Pembangunan Unit Metering System USM Lengkap Dengan Analyzer Gas Pipeline Development PLTGU Tanjung Batu Kaltimra
Project
ID Task Name Duration Start Oct '19 Nov '19 Dec '19 Jan '20 Feb '20 Mar '20 Apr '20
29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26
1 PEMBANGUNAN UNIT METERING SYSTEM USM LENGKAP DENGAN ANALYZER GAS 140 days Tue 15-10-19 15-10 27-04 27-04
PIPELINE DEVELOPMENT PLTGU TANJUNG BATU KALTIMRA PROJECT
2 PREPARATION , ENGINEERING & DOCUMENT, PROJECT MANAGEMENT 30 days Tue 15-10-19
3 Preparation 10 days Tue 15-10-19
4 Penyusunan schedule, organisasi & Admin Proyek 10 days Tue 15-10-19 15-10 28-10
5 Kick Off Meeting 1 day Tue 29-10-19 29-10 29-10
6 Engineering 33 days Tue 15-10-19 15-10 15-10 28-11
7 Submission Key Document 7 days Wed 30-10-19 30-10 07-11
8 Approval key Document 2 wks Fri 08-11-19 08-11 21-11
9 Submission & Approval Detail Engineering Document 3 wks Fri 08-11-19 08-11 28-11
10 Submission & Approval Project Management &l HSE Document 3 wks Fri 08-11-19 08-11 28-11
11 PROCUREMENT 80 days Fri 22-11-19 22-11 12-03
12 Instrument Material 80 days Fri 22-11-19 22-11 12-03
13 Senior Gas Ultrasonic Flow Meter 14 wks Fri 22-11-19 22-11 27-02
14 Flow Profiler 16 wks Fri 22-11-19 22-11 12-03
15 DBB Valve 8" 600#RF 16 wks Fri 22-11-19 22-11 12-03
16 Motor actuator c/w accessories 16 wks Fri 22-11-19 22-11 12-03
17 Gas Chromatograph c/w Gas Cal & Helium Gas 16 wks Fri 22-11-19 22-11 12-03
18 H2S Analyzer 16 wks Fri 22-11-19 22-11 12-03
19 Moisture Analyzer 16 wks Fri 22-11-19 22-11 12-03
20 Pressure Transmitter c/w LCD and 2 Way valve Manifold 12 wks Fri 29-11-19 29-11 20-02
21 Temperature Transmitter c/w LCD and 316SS Thermowell 12 wks Fri 29-11-19 29-11 20-02
22 Pressure Gauge c/w 2 way valve manifold 12 wks Fri 29-11-19 29-11 20-02
23 Temperature Gauge c/w 316SS Thermowell 12 wks Fri 29-11-19 29-11 20-02
24 Digital & Analog Junction Box, Class I Div I 12 wks Fri 22-11-19 22-11 13-02
25 Auto-Retractable Sample Probe 12 wks Fri 29-11-19 29-11 20-02
26 Manual Sample Probe 12 wks Fri 29-11-19 29-11 20-02
27 Gas Cal untuk GC Analyzer 12 wks Fri 29-11-19 29-11 20-02
28 Hellium Gas 12 wks Fri 22-11-19 22-11 13-02
29 H2S Gas 12 wks Fri 22-11-19 22-11 13-02
30 Nitrogen Gas 12 wks Fri 22-11-19 22-11 13-02
31 Instrument & Power cable 10 wks Fri 29-11-19 29-11 06-02
32 Bulk material 10 wks Fri 29-11-19 29-11 06-02
33 Control Panel Metering 60 days Fri 22-11-19
34 Control Panel Console 12 wks Fri 22-11-19 22-11 13-02
35 Flow Computer & Software 12 wks Fri 22-11-19 22-11 13-02
36 Power Supply 12 wks Fri 22-11-19 22-11 13-02
37 MMI Software 10 wks Fri 22-11-19 22-11 30-01
38 Workstation Computer 10 wks Fri 13-12-19 13-12 20-02
39 Laser Jet Printer 10 wks Fri 13-12-19 13-12 20-02
40 Dot Matrix Printer 10 wks Fri 22-11-19 22-11 30-01
41 Instrument & Power cable 10 wks Fri 29-11-19 29-11 06-02
42 Serial Hub/ ethernet switch 10 wks Fri 22-11-19 22-11 30-01
43 Bulk material 10 wks Fri 29-11-19 29-11 06-02
44 Regulating Skid 70 days Fri 22-11-19
45 Ball Valve 2 " Ansi 600 12 wks Fri 22-11-19 22-11 13-02
46 Pressure Regulating 1 " Ansi 600 12 wks Fri 22-11-19 22-11 13-02
47 Pressure Gauge c/w Two way Manifold 12 wks Fri 22-11-19 22-11 13-02
48 Temperature Gauge 12 wks Fri 22-11-19 22-11 13-02
49 Gas Turbin Meter 2" Ansi 600 12 wks Fri 22-11-19 22-11 13-02
