Go No 288

Download as pdf or txt
Download as pdf or txt
You are on page 1of 40

GOVERNMENT OF ANDHRA PRADESH

ABSTRACT
Municipal Administration & Urban Development Department – Hyderabad Urban
Development Authority – Extensive Modification to the Master Plan of Hyderabad
Urban Development Authority Area ( excluding the erstwhile MCH area and the
newly extended area of HUDA) – Approved– Orders – Issued.

MUNICIPAL ADMINISTRATION & URBAN DEVELOPMENT (I1) DEPARTMENT

G.O.Ms.No. 288 Dated: 3rd April 2008


Read the
following:
1. G.O.Ms.No.391, MA dated: 23-06-1980.
2. G.O.Ms.No.353, MA dated: 30-05-1980.
3. G.O.Ms.No.209, MA dated: 25-04-1984.
4. G.O.Ms.No.412 MA dated: 05-08-1986.
5. G.O.Ms.No.96 MA dated: 03-03-1989.
6. G.O.Ms.No.97 MA dated: 03-03-1989.
7. G.O.Ms.No.156 MA dated: 27-03-1989.
8. G.O.Ms.No.160, MA dated: 28-03-1989.
9. G.O.Ms.No.321 MA dated:10-06-1994.
10. G.O.Ms.No.362 MA dated: 06-07-1994.
11. G.O.Ms.No.386 MA dated: 25-07-1994.
12. G.O.Ms.No.479, MA dated: 02-09-1994.
13. G.O.Ms.No.22 MA & UD dept. dated: 22-01-2003
14. From Vice-Chairman, Hyderabad Urban Development Authority, D.O.
Letter No.11109/P/H/RMP/02 dated:19-04-2005.
15. From Vice Chairman, Hyderabad Urban Development Authority, Letter
No.11109/H/RMP/02, dated: 22-07-2006.
16. From Vice Chairman, Hyderabad Urban Development Authority, Letter
No. 11109/H/RMP/2002 dt.11-12-2006.
17. Govt. Memo No.9225/I1/2005, dated: 26-05-2007.
***

The appended notification shall be published in the extraordinary issue of the


A.P. Gazette dated: 04-04-2008

2. The Commissioner of Printing, Stationery and Stores Purchase, Hyderabad is


requested to supply 100 copies to the Government.

(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)

S.P.SINGH
PRINCIPAL SECRETARY TO GOVERNMENT

To
The Commissioner, Printing Stationery & Stores Purchase Hyderabad.
The Vice Chairman, Hyderabad Urban Development Authority, Hyderabad.
Copy to:
2

The Revenue Department.


The Industries & Commerce Department.
The Environment, Forest, Science & Technology Department.
The Panchayati Raj & Rural Development Department.
The Transport Roads & Building Department.
The Law (A) Department.
The Commissioner, GHMC, Hyderabad.
The Commissioner & Director of Municipal Administration, A.P., Hyderabad.
The Director of Town and Country Planning, A.P., Hyderabad.
The Managing Director, HMWS&SB, Hyderabad.
The Collector, Ranga Reddy District, Hyderabad.
The Collector, Hyderabad District, Hyderabad.
The Collector, Medak district
The P.S to Special Secretary to Chief Minister.
The P.S. to M (MA & UD)
The P.S. to Chief Secretary to Government.
Sf/sc.

//FORWARDED BY ORDER//

SECTION OFFICER

APPENDIX
NOTIFICATION

Whereas the Master Plan and 18 Zonal Development Plans for Non-MCH
area of Hyderabad Urban Development Authority Area were approved by the
Government in G.O.Ms.No. 391, MA, dated: 23-06-80, G.O.Ms.No. 353, MA dated:
30-05-80, G.O.Ms.No. 209, MA, dated: 25-04-84, G.O.Ms.No. 96, MA, dated: 03-03-
89, G.O.Ms.No. 97, MA, dated: 03-03-89, G.O.Ms.No. 156, MA, dated: 27-03-89,
G.O.Ms.No. 160, MA, dated: 28-03-89, G.O.Ms.No. 321, MA, dated: 10-06-94,
G.O.Ms.No. 362, MA, dated: 06-07-94, G.O.Ms.No. 386, MA, dated: 25-07-94 and
G.O.Ms.No. 479, MA, dated: 02-09-94;

2. And whereas Government, after reviewing the above Master Plan and Zonal
Development Plans, considered that the above plans needed overall modifications in
the form of Revised Master Plan for the entire Hyderabad Urban Development
Authority area. Therefore, Government after careful examination of the matter have
proposed to make extensive modifications to the above said Master Plan and Zonal
Development Plans in the form of overall modifications to the above said Master Plan
/ Zonal Development Plans as provided under section 12 (2) of the Andhra Pradesh
Urban Areas (Development) Act, 1975;

3. And whereas Government, while exercising the powers conferred under


section 56 (2) of the Andhra Pradesh Urban Areas (Development) Act, 1975 (Act-1 of
1975), issued orders in G.O.Ms.No.22 MA & UD Department, dated.22.01.2003
delegating the powers to Vice Chairman, Hyderabad Urban Development Authority to
prepare the revised Master Plan in the form of an overall modification to the Master
3

Plan and Zonal Development Plans and publish the same for inviting the objections
and suggestions from the public;

4. And whereas, in pursuance of the above orders, the Vice Chairman,


Hyderabad Urban Development Authority has prepared the Draft Revised Master
Plan comprising of 18 Zones covering the Non-MCH area of Hyderabad Urban
Development Authority jurisdiction (i.e., excluding the erstwhile MCH area and newly
extended HUDA areas the plans for which are being taken up separately by HUDA)
along with the Land Use Zoning, Building & Layout Regulations and published the
same in News Papers inviting objections and suggestions from the Public. After
examining and considering the objections and suggestions received from public on
the proposed Draft Revised Master Plan, the Vice Chairman, Hyderabad Urban
Development Authority, vide his letter Nos. 11109/P/H/RMP/02, dated: 19-04-2005,
11109/H/RMP/02, Dated: 22-07-06 and 11109/H/RMP/2002, dated: 11-12-06 has
submitted the comprehensive Revised Draft Master Plan along with the Land Use
Zoning, Building & Layout Regulations for approval of the Government.

5. And whereas, after examining the above draft Master Plan comprising of 18
Zones, Government have directed the VC-HUDA to make certain modifications /
incorporations in the draft revised Master Plan like (i) to delete multiple use zone
proposed in the areas covered by the G.O.Ms.No. 111 MA dated 08-03-1996; (ii) to
incorporate the areas identified for 22 proposed Satellite Townships along and
around the proposed Outer Ring Road; (iii) to earmark High-rise development zone
along the MMTS / MRTS corridors; (iv) to demarcate 10 proposed routes of MRTS
with clear Right of Way; (v) to delineate specific areas as Sky Craper Zone as
envisaged in the G.O.Ms.No.86, dated: 03.03.2006; (vi) to remove the Solid Waste
Disposal sites which do not conform to the Government of India guidelines; (vii) to
incorporate the Outer Ring Road alignment; and (viii) recent modifications made by
the Government in the Master Plan/ Zonal Development Plans and submit the same
to Government for approval. Accordingly, the V.C., HUDA has submitted the draft
Master Plan to the Government for approval.

6. And whereas Government, after careful consideration of the matter, have


proposed to approve the above Revised Draft Master Plan which is an extensive
modification to the present Master Plan / Zonal Development Plans which were
approved as given in para (1) above along with Land Use Zoning, Building & Layout
Regulations, as submitted by Hyderabad Urban Development Authority, in exercise
of the powers conferred under section 12 (2) of Andhra Pradesh Urban Areas
(Development) Act, 1975 read with rule 13-A of the Urban Development Authority
(Hyderabad) Rules, 1977;

7. And whereas, since the above modifications were extensive and major in
nature, and there was considerable time gap from the date of first notification issued
by the HUDA, Government have decided to issue a fresh notification inviting
objections / suggestions on the draft revised Master Plan and Land Use Zoning,
Building & Layout Regulations.

8. Accordingly, a notification has been published in the Extraordinary issue of


A.P. Gazette dated.31.05.2007 as required under sub-section (3) of section 12 of
Andhra Pradesh Urban Area (Development) Act, 1975 inviting objections and
suggestions on the above Draft Revised Master Plan comprising of 18 Zonal
4

segments and the Land Use Zoning, Building & Layout Regulations for non-MCH
area of Hyderabad Urban Development Authority jurisdiction (excluding the erstwhile
MCH area and the newly extended area of Hyderabad Urban Development
Authority).

