Hot Water Test Procedures
Hot Water Test Procedures
General Notes:
1. This is a generic test procedure for heating water systems. It addresses boiler and distribution system performance.
If the complexity, configuration, or other aspects of a specific project require substitute tests or additional tests,
explain on the comments sheets, and attach the additional test procedures and field data. Attach all relevant
functional performance verification sheets, and always attach the final signed and dated procedure certification
page.
2. In all test sections, circle or otherwise highlight any responses that indicate deficiencies (i.e. responses that don’t
meet the criteria for acceptance). Acceptance requires correction and retest of all deficiencies, as defined in each
test section under “Criteria for Acceptance” or “Acceptance”. Attach all retest data sheets. Complete the Deficiency
Report Form for all deficiencies.
3. This Commissioning Procedure does not comprehensively address fire and life safety or basic equipment safety
controls.
4. To ensure that this Commissioning Procedure will not damage any equipment or affect any equipment warranties,
have the equipment manufacturers’ representatives review all test procedures prior to execution.
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 1
Building Name:
PREFUNCTIONAL CHECKLISTS:
List all heating water system boilers and pumps and check if the data recorded in the prefunctional checklists has been
reviewed and accepted as accurate.
Pumps
Comments:
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 2
Building Name:
BOILER #
1. Leaving boiler heating water (HW) temp, / / /
design / measured
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 3
Building Name:
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 4
Building Name:
Sequence Verified?
Notes & Comments:
Results: Record requested information under each condition, and then document equipment status during each
condition in Table 3.1 at the end of this test section.
Condition 1: OSAT less than setpoint - 5 F degrees, and HW return temperature less than HW supply temperature -
differential (3 F deg, adjustable) - 3 F degrees.
Time and date of observation.
Programmed pump stop time delay, minutes
Programmed HW supply / return temperature differential.
Time and date of observation.
OSAT and setpoint (or range) during condition.
HW supply and return temperatures (or range) during condition.
Condition 2: OSAT less than setpoint - 5 F degrees, and HW return temperature greater than HW supply temperature -
differential (3 F deg, adjustable) + 1 F degrees.
Time and date, initial observation / boiler off.
Observed time in minutes until change of equipment status.
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 6
Building Name:
Condition 3: OSAT greater than setpoint + 5 F degrees, and HW return temperature greater than HW supply
temperature - differential (3 F deg, adjustable) + 1 F degrees.
Time and date, initial observation / pumps off.
Observed time in minutes until change of equipment status.
Programmed pump stop time delay, minutes
Programmed HW supply / return temperature differential.
Time and date of observation.
OSAT and setpoint (or range) during condition.
HW supply and return temperatures (or range) during condition.
Table 3.1
Equipment Status ---> Condition 1 Condition 2 Condition 3 Comments
HW Pump, lead prim.
HW Pump, lag prim.
HW Pump, lag-lag prim.
HW Pump, lead sec.
HW Pump, lag sec.
HW Pump, lag-lag sec.
Boiler, lead
Boiler, lag
Boiler, lag-lag
Sequence Verified?
Notes & Comments:
4. Lead / Lag by Failure of Lead Unit: Turn off the lead unit of each equipment type at the disconnect, and verify that
the lag unit starts and that an alarm is registered at the operator’s terminal. At the conclusion of the test, put all
units back in the auto position at the disconnect. (Note: For dedicated primary pumps, the lead/lag test assumes
that there is an automatic switch to a backup pump. Non-dedicated primary pumps or dedicated pumps with a
manual switch to backup may require a slightly modified test procedure.)
Test Conditions: The building must have a moderate positive heating load. The lead unit of each equipment type must
be operating under normal control at the time it is turned off at the disconnect. The load must be low enough that
the lag units are not operating under normal control. If necessary, change setpoints or command HW valves to
force these conditions.
Results:
If conditions were forced, describe method of forcing.
Boiler, lead at start of test Boiler, new lead after failure of lead
Primary HW pump, lead at start of test Primary HW pump, new lead after failure
Sec. HW pump, lead at start of test Sec. HW pump, new lead after failure
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 7
Building Name:
Sequence verified?
Notes & Comments:
Functional Performance Tests. (Each test number refers to the respective control sequence number, above.)
1. Document the selected representative/critical HW valves. Verify that at least 8 (or all) HW valves have been
selected, and that they are typical of several coils or support critical environmental requirements. Verify by
inspection of the valve signals that none of the valves is “wild” (i.e. usually or always open due to inability to meet
load, forcing the HW reset to the minimum temperature). Such a valve will be considered a deficiency.
Selected Valve (identify Area Served Represen- Critical? Wild?
by AHU, coil, TU, etc.) tative?
Sequence Verified?
