0% found this document useful (0 votes)
43 views20 pages

Report On Work Force June 2019

The document reports on the workforce status at the Chamkani Depot site of the Peshawar BRT project on June 26, 2019. It lists 20 areas of work at the depot, the number of workers in each area, and the major work activities. The total workforce is 334 people engaged in tasks such as plastering, painting, brickwork, steel fixing, and formwork across various buildings at the depot including the workshop, rest areas, washing bays, KPUMA office building, and Park & Ride building. Pictures show progress on activities like plastering, brick masonry, reinforcement, and formwork.

Uploaded by

Muhammad Arif
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views20 pages

Report On Work Force June 2019

The document reports on the workforce status at the Chamkani Depot site of the Peshawar BRT project on June 26, 2019. It lists 20 areas of work at the depot, the number of workers in each area, and the major work activities. The total workforce is 334 people engaged in tasks such as plastering, painting, brickwork, steel fixing, and formwork across various buildings at the depot including the workshop, rest areas, washing bays, KPUMA office building, and Park & Ride building. Pictures show progress on activities like plastering, brick masonry, reinforcement, and formwork.

Uploaded by

Muhammad Arif
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 20

Report On Work Force Status for Peshawar BRT Project (Chamkani Depot)

Date: 24 June 2019


Workforce
S.No Area Major Work Remarks
Nos.
A Chamkani Depot & Parking Area

1 Workshop Building 22 paint + Tile work +Cleaning

2 Rest Areas (Male) 0

3 Rest Areas (Female) 22 Paint +Tile Work

4 UGWT/OHWT & Tube Well 5 Sand Filling

5 Washing Bays/Plants 13 Brick Work + Steel Fixing

6 Depot Fire Fighting Line 0

7 Water Supply Line 0

8 Sewerage Line 0

9 Drain 7 0

10 BUS Parking Area 9 Cleaning

11 Fuel Station 0

12 Inspection Area 0

13 Tyre Shop 0

14 Charging Points 0
Electric Cable Trench and
15 0
Manholes
16 Cable Ducts and Manholes 0

17 Street Lights 0

18 Electrical Substation (Depot) 0

19 Main Gate & Entrance Office 0

20 Boundary Wall (Depot) 25 Paint + Repair+ Security Fencing

B KPUMA Office Building 107 Plaster + Repair + Brick work + Cleaning

C Park & Ride Building 72 Brick Work + Formwork + Steel Fixing

D Electrical Substation (WAPDA) 0

E BS-00 0

F Internal Roads 3 Excavation of Manholes

G Street Lights (Internal Roads) 0

H UGWT (for KPUMA & Park&Ride) 3 Steel Fixing

I WWTP 0

J Drain 8 0

K Drain 13 0

L Boundary Wall (External) 18 Formwork + Brick work + Pointing

Total: 299
Contractor Representative Consultant Representative
Workforce Status at Stations on Peshawar BRT Project
Chamkani Depot Pictures

External Boundary Wall Coping Beam Formwork

Internal Boundary Wall Surface Preparation for Paint work


Female Rest Area External Paint Work

Park & Ride Building Ground Floor Brick Work


Park & Ride Building First Floor Slab Formwork

KPUMA Building External Plaster Work


Depot Cleaning In Progress Workshop External Paint
Report On Work Force Status for Peshawar BRT Project (Chamkani Depot)
Date: 25 June 2019
Workforce
S.No Area Major Work Remarks
Nos.
A Chamkani Depot & Parking Area