9. In response to the above notification, a number of objections / suggestions


have been received from the public and various institutions and organizations with
regard to certain land uses, road widths and road alignments along with some
general suggestions on improving the quality of Draft Master Plan.

10. And whereas Government, after careful examination of the objections and
suggestions received, decided to make certain modifications to the said notified Draft
Revised Master Plan comprising of 18 Zonal Segments as shown in the Annexure –
II to this order. Further, since new buildings byelaws as applicable to HUDA areas
issued in G.O.Ms.No. 86, MA&UD (M) Deptt, dated: 03-03-2006 have removed
height restrictions in buildings, the proposed High Rise and Sky-scraper zones have
been omitted and lands earmarked for these zones shall be restored to their earlier
uses as suggested prior to earmarking these for the High Rise and Sky-scraper
zones.
5

11. Now, therefore, in exercise of the powers conferred by sub-section (2) of


Section 12 of A.P. Urban Areas (Development) Act, 1975 (Act–1 of 1975),
Government hereby approve the Revised Master Plan comprising of 18 Zonal
Segments covering the Non-MCH area of HUDA (excluding the erstwhile MCH Area
and the newly extended area of HUDA) along with the Land Use Zoning, Building
and Layout Regulations specified in Annexure – I to this order with the modifications
specified in Annexure – II to this order and also all the change of land uses and road
alignments ordered by Government from time to time in the interregnum period.

12. The Land Use Plans, Zoning and layout regulations and copy of Report can
be seen in the Office of the Vice-Chairman, HUDA during the office hours till such
time these are printed and made available for General Public.

S.P.SINGH
PRINCIPAL SECRETARY TO GOVERNMENT

SECTION OFFICER
6

ANNEXURE–I
(G.O. Ms. No. 288, MA &UD (I1) Department, Dated: 3-4-2008)

LAND USE ZONING, BUILDING AND LAYOUT REGULATIONS

I. LAND USE ZONING REGULATIONS

The Land Use Zoning Regulations contain the following classification of land uses:

1) RESIDENTIAL ZONE

2) COMMERCIAL ZONE

RETAIL
WHOLESALE

3) MANUFACTURING ZONE

4) PUBLIC AND SEMI-PUBLIC ZONE

5) MULTIPLE USE ZONE

6) PUBLIC UTILITIES

7) OPEN SPACE ZONE

8) CONSERVATION ZONE

9) FORESTS

10) WATER BODIES

11) SPECIAL RESERVATIONS


HERITAGE BUILDINGS AND AREAS
MILITARY LANDS
OTHERS

12) TRANSPORTATION AND COMMUNICATION ZONE


ROADS
RAILWAYS
AIRPORTS
BUS DEPOTS AND TRUCK TERMINALS

Uses permitted and prohibited in different categories of land use zones are described
against each. The uses are not to be treated as exhaustive. Similar uses and activities may
be permissible in the appropriate locations by the HUDA Board and shall be subject to such
restrictions and conditions as may be imposed.

1. RESIDENTIAL ZONE.
7

SL.N CATEGOR USES PERMITTED on all locations USES PROHIBITED


O Y
I II
1 RESIDEN All types of residential heavy, large and extensive
TIAL buildings industries:
hostels & boarding houses obnoxious and hazardous
Group housing / Apartment industries
Complexes
police posts warehousing
colleges
fire stations
schools
guest houses storage godowns of perishables,
research institutes hazardous and inflammable
goods
convenience shopping workshops for buses etc.
night shelters

doctors clinics and slaughter-housing


dispensaries
dharamshalas
health facilities with not more wholesale mandis
than 20 beds
petrol pumps
professional offices hospitals treating contagious and
motor vehicle repairing infectious diseases
workshops/garages
other educational buildings Sewage treatment plant/disposal
other than professional work
colleges/institutions
hotels on plots of above 2000
sq.meters and abutting road
of minimum width of 18
meters
community centres water treatment plant
auditoriums solid waste dumping yards
foreign missions
religious premises outdoor games stadium
function halls on plots above
3000 sq.meters and abutting
road of minimum 18 meters
width
weekly markets indoor games stadium
bakeries and confectioneries
library shooting range
auditoriums zoological garden
gymnasium
parks/totlots botanical garden
8

Electronic printing press international conference centre


plant nursery
technical training centre Courts of law
bus depots without workshop
yoga centres/health clinics Reformatory
cinema halls on plots above
3000 sq.meters and abutting
road of minimum 18 meters
width
exhibition and art gallery storage of gas cylinders
retail shopping centres
banks All other uses not mentioned in
transit visitors camp Col I
police stations
municipal, state and central
government offices
taxi stand/three wheeler
stands
burial-grounds/ Cremation
ground
electrical distribution station
water pumping station
post offices
games facilities of local
nature both indoor and
outdoor

public utilities and buildings


except service and storage
yards
clubs
computer software units /IT
Enabled Services
restaurants/eating places
Showroom for sale &
distribution of LPGas

customary home
occupation/household units
Bus stands

2. COMMERCIAL ZONE
9

SL.N CATEGORY USES PERMITTED USES PROHIBITED


o.

I II

COMMER- retail shops and retail shopping centers, hazardous and extractive
CIAL ZONE- Shopping Malls industrial units
Retail and offices
Wholesale hotels hospitals/research
banks laboratories treating
function halls on plots of minimum 3000 contagious diseases
sqr mtrs and abutting road width of poultry farms/ dairy farms
minimum 18 meters
stock exchange/financial institution slaughter-houses
cinema halls and multiplexes
bakeries and confectionaries sewage treatment/
health facilities with maximum 200 beds disposal sites
guest houses storage of perishable and
wholesale trade/markets inflammable commodities
restaurants reformatory
godowns and warehousing all activities which cause
repair garages nuisance and are noxious
weekly market and obnoxious in nature
non polluting non-obnoxious light
industries
petrol pumps
timber yards
hostel/boarding houses
bus and truck depots
colleges
gas installation and gas works
all health facilities
polytechnic and higher technical
institutes
religious places
junk yards
post offices
water treatment plant
multistoried parking complexes
railway yards/stations
research/training institute
sports/stadium and public utility
installation
service centres/garages/workshops
religious buildings
weekly / informal markets
all residential uses
library
10

conference centers
parks/open space
courts
museum
sports and related facilities
police stations/posts
Fire Station
clubs
taxi stand/three wheeler stands
parking sites
telephone exchange
research institutions
computer software units /IT Enabled
Services

Note : Special Commercial Zones Along All Highways, Ring Roads, Radial Roads And
Expressways (Upto a depth of 90 M after proposed Right of Way of road) wherever
Indicated on the plan; are conditional. These can be used subject to the following
conditions:

(i) Free handing over of land to local body/authority for widening of the road
up to the proposed width.

(ii) Construction of service road

(iii) Access from property to road only through service road.

(iv) Conformity with provisions of Hyderabad Revised BuildingRules,2006


11

3. MANUFACTURING ZONE.

SL CATEGO USES PERMITTED USES PROHIBITED


.N RY
O

I II
MANUFA all kinds of industries Residential dwellings other
CTURING Residential buildings for essential staff than those essential for
ZONE and for watch and ward operational and watch and
obnoxious and hazardous industries ward staff
except storage of perishable and schools and colleges
inflammable goods hotels
public utilities All other uses not mentioned
junkyards in Col I
parking of vehicles
sports/stadium/playgrounds
loading and unloading spaces
sewage disposal works
warehousing
electric power plants
storage and depot of non-perishable
and non-inflammable commodities and
incidental use
service stations & repair garages
cold storage and ice factory
cemeteries
gas godowns, godowns & warehousing
government/semi-government/private
business offices
bus terminal
banks and financial institutions
bus depot and workshop
helipads
wholesale business establishments
religious buildings
taxi stands
parks and playgrounds
gas installations and gas works
health facilities incidental to main uses
animal racing or riding stables
restaurants
workshops/garages
computer software units /IT Enabled
Services.
dairy and farming
12