Notes & Comments:
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 8
Building Name:
2. Verify that, on lead boiler startup, the initial primary heating water supply temperature setpoint is set at the
midpoint between the upper and lower reset limits. Data for this test can be recorded at the same time as the
system start/stop test, or the lead boiler status and PHWST setpoint can be trended over the startup period at a 1
minute interval.
Results:
Time and date of boiler startup.
Programmed upper and lower PHWST reset limits, deg F.
Primary HW supply temperature setpoint at time of boiler startup.
Sequence Verified?
Notes & Comments:
Results:
Time and date of observation.
Programmed reset increment.
Programmed time delay between incremental resets.
HW supply & return temperatures at smallest differential during test.
Time Valve Positions, 3 most PHWST PHWST
open rep./crit. valves Setpoint
/ /
1st Observation: all representative/ / /
critical HW valves < 70% open. / /
/ /
2nd Observation: all but one rep./ / /
critical HW valves <70% open. / /
1 rep/crit valve fully open. / /
/ /
3rd Observation: all but two rep./ / /
critical HW valves <70% open. / /
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 9
Building Name:
Sequence Verified?
4. Verify the reasonableness of the PHWST setpoint reset table. Note that this is not so much a test as an
investigation of the parameters that go into defining the reset table.
Data
Highest coil design entering HW temperature
Upper PHWST reset limit.
Acceptance: < highest design ent. HW + 10 F deg
Lower PHWST reset limit.
Acceptance: For non-condensing boilers, >145F or as required to
ensure a boiler vessel temperature > 140°F; For condensing boilers, at
least 40 F deg < upper limit, if adequate to meet loads.
Sequence Verified?
Notes & Comments.
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 10
Building Name:
Functional Performance Tests. (Each test number refers to the respective control sequence number, above.)
1. a. Set up a table showing which HW valves must be fully open for each of the following flow situations. Note that,
after the lead boiler, each successive flow situation is the sum of the previously staged boiler(s) flow plus the
indicated percentage of the newly staged boiler. The flow in the 2nd and 3rd columns is either the secondary loop
flow or the variable primary loop flow, as applicable.
Operating Boilers Flow % GPM Reqd for HW Valve #s to be GPM of fully open HW
Total Flow opened valves (from TAB report)
Lead boiler #_____ 80%
100%
100%
100%
80%
100%
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 11
Building Name:
b. Force open the HW valves selected in the above table for each stage by either changing setpoints or manually
commanding them open. Hold each stage for 10 minutes before forcing open the valves required for the next
stage. (The valves from the previous stages will remain open.) Verify that at each stage that the secondary or
variable primary loop flow equals 100% of the currently staged boilers, the next boiler is turned on.
Method used to force valve position:
c. Following the above test of staging up, sequentially force closed the HW valves selected in the above table for each
stage by either changing setpoints or manually commanding them closed. Hold each stage for 10 minutes before
forcing closed the valves required for the next stage. (The valves from the previous stages will remain closed.)
Verify that at each stage that the secondary or variable primary loop flow equals 80% of the currently staged
boilers, the most lag boiler is turned off. For dedicated primary pumps, verify that the appropriate primary pump is
turned off with the respective boiler, after a time delay. At conclusion of tests, return all setpoints to original values.
Operating Boilers Time Record Boiler #s & Comments, Notes, Deficiencies
Primary Pump #s
On
Lead + lag boilers + 100%
Lag-lag boiler #___
80%
Lead boiler + 100%
Lag boiler #______
80%
Lead boiler #_____ 100%
80%
100%
80%
Sequence Verified?
Notes & Comments.
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 12
Building Name:
Functional Performance Tests. (Each test number refers to the respective control sequence number, above.)
1. This test is to be completed only if the HW plant contains boilers of more than one model or capacity.
Describe in detail the programmed logic for selecting the most efficient boiler for given conditions.
Does this logic meet the intent of the optimal selection sequence?
Attach annotated trend logs to document that the above-described logic controls lead boiler selection.
Sequence Verified?
Notes & Comments.
2. Trend status of all boilers and primary pumps at a 15 minute interval (or on change of status) for a 3 day period, or
as required to observe all boilers as leads. (It’s only necessary to trend the several hours that encompass normal
startup each day.) At the end of each occupied day, switch the lead, lag, and lag-lag boilers via operator
command. Verify that the commanded unit starts as the lead on the following day during normal startup. Record
observations of start-of-day statuses in the table below.
Test conditions: This test is most conveniently done during the heating season, when boiler startup is reasonably
certain each day. If this condition cannot be met, force boiler startup by changing OSA setpoint, forcing HW valves
open, and/or other means of triggering startup conditions. Do not force boiler startup by direct manual command.
At conclusion of tests, return all setpoints to original values.
Results:
Are primary pumps (boiler circulation pumps) dedicated to specific boilers?