50 Ball Valve 3/4 " ansi 600 12 wks Fri 22-11-19 22-11 13-02
51 Fabrication Metering & Skid 90 days Fri 22-11-19
52 Contract Finalization 1 wk Fri 22-11-19 22-11 28-11
53 Kick Of meeting 1 day Fri 29-11-19 29-11 29-11
54 Fabrication process 90 days Mon 02-12-19
55 Engineering Fabrication metering skid 24 days Mon 02-12-19
56 Drawing 20 days Mon 02-12-19 02-12 27-12
57 Procedure 20 days Fri 06-12-19 06-12 02-01
58 ITP 20 days Fri 06-12-19 06-12 02-01
59 Procurement (local material) 30 days Mon 09-12-19 09-12 17-01
60 Fabrikasi 70 days Fri 27-12-19
61 Fabrication USM Meter Spool dan Skid Structure 82 days Fri 27-12-19
62 Inspection Material 1 day Fri 27-12-19 27-12 27-12
63 Setting & welding pipe spool c/w NDE 3 wks Mon 30-12-19 30-12 17-01
64 Setting & welding skid Stucturel c/w NDE 3 wks Mon 30-12-19 30-12 17-01
65 Final Visual & Dimensional inspection 2 days Mon 20-01-20 20-01 21-01
66 Honning pipe spool 10 days Wed 22-01-20 22-01 04-02
67 Hydrotest witnes by Migas 2 days Wed 05-02-20 05-02 06-02
68 Sandblasting and Painting 10 days Fri 07-02-20 07-02 20-02
69 Assembly complete Metering system 7 days Fri 21-02-20 21-02 02-03
70 Packing & Deliver meter tube from Jakarta to calibration facilities (air freight) 8 days Wed 26-02-20 26-02 06-03
71 FAT Metering system & Closing punchlist 3 days Tue 07-04-20 07-04 09-04
72 MDR Metering Skid 7 days Fri 10-04-20 10-04 20-04
73 Fabrication Metering Regulating System 33 days Thu 27-02-20
74 Inspection Material 2 days Thu 27-02-20 27-02 28-02
75 Setting & welding pipe spool c/w NDE 2 wks Mon 02-03-20 02-03 13-03
76 Setting & welding skid Stucturel c/w NDE 2 wks Mon 02-03-20 02-03 13-03
77 Final Visual & Dimensional inspection 2 days Mon 16-03-20 16-03 17-03
78 Hydrotest witnes by Migas 2 days Wed 18-03-20 18-03 19-03
79 Sandblasting and Painting 7 days Fri 20-03-20 20-03 30-03
80 Assembly complete Metering system 5 days Tue 31-03-20 31-03 06-04
81 FAT Metering system & Closing punchlist 3 days Tue 07-04-20 07-04 09-04
82 MDR Metering Skid 5 days Fri 10-04-20 10-04 16-04
83 Control Panel fabrication 30 days Fri 14-02-20
84 Fabricate, Install Mounting Plate & Bulk Material Panel 20 days Fri 14-02-20 14-02 12-03
85 Configuration and Set Up Meter System 20 days Fri 14-02-20 14-02 12-03
86 FAT & Closing Punchlist 8 days Fri 13-03-20 13-03 24-03
87 MDR Panel 10 days Wed 25-03-20 25-03 07-04
88 USM WET & DRY CALIBRATION 30 days Thu 27-02-20
89 USM dry calibration at Emerson Factory 3 days Fri 28-02-20 28-02 03-03
90 Packing & Delivery USM from Emerson factory to Calibration facilities 7 days Wed 04-03-20 04-03 12-03
91 USM Wet calibration at Calibration facilities 3 days Fri 13-03-20 13-03 17-03
92 Paking Meter tube & Calibrated USM 7 days Wed 18-03-20 18-03 26-03
93 Deliver meter tube c/w USM from Calibration facilities to Jakarta ( air freight) 7 days Fri 27-03-20 27-03 06-04
94 PACKING & SHIPMENT PROCESS 10 days Fri 10-04-20
95 Packing & Shipment to project site 10 days Fri 10-04-20 10-04 23-04
́Task Progress Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only
Critical Task Milestone Split Inactive Milestone Manual Task Manual Summary Rollup Start-only Manual Progress
Document No. : POC254-A1900XX
Date : 28 OCT 2019 1
Revision : Rev. A
Periode Waktu : 24 weeks - FOT