4. PUBLIC AND SEMIPUBLIC ZONE.

Sl. CATEGO USES PERMITTED USES PROHIBITED


No. RY

I II
PUBLIC offices heavy, extensive and other
AND universities and specialised obnoxious and hazardous
SEMI- educational institutions industries
PUBLIC residential plotted or group housing slaughter houses
ZONE for staff / employees as incidental
to the main use
colleges junk yards
open air theatre wholesale markets
schools dairy and poultry farms
clubs
research and development centres farm houses
guest house workshops for servicing and
repairs
social and welfare centres
processing and sale of farm
bank
products and uses not
libraries
specifically permitted herein
museum
hospitals All other uses not mentioned in
hostels Col I
health/primary centres
water supply installations
dispensaries
sewage disposal works
clinics and laboratories
service stations
social and cultural institutions
railway stations/yards
religious buildings/centres
polytechnics
conference halls
cultural and religious buildings
community halls
bus/truck terminals
dharam shala
warehouses/storage godowns
museums/art galleries
helipads
13

exhibition centres
retail shopping centres
auditoriums
cinema halls/Multiplexes
police station/police posts
hotels on plots
jails
fire stations/fire posts
function halls,
burial grounds/ cemeteries/
cremation grounds
public utilities and buildings
petrol pumps
L P Gas godowns
post offices
bus and railway passenger
terminals
monuments
radio transmitter and wireless
stations
telecommunication centre
telephone exchange
computer software units /IT
Enabled Secvices on independent
plots of more than 1000 sq.mt size.

5. MULTIPLE USE ZONE.

SL.N land use USES PERMISSIBLE USES PROHIBITED


O categories

I II
MULTIPLE All activities except Industries All other types of industries
USE ZONE Computer software and
Hardware units
function halls
cinema halls
hotels

6. PUBLIC UTILITIES

SL land use USES PERMITTED USES PROHIBITED


.N category
O
14

PUBLIC Water supply, drainage, storm water, solid any other use other
UTILITIES waste disposal, electricity, communication than the specific
systems and related installations, Parking reservation.
lots, Public utility buildings

7. OPEN SPACE ZONE

Sl. land use USES PERMITTED USES PROHIBITED


No. category

I III
OPEN Regional parks Any building or structure
SPACE local parks which is not required for
ZONE Building and structures ancillary open air recreation
to use permitted in open spaces dwelling units except for
and parks subject to the total watch and ward
ground coverage not exceeding
2%
playgrounds
commercial use of transit nature
like circus
children traffic parks
camping grounds
botanical/zoological garden
restaurants as part of sports,
recreational outdoor facilities not
exceeding 5% ground coverage
picnic huts with built up area not
exceeding 2%
open air cinemas/auditoria
bird sanctuary
outdoor sports stadiums
holiday resorts with ground
coverage not exceeding 2%
shooting range
sports training centres
specialised parks/maidans for
multi-use
swimming pools with built up
areas not exceeding 2% of total
area
public & institutional libraries
with total built up area not
exceeding 2% of total site

Note: On sites specifically indicated as parks, playgrounds or Green Belt


Project, no other activity except the specified use shall be allowed
15

8. CONSERVATION ZONE

SL. land USES PERMITTED USES PROHIBITED


NO use
categor
ies
I II
CONSE agriculture Residential use
RVATI horticulture, floriculture , forestry except those
ON sewage disposal works and ancillary uses
ZONE public utility facilities permitted in
poultry and dairy farm agricultural use zone
electric power plant subject to 2% ground
agro based cottage industries coverage
without use of power
quarrying The activities
mentioned in Col I
storage, processing and sale of
are not allowed in the
farm produce
prohibited areas
petrol and other fuel filling
mentioned in
stations
G.O.Ms. 111 MA
public utilities dt.8-3-1996
Dwellings and ancillary buildings
for the people engaged in the
farm (rural settlement) subject to
a maximum height of 7 meters
and maximum ground coverage
of 10% with minimum land
extent of one acre.
milk chilling stations and
pasteurisation plants
Transport and communication
facilities
Village settlement expansion

9. FORESTS ZONE

(i) This zone indicates all Reserved Forests as notified by the Forest Department
(ii) No activity other than forest is permitted in this zone unless expressly allowed by
the Forest Department.

10. WATER BODIES.

Water Bodies Zone generally indicates all existing water bodies, rivers, streams, lakes, tanks
and kuntas as indicated in the topographical sheets published by the Survey of India, the
State Irrigation Department or revenue or other competent authorities. The boundary of the
water bodies relate to the Full Tank Level as indicated in relevant maps, covering both
perennial and non perennial parts when such distinction exists.

In Water Body Zone no construction is permitted in the water-spread and the buffer belt of
minimum 30 meters around the FTL. The only exception is fishing, boating, and picnics
along the banks provided that only construction allowed is open to sky jetties for boating,
16

platforms for fishing and rain sheltersand snack bars each not exceeding 10 sqm in area and
not exceeding four in numbers around one water body.

11. SPECIAL RESERVATIONS.

(i) HERITAGE BUILDINGS AND AREAS

a) Heritage Buildings and areas shall indicate the location of notified Heritage
Buildings and will indicate the boundaries of notified Heritage Precincts.

b) In Heritage Buildings and Heritage Precincts, it is necessary to obtain specific


clearance from HUDA, after consultation by Heritage Conservation Committee
before undertaking certain kinds of development and redevelopment as
specified by the Government or issued as specific guidelines. Special
exemption from land use controls are allowed subject to approval from the
Government in the interest of conservation of the Heritage Buildings.

c) The Heritage Regulations issued vide GOMs No. 542, MA dated 14-12-1995
and other relevant orders/amendments issued by the Government from time to
time shall be applicable.

(ii) MILITARY LANDS.

Military Lands are lands under occupation of the Defense Services or otherwise
earmarked for defense services. These can not be put to other uses. The areas
covered by Defense lands and certain adjoining areas as may be specifically
notified, may be subjected to restrictions on constructions or on the use of lands in
the interest of safety and security of the defense services or the civil population
living in the contiguous areas.

(iii) OTHERS

Any other Special Reservations earmarked in the Master Plan.

(iv) Bio Conservation Zone

The developments in the Bio Conservation zone shall be strictly in accordance with
the provisions of G.O.Ms.No.111 M.A dated8-3-96, and as per the
regulations/stipulations issued by the Government from time to time.

12. TRANSPORTATION AND COMMUNICATION ZONE.

SL. CATEGORY USES PERMITTED USES


NO PROHIBITE
D
I II III
12 TRANSPORT Road transport terminals (bus terminals Use/activity
AND and depots) not
COMMUNICATI goods terminals specifically
ON ZONE Any other use/activity incidental to permitted
transport and communication herein.
17

parking areas/buildings
residential dwelling units for essential staff
and watch and ward
airports-buildings and infrastructure
truck terminal
motor garage
workshop
repair and repair shop and facilities such
as night shelter
hotels
banks
restaurants
booking offices
wireless station
radio and television station
observatory and weather office
accessory and support shopping activity

II. BUILDING REGULATIONS:

The Hyderabad Revised Building Rules,2006 issued vide G.O.Ms.No.86, M.A. & U.D. (M)
dated 03-03-2006 and as amended by the Government and other instructions issued or to
be issued by the Government from time to time shall be followed.

III. LAYOUT AND LAND SUB-DIVISION REGULATIONS,2008

1. Assemblage of land requirements:

(i) Land development in HUDA area would be promoted and facilitated in any of the
following manner:

(a) Land Pooling or Township Development Scheme


(b) Layout Development Schemes
(c) Group Housing Schemes/Cluster Housing
(d) Individual plot sub-division /amalgamation

(ii) Excepting in cases of 1.0 (d) above, no Assemblage of land for development
shall be permitted unless such a Scheme or layout development is undertaken
through a licensed developer, i.e.,
(iii) Land Pooling Scheme or township development should be a self-contained
township planned and developed through a licensed developer/firm /development
Company together with work place and places of residence with all attendant
facilities and amenities in such township and in accordance with the approved
township policy of the Government.
(iv) layout development scheme may be permitted for residential, commercial,
industrial, institutional, recreational and truck terminal/traffic node and other
activities like Corporate Townships, etc. subject to the compliance of these
regulations and development specifications of HUDA.
18

(v) Individual plot sub-division/amalgamation would be allowed only in case of plots


forming part of approved Land Pooling Schemes or layouts approved by the
Competent Authority.
(vi) All land assemblage developments as mentioned above would be considered
only if :

a. The proposed Scheme or development conforms to the Statutory Master plan


and the rules/regulations and conditions governing such development
requirements like:

i. All facilities and services like roads, storm water drainage, water supply,
electricity, landscaping and greenery, rainwater harvesting structures, and
provisions of other public utilities, are provided and developed.
ii. Comply with the obligations and conditions for implementation of the
Statutory Master Plan roads and other communication network system
and the area of land so affected is surrendered free of cost to HUDA after
development.

