLAUSAS
Civil Engineer