Lead Boiler per Lead Boiler per Lead Primary Comments, Notes,
Operator Trend Log Pump per Deficiencies
Command Trend Log
Day 0 (lead boiler prior NA
to operator command)
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 13
Building Name:
Sequence Verified?
Notes & Comments:
3. Change the adjustable boiler run-time setpoints to the minimum allowable (probably 1 or 2 hours). Allow lead
boilers to run for programmed run-time + 30 minutes. Indirectly force boilers to stop by forcing HW valves closed,
changing setpoints, etc. Do not directly command boilers to stop. Wait 15 minutes, and allow or force conditions
such that lead boiler starts. Observe which boiler and dedicated primary pump starts as lead. At conclusion of
tests, return all setpoints to original values.
Test conditions: This test will disrupt normal HW system operation and can cause comfort complaints. Perform the test
with the building unoccupied or lightly occupied. The test should be performed during the heating season if
possible, so that normal boiler and tower startup is reasonably certain.
Results:
Original boiler run-time setpoints, hours.
Adjusted boiler run-time setpoints, hours.
Sequence Verified?
Notes & Comments:
4. This test applies to secondary and non-dedicated primary HW pumps. Change the adjustable pump alarm run-time
setpoints to 4 hours. (If there is a large discrepancy between accumulated run-times for like service pumps, record
run-times and then zero them out, with County permission.) Allow lead pumps to run for programmed alarm run-
time + 30 minutes. Verify that an alarm is registered at the operator’s terminal and at the Ford Building Insight
station. Verify that pump lead does not switch automatically. At conclusion of tests, return all setpoints to original
values.
Results:
Original pump alarm run-time setpoints, hours.
Adjusted pump alarm run-time setpoints, hours.
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 14
Building Name:
Observation 1: initial / /
condition. Expected result: no
alarms
Observation 2: run-time + at / /
least 30 minutes. Expected
result: alarms but no auto-
switch
Sequence Verified?
Notes & Comments:
Standard Secondary or Variable Volume Primary Heating Water Pump Speed Control:
Control Sequence:
1. All variable volume pumps shall be of identical capacity and head. Each such pump shall be controlled by an
individual VFD. When 2 or more secondary pumps are running, they shall run at the same speed (within ± 1% of
each other).
4. The end-of-run differential pressure setpoint will be determined by the test and balance agency such that the 2–
way valve serving the heating coil with the greatest load is between 90% and 98% open at the same time that the
majority of other heating coils are under a moderate to heavy heating load.
1. The lead pump speed will be modulated between minimum speed (initial setpoint, 20%, adjustable, or minimum
acceptable to motor manufacturer) and an upper staging limit (adjustable), to maintain the end-of-run differential
pressure at setpoint. The upper staging limit is to be selected by the engineer for optimum system wire-to-water
efficiency. Generally, this setpoint will be between 50% and 70% speed, depending on pump capacities, number of
secondary pumps, system head characteristic, etc.
4. If the lead pump is operating at greater than the upper staging setpoint for at least 5 minutes, and the end-of-run
differential pressure is below the setpoint minus an adjustable differential (initial differential, 2 psi), then the lag
pump shall be started and its speed ramped up. Both pumps will run at the same speed, as required to maintain
the end-of-run differential pressure at setpoint.
5. The lag pump is turned off when the end-of-run differential pressure is above the setpoint plus an adjustable
differential (initial differential, 1 psi) for more than 1 minute, and both pumps are running at less than the upper
staging setpoint speed.
6. If the differential pressure is above setpoint plus 2 psi for more than 1 minute, and only the lead pump is running,
and the lead pump is running at minimum speed, then the secondary loop bypass valve will modulate to maintain
the differential pressure at setpoint.
Functional Performance Tests. (Each test number refers to the respective control sequence number, above.)
1. Are all variable volume HW pumps in the same circuit the same capacity and head?
Is each var. volume HW pump driven by its own VFD?
Test Conditions: The building heating load must be high enough that all variable volume HW pumps are running.
Note HW pump speeds (EMS output signal or display at VFD panel) at three different times (with all pumps on), or
attach trend logs of speeds over a period of several hours, and an interval of 15 minutes.
TimePump # ___ Pump # ___ Pump # ___ Pump # ___
Observation 1: ________ __________ __________ __________ __________
Observation 2: ________ __________ __________ __________ __________
Observation 3: ________ __________ __________ __________ __________
Are speeds of all pumps the same ± 1% at each observation?
Sequence verified?
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 15
Building Name:
2. Does the TAB report give evidence that the end-of-run differential pressure setpoint was optimally selected? If not,
comment. Optimal setpoint selection: The 2-way valve serving the heating coil with the greatest load is between
90% and 98% open at the same time that the majority of other heating coils are under a moderate to heavy
heating load (a load roughly equal in magnitude to the design building heating diversity).
b. Trend variable volume HW pump speeds and end-of-run differential pressure for 24 hours at a 2 minute interval. If,
upon examination of the trend log, the lead pump speed has not decreased to within 10% of the minimum speed
and increased to within 10% of the upper staging speed limit setpoint (prior to start of lag pump), force HW coil
valves closed and open as necessary to simulate minimum and maximum flows, respectively. (Record maximum
speed at the point when the lag pump is started.) Attach annotated trend logs.