2. Undertaking of Land Pooling Schemes:

Land Pooling Schemes may be undertaken either by public authority or licensed


private developers, provided the area of such a Scheme is not less than 20 Hectares.
These shall apply to all new areas and greenfield sites. These shall be subject to the
following:

(i) The lands covered by such land pooling scheme shall be contiguous and
approachable by an existing black-topped road of 18 mts (60 feet) – where
such a road does not exist the developer shall first provide for the same at his
own cost; apply with copies of necessary ownership documents, Revenue
sketches, etc. of the site;
(ii) A Joint Undertaking between the owners, licensed developer, qualified
technical personnel for provision and compliance of the services and facilities;
(iii) Apply to the Competent Authority for necessary development permission as
prescribed and in accordance with these Regulations;
(iv) Carry out all the development works and facilities as per specifications and
standards.
(v) The owner and licensed developer are required to mortgage 25% of the
saleable land to HUDA as surety for carrying out the developments and
complying other conditions in the given time period, in the failure of which, the
HUDA shall be empowered to sell the mortgaged plots and utilize the amount
so realized for completing the development works. In such an eventuality the
developer his associates and the engineer/architect shall be black-listed and
not be allowed to undertake development works in the HUDA area.
(vi) The owner shall be entitled to dispose off the non-reserved sites and non-
mortgaged plots.
(vii) The owner shall hand over the specific sites stated in Regulation 3 (iii), (v)
and (vi) below to the HUDA free of cost and encumbrances before
undertaking development as per the approved plans.

3. Any Land Pooling Scheme shall make for the following provisions:
19

(i) Comply with the hierarchy of road network requirements as given in these
Regulations;
(ii) Earmark at least 1/3rd of total land area for Work center which may include
activities like commercial/offices/ market/ Information Technology Enabled
Services (ITES) / Light industries/ Service industries/ Transportation Node
activities/ Recreation based activities and Amusement.
(iii) Minimum of 10% of total area for parks, playgrounds, open spaces and properly
distributed within the Scheme and shall be of regular shape;
(iv) 2.5% for social infrastructure such as schools, dispensary/hospital, public utilities
spaces, shopping centres and other community spaces and earmark specific
sites for bus stands, auto stands, garbage collection points, etc.. These could be
planned as part of the area earmarked for Work center mentioned in (b) above;
(v) 5 % for sale by HUDA for residential/commercial use and as per location decided
by the Competent Authority;
(vi) 5% reservation of land for the purpose of providing housing accommodation for
Economically Weaker Sections( EWS)
(vii) 10% of the total land is earmarked for Lower Income Group (LIG) Housing with
maximum plot size upto 100 sqm
(viii) 10% of the total land is earmarked for Middle Income Group (MIG) Housing with
maximum plot size upto 100 sqm
(ix) The owner shall develop and dispose of the areas earmarked for LIG and MIG
given in (vii) and (viii) above. No amalgamation of plots in such blocks shall be
allowed.

4. There is no restriction on the plotted area. The balance area of saleable area shall
clearly give the type of housing development that would be undertaken viz., detached
houses, semi-detached houses, row type houses, duplex housing, condominiums,
apartment complexes, cluster housing, etc or a mix of all or combination of the
above. For each of the above, separate utilities and services plans and building type
designs as required under these regulations shall be got approved and development
and civil works undertaken as per approved plan and conditions. Approval would be
considered for these as a comprehensive approval as a project in which not only the
layout and development specifications and conditionalities are covered but also the
approval of individual blocks, buildings, scheme for development of on site
infrastructure facilities and amenities, etc are also included. The owner shall be
entitled to dispose off non-reserved sites and non-mortgaged sites either as plots or
as developed houses.

5. Maintenance to be under a single body:

The Land pooling Scheme developed shall be under the overall control and
management of a single management body who shall be responsible for the
maintenance and upkeep of the common facilities, greenery and the township.

6. Layout development schemes:

Layout provisions shall primarily apply to interstitial pockets of lands and


redevelopment schemes, plots sub-divisions, and those areas not covered in land
pooling schemes.

The owner of any land or groups of owners/developers who intend to sub-divide or


layout the land in such areas into building plots shall:
20

(i) Apply along with a licensed developer to the Competent Authority for necessary
layout permission as prescribed and in accordance with these Regulations;
(ii) Apply with copies of necessary ownership documents, Revenue sketches, etc. of
the site;
(iii) Carry out the layout development works as per specifications and standards.
(iv) the owner and licensed developer are required to mortgage 25% of the saleable
land to HUDA as surety for carrying out the developments and complying other
conditions in the given time period, in the failure of which, the HUDA shall be
empowered to sell away the mortgaged plots and utilize the amount so realized
for completing the development works. In such an eventuality the developer his
associates and the engineer/architect shall be black-listed and not be allowed to
undertake development works in the HUDA area.
(v) The owner shall hand over the specific sites stated in Regulation 8 (ii), (iii) and
(iv) below to the Competent Authority free of cost and encumbrances.

7. Plot sub-divisions/Amalgamation requirements:

(i) No plot sub-division/amalgamation shall be allowed unless these are permitted by


the Competent Authority. No building permission shall be entertained unless such
a sub-division permission is obtained first from HUDA.
(ii) The abutting road requirements, minimum plot size and other requirements shall
be in conformity with the Hyderabad Revised Building Rules,2006.
(iii) However, for a plot abutting existing major roads or highways, no plot sub-
division/amalgamation permission is necessary.
(iv) Such a site shall be minimum 125 sq mtrs.with a minimum frontage of 9 m and
abutting road shall be 9m for residential and 12 m for other non-residential uses.
(v) The minimum access permitted in case of sub-division of plots shall be 3.6 m for
residential and 6 m for non-residential plot sub-divisions.
(vi) Pro-rata open space charges (equivalent to 10 % of the total layout/colony area)
is required to be paid where there are no open spaces or shortfall.

8. Minimum area & other requirements for Layout Development:

The minimum area for layout application shall be 4 hectares. Owners of sites less
than 4 hectares have to jointly apply so as to conform to the minimum land area. The
layout proposals shall provide for the following:

(i) Comply with the hierarchy of road network requirements as given in these
Regulations;
(ii) Earmark minimum of 10% of total area for parks, playgrounds, open spaces,
(iii) Reservation of 5% of total area to be given free of cost to HUDA for disposal
for residential/commercial use
(iv) 5% reservation of land for the purpose of providing housing accommodation for
EWS.
(v) Earmark 2.5% for social infrastructure such as schools, dispensary/hospital,
public utilities spaces, shopping centres and other community spaces;
(vi) Earmark specific sites for bus stands, auto stands, garbage collection points,
etc.
(vii) 10% of the total land is earmarked for Lower Income Group (LIG) Housing with
maximum plot size upto 100 sqm
21

(viii) 10% of the total land is earmarked for Middle Income Group (MIG) Housing with
maximum plot size upto 100 sqm
(ix) The owner shall develop and dispose of the areas earmarked for LIG and MIG
given in (vii) and (viii) above. No amalgamation of plots in such blocks shall be
allowed.
(x) The owner shall be entitled to dispose off the non-reserved sites and non-
mortgaged sites either as plots or as developed houses/buildings. The owner
shall hand over all the above reserved sites at (iii) and (iv) to HUDA free of cost.
(xi) HUDA shall have the discretion of grouping the areas surrendered for LIG/EWS
Housing at one place or elsewhere and disposing the area earmarked for EWS
in the layout as normal building plots.
(xii) Residential enclaves may be permitted only if a through public road of width as
specified in Regulation 9 is developed at the periphery for the convenience of
accessibility of other sites and lands located in the interior.

9. Hierarchy and width of roads required in Land Pooling/layout schemes:

Land Pooling Scheme requirements shall conform with Regulation 2 and 3 above. In
case of layouts and sub-division of land for building purpose shall be carried out only
in accordance with the provisions of Regulation specified below:

(i) The layout shall have an approach from existing public or private roads of width
not less than 9 metres which shall be black-topped.