1 Workshop Building 14 paint + Tile work

2 Rest Areas (Male) 11 Paint +Tile Work + Public Health Work

3 Rest Areas (Female) 21 Plaster +Electrical + Tile

4 UGWT/OHWT & Tube Well 8 Sand Filling + Removal of Formwork

5 Washing Bays/Plants 15 Brick Work + Steel Fixing

6 Depot Fire Fighting Line 0

7 Water Supply Line 0

8 Sewerage Line 0

9 Drain 7 0

10 BUS Parking Area 11 Cleaning

11 Fuel Station 0

12 Inspection Area 0

13 Tyre Shop 0

14 Charging Points 0
Electric Cable Trench and
15 0
Manholes
16 Cable Ducts and Manholes 0

17 Street Lights 0

18 Electrical Substation (Depot) 0

19 Main Gate & Entrance Office 4 Painting

20 Boundary Wall (Depot) 23 Paint + Repair+ Security Fencing

B KPUMA Office Building 96 Plaster + Paint + Cleaning

C Park & Ride Building 60 Steel Fixing + Formwork

D Electrical Substation (WAPDA) 0

E BS-00 0

F Internal Roads 6 Brick Work + Excavation of Manholes

G Street Lights (Internal Roads) 0

H UGWT (for KPUMA & Park&Ride) 0 Steel Fixing

I WWTP 0

J Drain 8 0

K Drain 13 0

L Boundary Wall (External) 30 Brick Work + Formwork + Pointing

Total: 299
Contractor Representative Consultant Representative
Workforce Status at Stations on Peshawar BRT Project
Chamkani Depot Pictures
Entrance Gate Office External Paint Rest Are

Washing Bay Brick Work in Progress


KPUMA External Plaster Work KPUMA Internal Plaster Work

KPUMA Internal Plaster Work


External Boundary Wall Coping Beam Formwork In Progress

KPUMA Boundary Wall Brick work In Progress

Chamkani Depot Arial View


Park & Ride Columns Steel Park & Ride Slab Formwork

Park & Ride Columns Formw Park & Ride Columns Formwork/Scaffolding
Workshop Paint Work Sand Filling Aroung UG

Workshop Paint Work Rest Area Paint Work


Report On Work Force Status for Peshawar BRT Project (Chamkani Depot)
Date: 26 June 2019
Workforce
S.No Area Major Work Remarks
Nos.
A Chamkani Depot & Parking Area

1 Workshop Building 32 paint + Tile work + Plumbing

2 Rest Areas (Male) 11 Paint +Tile Work + Plaster

3 Rest Areas (Female) 7 Plaster + Paint+ Plumbing

4 UGWT/OHWT & Tube Well 0 Sand Filling + Removal of Formwork

5 Washing Bays/Plants 13 Brick Work + Steel Fixing

6 Depot Fire Fighting Line 0

7 Water Supply Line 0

8 Sewerage Line 0

9 Drain 7 0

10 BUS Parking Area 13 Cleaning

11 Fuel Station 4 Sand Filling

12 Inspection Area 0

13 Tyre Shop 0

14 Charging Points 0
Electric Cable Trench and
15 0
Manholes
16 Cable Ducts and Manholes 0

17 Street Lights 0

18 Electrical Substation (Depot) 5 Preparation for Rigid Around Sub Station

19 Main Gate & Entrance Office 3 Painting

20 Boundary Wall (Depot) 17 Paint + Surface Preparation

B KPUMA Office Building 117 Plaster + Formwork of Shear Wall

C Park & Ride Building 77 Steel Fixing + Formwork + Brick work

D Electrical Substation (WAPDA) 0

E BS-00 9

F Internal Roads 0 Plaster of Manholes + Electrical Conduiting

G Street Lights (Internal Roads) 0

H UGWT (for KPUMA & Park&Ride) 5 Spreading & Compaction of River Bed material

I WWTP 0

J Drain 8 0

K Drain 13 0

L Boundary Wall (External) 21 Brick Work + Formwork + Pointing

Total: 334
Contractor Representative Consultant Representative
Workforce Status at Stations on Peshawar BRT Project
Chamkani Depot Pictures

Park & Ride Ground Floor Brick Masonary In Progress

Park & Ride Slab Reinforcement & Columns Formwork In Progress


KPUMA Plastering in Progress

KPUMA Plastering in Progress


KPUMA Boundary Wall Brick Work in Progress

Entrance Gate Office External Finishing


Workshop Paint work In Progress

Workshop Tile Flooring


Internal Roads Boundary Wall
Public Health Works Is In Progress Workshop & Rest Area Blocks