Minimum speed setpoint Upper staging limit setpoint
Identify the lead pump.
Min. lead pump speed during 24 hr trend period
Max. lead pump speed during trend period
If HW coil valves were forced open to achieve minimum and maximum lead pump speeds, describe method of forcing
and record observations for the 2 following questions.
4. Trend variable volume HW pump speeds and end-of-run differential pressure for 24 hours at a 2 minute interval.
This period can coincide with the trend period for test #3, if conditions are such that all variable volume HW pumps
are staged on. If, upon examination of the trend log, all pumps have not staged on, force HW coil valves open as
necessary to stage on all pumps. Attach annotated trend logs.
Identify the lead pump. Identify the lag pump.
Identify the lag-lag pump, if applicable.
Programmed time delay, minutes, for pump stage-on.
Pressure or diff. pressure setpoint Upper differential Lower differential
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 16
Building Name:
Were HW coil valves forced to achieve staging of all pumps? If yes, describe method of forcing.
Record the time, the speed of each running pump, and the end-of-run differential pressure at the time that each
succeeding pump is started (but before the speed ramps up). If the trend log adequately demonstrates this
sequence, attach the annotated trend log in addition to recording in the following table. Expected result: When the
speed of the running pumps reaches the upper staging limit setpoint and the end-of-run differential pressure is less
than the setpoint minus differential and a time delay has elapsed (5 minutes, or as programmed), then, the next
pump is staged on, and all pumps run at the same speed, as necessary to maintain the pressure (DP) at setpoint.
Time End-of-Run Diff. Pump #____ Pump #____ Pump #____
Pressure Speed Speed Speed
Observation 1: lead pump speed <
upper staging limit and DP >
setpoint (- differential)
Observation 2: lead pump speed >
upper staging limit and DP <
setpoint and time of condition >
5 min. Expected: lag pump starts
Observation 3: lead & lag pump
speeds > upper staging limit and DP
< setpoint and time of condition >
5 min. Expected: lag-lag pump
starts
Sequence verified?
Notes & Comments:
5. Trend secondary (or variable volume primary) HW pump speeds and end-of-run differential pressure for 24 hours
at a 2 minute interval. This period can coincide with the trend periods for tests # and/or #4, if conditions are such
that all lag and lag-lag variable volume HW pumps are staged off. If, upon examination of the trend log, all lag
pumps have not staged off, force HW coil valves closed as necessary. Attach annotated trend logs.
Identify the lead pump. Identify the lag pump.
Identify the lag-lag pump, if applicable.
Programmed time delay, minutes, for pump stage-off.
Were HW coil valves forced to achieve staging off of pumps? If yes, describe method of forcing.
Record the time, the speed of each running pump, and the end-of-run differential pressure at the time that each pump
is stopped. If the trend log adequately demonstrates this sequence, attach the annotated trend log in addition to
recording in the following table. Expected result: When the speed of the running pumps decreases to the upper
staging limit setpoint and the pressure is more than the setpoint plus differential and a time delay (1 minute, or as
programmed) has elapsed, then the lag or lag-lag pump is staged off, and all remaining pumps run at the same
speed, as necessary to maintain the pressure (DP) at setpoint.
Time End-of-Run Diff. Pump #____ Pump #____ Pump #____
Pressure Speed Speed Speed
Observation 1: lead, lag, & lag-lag
pump speeds < upper staging limit
and DP > setpoint (+diff.) and time
of condition > 1 min. Expected: lag-
lag pump stops.
Observation 2: lead & lag pump
speeds < upper staging limit and DP
> setpoint and time of condition >
1 min. Expected: lag pump stops.
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 17
Building Name:
Sequence verified?
Notes & Comments:
6. This test can also be verified during the trend periods of tests #3-5. If, upon examination of the trend logs, the lead
pump is never running at minimum speed with the end-of-run differential above setpoint plus differential, force HW
valves closed as necessary to force this condition. Attach annotated trend logs.
Is only the lead pump running?
Lead pump minimum speed observed or trended
Greatest end-of-run differential pressure observed when lead pump is at minimum speed
Programmed time delay, minutes, for bypass valve modulation
Does secondary loop bypass valve modulate open to maintain the pressure below setpoint plus upper differential?
Sequence verified?
Notes & Comments:
I certify that the data and test results as recorded herein are accurate.
File: 58082906, Release 1.0, 8/97 Heating Water System Commissioning Procedure, page 18