The width of the internal roads in a land pooling/layout scheme for different purposes
shall be regulated as follows:

Width of road for


commercial,
Width of road
Group Housing,
Road length (in for normal
industrial, other Other requirements
Mt.) residential
non-residential
plot/use (in mt.)
plot/use or for
mixed use(in mt.)
Utilities and services to be
underground and located
Up to 300 9.00 12.2 preferably under the
footpaths and not under
the main carriageway
Above 300 & up
12.2 15.00 -Do-
to 500
Above 500 & -Do- & mountable Road
18.00 18.00
less than 1000 Divider essential
Median and Service road
development essential;
Utilities and services to be
underground and located
1000 and above 36.00 36.00
preferably on service
roads and under the
footpaths and not under
the main carriageway
22

10. Splay at Road junctions:

Splay at road junctions shall be provided as prescribed below:

3.0 mt x 3.0 mt offset/splay if the width of the road is 9.00 mt or less;

4.5 mt x 4.5 mt. offset/ splay if the width of the road is above 9.00 mt but less than 18
mt

6.0 mt x 6.0 mt. offset/ splay if the width of the road is more than 18 mt in width

The area of such splay would be deemed to form an integral part of the road junction.

11. Development for EWS Housing:


These shall be permitted as group Housing and not as individual plotted
developments. The norms and specifications of development shall be as given by the
AP Housing Corporation Ltd/ A.P.Weaker Section Housing Programme/Government
issued from time to time.

12. Group Housing Schemes/Group Development Schemes:

(i) Such type of developments shall be in accordance with the provisions of the
Hyderabad Revised Building Rules,2006.

(ii) In such type of developments in sites 4000 sq m and above:

a. at least 10% of the total built up area /dwelling units shall be developed for
EWS dwelling units with a maximum plinth area of 20 sq m for each unit

b. at least 5% of the total built up area/ dwelling units shall be developed for LIG
dwelling units with a maximum plinth area of 40 sq m for each unit;

c. at least 5% of the total built up area/ dwelling units shall be developed for MIG
dwelling units with a maximum plinth area of 60 sq m for each unit
d. The areas mentioned in (a) to (c) above, shall be allotted/disposed off only for
these categories. No amalgamation of units shall be allowed.

13. Application for Permission:

For Land Pooling Scheme/Layout development:

Every licensed developer or body who intends to carry out development work or
undertake assemblage/ parceling of land into plots, or layout activity or Group
Housing Scheme/Cluster Housing Scheme or subdivide or make material alterations
shall apply in writing to the Vice-Chairman, Hyderabad Urban Development Authority
of such intention in the Form prescribed in Annexure A and the application for any
such permission shall be accompanied by Plans and statements in original ( drawn
on any durable medium) plus four prints along with copy of the ownership documents
of the plot/property/ land concerned and payment of prescribed application fees and
charges.
23

14. The Application for permission for a Land pooling Scheme or layout
development shall be accompanied by

i) a site plan drawn to scale of not less than 1:500 showing all physical details of the
land, boundaries of the land, the surrounding lands, airport zoning safety & obstacle
limitation surfaces and existing approach road to the land where the layout is
proposed;

ii) a Layout Plan (in required number of copies) drawn to a suitable scale preferably on
1:1000 for Land Pooling Schemes and 1: 600 for layout applications, showing
boundaries of land, sub-division of the land into building plots/ uses with dimensions
and area of each plot and its uses as per these regulations; width of the proposed
streets/roads ;dimensions and areas of open space provided according to these
regulations; dimensions and areas to be set apart for EWS housing, area for social
and cultural amenities, and area to be handed over to HUDA in case of a Land
pooling Scheme;

iii) Certificate of Undertaking in prescribed Form jointly by owner, licensed developer


and Licensed surveyor/engineer for carrying out the development works as per
standards.

iv) A topographical plan drawn to scale with contours and indicating the proposed
location of the water supply system, drainage and sewerage network and other
utilities of the proposed scheme

v) Land development schemes involving housing construction activity/civil works, the


building type designs together with the details of facilities proposed to be provided
shall be submitted. Such Land Pooling Schemes shall be prepared and signed by a
qualified town planner

Provided that before submission of such an application, pre-application consultation


shall be undertaken by the licensed developer/body with the Chief Planning Officer of
HUDA prior to the formal filing of an application for approval of a Land Pooling
Scheme or layout development scheme. This step does not require formal
application or the payment of a fee. When submitted, this Sketch Plan shall show in
simple sketch form the proposed Land Pooling Scheme and layout of streets, roads,
location of amenities, open spaces and other features in relation to existing
conditions.

Within fifteen (15) days, the Chief Planning Officer shall inform the licensed developer
wherein the plans and data as submitted or as modified do or do not meet the objectives of
the master plan/these Regulations and shall inform the licensed developer as to how said
objectives may be met. Any such consultation or advise by HUDA shall not constitute
approval or be binding on HUDA.

15. Sanction or Refusal of Permission:

The Land Pooling Scheme or Layout plans/ building plans with drawings and
specifications in accordance with these Regulations may be technically approved
with or without modifications or directions as are deemed necessary or refused by
24

the Hyderabad Urban Development Authority within 90 days from the date of receipt
of application.

Where no orders are communicated by the VC, HUDA of sanction or refusal of the
permission, the HUDA shall deemed to have permitted the proposals and the owner
may go ahead with the works after intimation and paying the requisite fees and
charges to HUDA before undertaking such development, and provided, the same is
in accordance with these regulations.

16. Payment of necessary fees and charges

The layout/Land Pooling Scheme applicant shall pay the necessary scrutiny fees and
charges including development charges before receiving the tentative approved layout
copy to VC,HUDA.
25

17. Duration of Technical Approval:

The technical approval shall be valid as follows:

for land pooling scheme – 3 years


for layout development approval – 2 years

during which time the land pooling scheme works/layout works/building construction
shall be completed, and if not completed the permission for land pooling
scheme/layout/building construction shall be revalidated on application subject to the
requirements then in force.

The revalidation fees shall be 50% of the scrutiny fees.

18. Revoking of Permission:

HUDA or the Collector or the Government as the case may be , may revoke any
permission issued under these regulations whenever it is found that there has been
any error or false statement or any misinterpretation of any material fact or regulation
on which the permission was sanctioned.

19. Deviations during construction/undertaking of layout works:

If during the execution of any land pooling scheme/layout or building construction any
deviation is made from the approved plan, the licensed developer/owner shall obtain
revised approval by duly following the above- mentioned procedure

20. Responsibilities and Duties of Licensed developer/ Builder/Owner:

The licensed developer/builder/owner who has been given approval and the technical
personnel shall be wholly and severally responsible for the quality of workmanship of
the building/layout development works, and/or structural safety of the building and for
ensuring safety during the construction /development works, and for complying with
the conditions laid down in these Regulations and the approved plans/drawings.

21. Obligations of the owner and licensed developer/builder/licensed technical


personnel to implement and develop the Master Plan circulation network and
specific land uses:

The owner and licensed developer/builder shall incorporate in the land pooling
scheme or layout all Master Plan specific land uses and amenity areas like
recreational buffer zone/Sector level open space and amenity space and road
network and shall develop the Master plan roads as part of the land pooling scheme
or layout at his cost. However, such area of Master Plan road alignment/ recreational
buffer zone/Sector level open space and amenity space shall be deducted from the
total site area of the Land Pooling Scheme or layout. The proposals of the Scheme
and the land utilization analysis would be taken on the remaining net area, and no
fees and development charges and other charges are leviable for such Master Plan
reservation areas and Master Plan circulation network.

22. Scrutiny by the Authority and responsibilities of layout developer for providing
services and facilities in the layout site:
26

(i) Layout shall be finalised by the Planning Department on the proposals


submitted by the applicant as per the notified Land Use and layout rules in force
from time to time and also as per the conditions imposed in change of land use
wherever applicable and should obtain the approval of Competent Authority.

(ii) A copy of such approved layout (unsigned) shall be handed over to the
applicant for demarcation of plots and open spaces as shown in the plan on
ground, only after payment of Development charges and processing charges
etc., to HUDA by the applicant.

(iii) The applicant shall submit a layout plan showing the measurements of plots
and open spaces along with the layout boundary measurements within a week
from the date of receipt of information.

(iv) The layout plan as submitted by the applicant should be recorded by giving the
L.P.No. ______________(Layout Plan No., with year) i.e., year-wise separately
and then the same will be forwarded to the concerned Local Authority for its
release after obtaining the approval of Competent Authority (Vice-Chairman),
along with earmarking 25% of plotted area in the layout plan duly imposing the
following conditions that:

a) The applicant shall execute the Deed of Mortgage by conditional sale to


HUDA as per rules.

b) The applicant shall solely be responsible for the development of layout and
in no way HUDA will take up the development works.

c) The deed of mortgage by conditional sale executed by the applicant in


favour of HUDA is purely a measure to ensure compliance of the condition
of development of infrastructure by the applicant/developer and HUDA is in
no way accountable to the plot purchaser in the event of default by the
applicant /development.

d) In case the applicant/developer fails to develop the layout area with the
infrastructure facilities as specified by the HUDA, the area so mortgaged in
favour of HUDA shall be forfeited and also HUDA is liable to take criminal
action against such applicants/developers as per provisions of A.P.U.A.(D),
Act,1975

e) The concerned Registrar of the Registration Department shall be informed


by HUDA, duly enclosing a copy of layout plan indicating clearly the
mortgaged area and the other plotted area, which can be permitted for sale
by the applicants.

f) The deed of mortgage by conditional sale executed by the applicant is


purely a measure to ensure compliance of the conditions of development of
infrastructure by the applicant/ developer and HUDA is in no way
accountable to the plot purchaser in the event of default by the
applicant/developer.
27

g) The Local Authority shall release such layout plan duly collecting the
required fee and charges as per their rules and also imposing any condition
on development of open spaces in the layout if necessary and the Local
Authority shall also ensure taking possession of roads and open spaces in
the layout.

h) The applicant shall take up the development of amenities such as formation


of roads, drainage line with septic tank as per standards, electric lines
including street lighting, water supply lines including overhead tank if
necessary and Avenue plantation along the roads and in open spaces to
the satisfaction of the HUDA within the stipulated period and the applicant
shall submit a requisition letter to the said effect to HUDA for taking further
action on release of mortgage plots/area which is in favour of Estate
Officer, HUDA, duly handing over open spaces and roads to the
concerned local authority.

i) In case the applicant does not want to take up the developmental works in
layout as mentioned at item ‘h’ above, he may as well be permitted to pay
the betterment charges to the Local Authority as per the rate prescribed by
them or the actual cost of development as arrived.

j) The Local Authority shall open a separate account for each layouts, where
the betterment cost has been paid by the applicant and the Executive
Officer of Local Authority shall ensure to spend the amount for development
of amenities in the same layout.

k) The concerned Executive Officer of Local Authority shall be responsible for


any problems in future either from the residents of the same layout area or
from any other person for non-implementation of amenities.

l) In case the applicant fails to implement Item ‘h’ above, the Vice-Chairman,
HUDA is competent to take up auction of mortgaged plots/area without any
further notice to the applicants and the amount so received in the auctioning
of plots/area shall be spent for providing amenities in the same layout.

m) The applicants/owners of plots in the layout are not competent to question


HUDA about the receipt of amount in the auction and also expenditure
towards the developmental works.

n) The concerned local authority shall not approve and release any building
permission or allow any unauthorised developments in the area under
mortgage to HUDA in particular and in other plots of the layout in general
until and unless the applicant has completed the developmental works/pay
required betterment charges etc., to the Municipality and then got released
the mortgage land from HUDA.

o) In case the said procedure is violated by the concerned local authority,


stringent action will be taken up against the responsible officers as per
rules.
28

p) Open areas shall be developed by the concerned developer along with


other developments of the layout as per the directions of the Director, Urban
Forestry, neatly with ornamental compound wall.

23. The licensed developer/owner while advertising/disposing the plots/blocks shall


clearly state the above status or category of the Land Pooling Scheme/layout development
with break up of infrastructure costs. In the case of Grade II development, the pricing shall
clearly mention the infrastructure facilities provided and assurance of the time frame for
completion of the full infrastructure facilities required.

S.P.SINGH
PRINCIPAL SECRETARY TO GOVERNMENT

SECTION OFFICER
29

ANNEXURE A
GROUP HOUSING SCHEME/LAYOUT APPROVAL UNDER REGULATION 12 AND 13 OF
THE HUDA DEVELOPMENT PROMOTION REGULATIONS & READ WITH U/S 13 & 14
OF THE A.P. URBAN AREAS (DEV) ACT, 1975.
(Read the provisions of the HUDA Development Promotion Regulations for the
conditionalities and requirements for permitting/undertaking such development)
FORM - A

To Dated :
The Competent Authority
Hyderabad Airport Development Authority
Secunderabad - 500 003.

Sir/Madam,

Application for (specify-- Land Pooling Scheme/Layout/Group Housing Scheme )

1. I/We hereby submit application for (specify - Land Pooling Scheme/Layout/Group


Housing Scheme and permission to carryout development works in the site covered by
Sy. No. ______________________ of ________________________ Village,
______________ mandal, District admeasuring -----------Ha/------- sq m / ---------- Acres
in accordance with section 13 & 14 of the A.P. Urban Areas (Dev.) Act, 1975.
2. I/We intend to undertake: (tick /specify which is applicable and strike out the ones not
applicable.)
a) Plotted layout development ;
b) Residential colony development with Civil construction as per approved type design;

c) Group Housing Scheme/ Cluster Housing Scheme with blocks of proposed residential /
dwelling units with Civil construction as per approved type design;
d) A mix of ------------------------------ with Civil construction as per approved type designs ;

3. I/We hereby enclose the necessary building type designs drawn to scale and in
accordance with the provisions of the Hyderabad Revised Building Rules,2006
(applicable only in case of (b) to (d).
4. The total extent of the site for the proposed development mentioned in 2 above is
__________ hectares _______________( acres).
30

1. The net area of the proposed development after deducting the area under the
following Master plan roads: (a) --------------------------------------------- (b) --------------------
------------ (c) ---------------------------- is __________ hectares ____________
( acres).

6. I submit the following documents & Plans and particulars in respect of the above
site proposed _____________ development (All copies of documents to be attested by
a Gazetted Officer).

i) Ownership and one link document copy.


a) Latest copy of the Pahani issued by Mandal Revenue Officer ;
b) Record of Rights pass Book/title deed for the proposed site.
c) Registered documents for the proposed site.
d) Copy of the Registered General Power of Attorney.
e) Copy of the Non-Encumbrance Certificate for the past 13 years
f) Copy of the Link Document

f) An affidavit declaring the total holding of the proposed site is within Urban ceiling
limits by each owner (wherever applicable).

g) Court orders / decrees confirming ownership/U.L.C clearance (wherever applicable).


h) Other documents (specify ________________________ in support of ownership &
U.L.C. Clearance aspects, if applicable
i) Revenue sketch of proposed site duly attested by Revenue Authorities.
ii) Location Plan of site and surrounding developments/lands drawn to a minimum
metric scale of 1:1000 showing surrounding roads, electricity lines, approved
layouts/Land Pooling Scheme/Group or Cluster Housing Scheme ,drainage, sewerage
etc. within 500 meters radius.
iii) A detailed surveyed topographical plan of proposed site for
___________________development to a metric scale of 1:600 showing the contours
of the land at 2 meters intervals, nalas, drains, wells, trees, roads, electricity lines,
sewer lines, etc.
iv) The proposed Land Pooling Scheme Land Pooling Scheme/Layout/ Group
Housing Scheme pattern draw to a scale 1 : 600 (original in any durable medium like
tracing cloth, film or reproduction tracing film, etc., & 3 sets of prints). Showing the
following details:

a) The boundaries of the proposed site distinctly shown in red;


b) The proposed plots/blocks with clear dimensions (limited to 55 % of total site
areas in case of layout applications).
31

c) The Public Open spaces of minimum 10% of the site area in one or more places
and in centre of proposed site’s blocks.
d) The area to be left for 5% EWS housing; 5% for HUDA in prominent location of
the site with clear approach roads to these Blocks;
e) The area earmarked for 10% LIG Housing of total land area with clear approach
road of 12.2 m
f) The area earmarked for 10% of total land area for MIG Housing with clear
approach road of 12.2 m
e) The area for common amenities like, Overheard Water Reservoir, common
septic tank areas, electricity Sub-station, Garbage disposal points etc., at proper
locations (which shall be over & above area mentioned in (c) above.
(e) The sites for social and community facilities (up to 2.5%) like Community
Centre/ Shopping Centre/ Educational Center/ Medical Centre

(f) The proposed road network within the site and integrating with neighboring and
surrounding road network and pattern, and incorporating the alignment of the
statutory Master Plan roads and developing these as required as per the HUDA
Development Promotion Regulations.

(g) The proposed channelization of natural drains & nalas with proper width and
green belt buffer within the site as required as per the HUDA Development
Promotion Regulations.

(h) Separate plans showing the proposed drainages, sewerage disposal


system and water supply, supply system for the project as per BIS code &
standards.

(i) All the above plans, and details of the above proposed project and
implementation are being undertaken through the following licensed technical
personnel:
Licensed Developer/ Architect Town Civil Structural Real
Technical Builder Planner Engineer Engineer Estate
Personnel Firm
Name
Address
License No. (Registration
No. only)
Signature

(j) I/we am/are herewith submitting the Joint Declaration & check list jointly filled by
me and the registered Architect and licensed Civil Engineer and request that our
application/development project may be considered and approved.

Dated : Signature of Owner (s) & Licenced developer/builder


32

Name Of Owner (s) & Licensed Developer/Builder ___________________________

______________________________________________________________________

Complete Mailing Address ____________________________________________________

_____________________________________________________________________

Phone No _______________________

DECLARATION

(TO BE SUBMITTED ON RS. 100/- STAMP PAPER & NOTARISED)

1. I/We hereby declare that I/We am/are the Owner/s of the site in Survey No. (s)
___________________ of ________________________ Village,
_____________________ Mandal, admeasuring _____________________ Hectares
on which the Land Pooling Scheme/layout development /Group/Cluster Housing
Scheme is proposed.

2. I / We hereby affirm / declare that the site / plot / property is not declared surplus
under the provisions of Urban Land ceiling Act, 1976. and is not a Government land.

3. The boundaries of the site and the areas mentioned in the layout plan are correct and
true.

4. I/We hereby affirm that I/we will abide by the Land Pooling Scheme/ Group /Cluster
Housing Scheme /layout approval conditions and the provisions of the HUDA Layout
Development Regulations, 2008, and will execute the all works including development
of the Master Plan roads at our cost and as per the specifications.

5. I/We affirm that I/we shall not sell or lease the plots of the areas earmarked for
mortgage sites until the final layout is approved;

6. I /We will hand over the sites/areas/plots duly developed and earmarked for EWS
housing, for HUDA, for public open spaces and for social & community facilities to
HUDA free of cost and without encumbrances through registered Gift deed to HUDA
before the release of the approved plans;

7. I/We agree that if I/we do not comply with the same within the given time period from
the date of approval, and HUDA would be at liberty to dispose off the mortgaged plots
and undertake the development works and we would not have any claim whatsoever
in the matter.

Dated: Signature/s of Owner(s) & Licenced Developer/ Builder


33

ANNEXURE- II
(G.O.Ms.No.288 M.A & U.D. (I1) Department dated 03-04-08)

The text and maps which indicates extensive modifications carried out to the Master
Plan / Zonal Development Plans of HUDA Area shall be read with the following
modifications:

A. The following Survey numbers are earmarked for Residential Use:


1. Sy. Nos. 323/2, 323/3, 323/4, 323/5, 323, 355, 356, 384, 385, 386, 387, 394, 395,
395/63, 396 to 403, 406, 407, 423, 444, 445 & 505 of Tellapur Village,
Ramachandrapuram Mandal
2. Sy. Nos. 285, 325, 326, 327, 328, 334, 335, 441 and 447 of Poppalaguda village,
Rajendranagar Mandal
3. Sy .Nos. 724, 725, 726, 728, 729 of Dever Yamzal village, Shamirpet Mandal
4. Sy. Nos. 36/B, 83, 85, 86, 101, 106, 111, 112, 113, 187, 188, 189, 190,191, 193,
201, 202, 203, 205, 206, 207, 221, 307, 308, 309, 310, 310/B, 311, 312, 313, 316,
316/B, 317, 317/B, 317/C, 317/D, 323/C, 332, 445/1, 445/2, 446 and 487 of
Bachupally village, Qutubullapur Mandal
5. Sy. Nos. 68, 100, 106 , 108, 109, 111, 112, 113, 115, 116, 117, 118, 119, 149, 150
( to the extent falling outside FTL and subject to leaving required buffer zone of 30
mts) of Kompally Village, Medchal Mandal
6. Sy. Nos. 569, 591, 593, 596, 993/46, 993/47 of Ameenpur village, Patancheru
Mandal
7. Sy. Nos. 101, 105, 130, 131, 132, 134 of Edulanagulapally village,
Ramchandrapuram Mandal.
8. Sy. No. 82/1 of Mallapur village, Uppal Mandal.
9. Sy. Nos. 17, 18, 19, 44, 47, 48, 49, 82, 83, 84, 123, 52/A of Jeedimetla village,
Qutubullapur Mandal
10. Sy. Nos. 35, 37, 38, 38/1 of Upparpally village, Rajendranagar Mandal
11. Sy.No. 9 of Alijapur village Rajendranagar Mandal
12. Sy.Nos 271, 272 of Ankushapur village, Ghatkesar Mandal
13. Sy.Nos 11 to 19, 21, 22, 23, 25 to 34, 39, 40 to 43 of Peerancheru village,
Rajendranagar Mandal
14. Sy.Nos 135, 136, 137 of Dulapally village, Qutubullapur Mandal.
15. Sy.Nos 91 ,92,93, 94, 100, 144, 145, 299, 300,350 and 353 of Balapur village,
Saroornagar Mandal subject to providing buffer towards RCI land
16. Sy.Nos 23 and 33 of Kowkur village, Malkajgiri Mandal
17. Sy.Nos 74, 75, 81 to 85, 177 of Yellampet village, Medchal Mandal
18. Sy.Nos 172, 173, 174, 175 of Hayatnagar village, Hayatnagar Mandal
19. Sy.Nos 104 to 109 of Nagaloor village, Qutubullapur Mandal
34

20. Sy.Nos 439, 443 to 446, 448 to 453, 455 to 460, 458/A, 462 , 468, 469, 470, 494,
495 and 497 of Gowdavalli Village, Medchal Mandal
21. Sy.Nos 61 to 65, 107, 260, 261, 284, 298 to 354, 302/AA of Kollur Village,
Ramachandrapuram Mandal and all other adjoining Sy. Nos. of Kollur Village and
Edulanagulapalli Village bounded by residential use on northern side; ORR Growth
Corridor on eastern side; Kollur Cheruvu on southern side and proposed multiple
use zone on western side.
22. Sy.Nos 10 to 17, 217, 219, 262 to 269, 273, 276, 278 to 303, 284/1 ,2 ,285/A,
302/1, 303/1, 315 to 327, 317/1,317/3, 318/2, 318/3, 332, 332/A, 332/AA, 334, 336,
337, 328, 330, 331, 333, 335, 338, 339, 341, 342, 343, 345, 347, 348, 349, 350,
357, 373, 374, 375, 387, 429, 430, 431, 432, 437, 438, 439, 440, 444, 446 to 454,
457 to 467, 523, 523/2, 538 of Gundlapochampally Village, Medchal Mandal
23. Sy.Nos 83 to 87, 91, 92, 148, 149, 150, 151, 152 of Boduppal village, Ghatkesar
mandal
24. Sy.Nos 133, 140 of Chengicherla village, Ghatkesar Mandal
25. Sy.Nos 78, 98 to 106, 108 to 116, 128, 129, 130, 132 to 140, 142, 143, 144, 145,
159 to 163, 197, 198, 249, 252, 253, 255 to 259, 264,312,313/1 and 313/A of
Athvelly village, Medchal Mandal
26. Sy.Nos 18, 20 to 24, 27 to 31, 37, 52, 54, 55, 60 to 65, 67 to 69, 149, 151, 152/1,
153, 154/1/A, 156/1, 164, 166/2, 167, 181 to 187, 190 to 192, 208 to 214 and 220
of Kokapet village, Rajendranagar Mandal
27. Sy.Nos 15, 23, 23/A, 29 to 33 of Shivarampally Jagir village, Rajendranagar
Mandal
28. Sy.Nos 54 and 76 of Hafeezpet Village, Serilingampally Mandal
29. Sy.Nos 107, 108, 109, 110, 112, 113, 116, 119, 120, 135, 136, 140, 143, 149, 158,
160, 161, 165, 168, 170, 171 of Aushapur village, Ghatkesar Mandal
30. Sy.Nos 522 to 527, 543/3 to 543/7, 543/9 to 543/12 of Ghatkesar village,
Ghatkesar Mandal
31. Sy.No. 549 of Uppal Khalsa village, Uppal Mandal
32. Sy.Nos 33, 61 to 65 of Ahamadguda village, Keesara Mandal
33. S.Nos. 368, 368/A, 380, 504 to 508, 510, 511 of Puduru Village, Medchal Mandal
34. Sy.Nos. 19, 20, 21, 23, 28 to 35, 38, 39 of Gandipet Village, Rajendranagar Mandal
35. Sy.No.71 of Dabilpur village, Medchal Mandal
36. Sy.No. 59 of Kothapet village, Saroornagar Mandal
37. Sy.Nos. 57 to 60, 63, 290, 291 of Cherlapally village, Keesara Mandal
38. Sy.Nos. 12, 13, 14, 18, 20, 43, 45, 50 to 53, 59, 60 (to the extent falling outside
FTL and mandatory buffer zone) of Bandlaguda village, Uppal Mandal
39. Sy. Nos. 44, 51, 52, 63, 65, 66, 76, 77, 78, 80, 102, 119 to 124, 1246, 1248, 1274
to 1277, 1278, 1283 of Shameerpet village. Shameerpet Mandal
40. Sy.No 1009 of Kukatpally village, Balanagar Mandal
41. Sy.Nos. 345 to 348, 351, 352, 353 of Muttangi village, Patancheru Mandal
35

42. Sy.No. 294 of Pedda Amberpet village, Hayathnagar Mandal


43. Sy.Nos. 5, 6, 7, 10 to 14, 16, 17, 22, 25, 27, 28, 29, 31, 33 of Osmannagar village,
Ramachandrapuram Mandal and all other adjoining Sy. Nos. of Osmannagar
village located on northern, eastern and westernsides up to village boundary.
44. Sy.Nos. 145 to 149 of Yemnampet village, Ghatkesar Mandal
45. Sy.Nos. 267, 268, 269 of Keesara village, Keesara Mandal
46. Sy.Nos.881 of Medchal village and Medchal Mandal
47. Sy.Nos. 142, 143, 144, 150 of Narsingi village, Rajendranagar Mandal
48. Sy.Nos. 69, 86, 87, 88, 89, 99, 100, 102 of Suraram village, Qutubullapur Mandal
49. Sy.Nos. 360, 361, 396, 397, 398 of Manchirevula village, Rajendranagar Mandal
50. Sy.Nos. 220 to 223, 228, 231, 232, 233, 235, 238 to 242 of Bogaram village,
Keesara Mandal
51. Sy.Nos. 201 to 208, 215, 216 of Gogillapur village, Qutubullapur Mandal
52. Sy.Nos. 50, 51, 56, 57, 115, 116, 117, 250, 251, 254 of Gopanapally village,
Serilingampally Mandal
53. Sy.Nos 225, 226, 267, 268, 269, 288 of Rampally village, Keesara Mandal
54. Sy.Nos. 575, 576, 588 to 593, 619 of Ghanapur Village and S.No.286, 287 of
Patighanapur village, Patancheru Mandal
55. Sy.Nos. 802/A/AA, 802/A/E, Ankireddypally village, Keesara Mandal
56. Sy.Nos. 177, 179, 180/2, 185, 187, 195 of Tumukunta village, Shameerpet Mandal
57. Sy.Nos. 612, 613, 614, 616, 642 to 644, 689 of Dundigal Village, Medchal Mandal
58. Sy.No. 13 of Akbarza village and Sy.No 11 of Macchabollaram village, Malkajgiri
Mandal
59. Sy.Nos. 268,269,272 to 275 of Chandanagar village, Serilingampally village are
deleted from congested zone and developments shall be allowed without any
height restrictions
60. Sy. Nos. 923 to 926, 933 to 935, 946, 952, 957 to 961 of Jawahar Nagar Village,
Shamirpet Mandal.
61. Sy. Nos. 118 to 121, 126 to 131, 194 to 198, 200 to 205, 207 to 216, 235 to 246
248 to 252, 254, 256, 257, 258 of Tellapur Village, Ramachandrapuram Mandal
and all other adjoining S.Nos. of Tellapur Village bounded by railway track on
northern side; 30 mts wide proposed road on eastern side (located on the western
side of Tellapur village settlement ) ; 30 mts wide proposed road on southern side
and Tellapur village boundary on western side.

B. The following Survey numbers are earmarked for Commercial use:

62. Sy.No. 353 of Gajularamaram village, Qutubullapur Mandal


63. Sy.Nos. 429, 430, 431, 432, 433, 439 Bowrampet village, Qutubullapur Mandal
64. Sy.Nos. 8, 11, 12, 13, 55, 55 / E of Kondapur village, Serilingampally Mandal
36

65. Sy.Nos. 516/A, 516/AA, 517 of Muttangi village, Patancheru Mandal


66. Sy.No. 645 / 1 of Amberpet Kalan village, Hayatnagar Mandal
67. Sy.Nos.169 and170 of Kukatpally village, Balangar Mandal
68. Sy.No. 47 of Jeedimetla village, Qutubullapur Mandal
69. Sy.Nos 79 of Yellampet village, Medchal Mandal
70. Sy.Nos 83, 84, 85, 86, 87, 88 of Hafeezpet Village, Serilingampally Mandal
37

C. The following Survey numbers are earmarked for Multiple Use Zone:

71. Sy. Nos. 199, 200, 204, 223, 257, 258, 259, 262, 276, 281, 282 of Bachupally
village, Qutubullapur village
72. Sy. Nos. 109 to 114, 244 to 249 of Gopanapally village, Serilingampally Mandal
73. Sy. Nos. 511 to 518, 599, 621, 649 to 666 of Gundlapochampally village, Medchal
Mandal
74. Sy.Nos. 329 to 333, 345, 346, 351, 352, 353, 354, 355, 356, 381, 391, 392, 393 of
Poppalguda village, Rajendranagar Mandal
75. Sy.Nos. 136, 137, 145 to 148 of Narsingi village, Rajendranagar Mandal
76. Sy.Nos. 219, 222, 224, 225, 226, 229, 264 to 272, 276, 277, 279 to 284, 286 to
297, 299 of Nallagandla village, Serilingampally Mandal
77. Sy. Nos. 1050, 1051 of Kukatpally village, Balangar Mandal

D. Other Modifications

78. Sy.No. 90 of Mansoorabad village, Saroornagar Mandal is earmarked for


Institutional Use Zone
79. Sy.Nos.450 of Sultanpur village, Patancheru, Mandal is earmarked for Industrial
Use
80. Sy.Nos.165 to 172 of Boduppal village, Ghatkesar Mandal is earmarked for
Conservation Use Zone
81. The proposed 30 Mtrs Road passing through Sy.No.384, 385, 386 and 387 of
Tellapur Village is realigned to converge it with the existing 9 meters Road leading
from Tellapur to Shankarpally Road to join at 24 meters T-junction.
82. The proposed 60 meters road in Sy.No.280, 281 & 279 in Budvel village of
Rajendranagar Municipality lands, is realigned along the existing 30 meters wide
road in the Sy.No.281, 284, 285 and 286 of Budvel (V), Rajendranagar (M)
R.R.District and another 30 meters wide proposed road passing through
Sy.No.277, 270 and 268 of Budvel village is deleted.
83. The existing 12 meters Road from Sufilguda Station point to Jyothi nagar in
Malkajgiri village is designated as 18 meters road.
84. The proposed Uttam Nagar to Jyothi Nagar road in Malkajgiri area till Tukaram gate
is designated as 18 meters road.
85. The proposal to widen the existing road passing through Sy.No.661, 771, 658 &
684 of Yellareddyguda, Kapra is dropped.
86. The existing road from Gopanpally X Road to Nallagandla settlement is designated
30 meters.
87. The width of proposed road from Kukatpally main road (near JNTU gate) to
Pragathinagar passing through HMT Colony and Amber Cheruvu is designated as
15 meters.
38

88. The proposed 30 meters road passing through Sy.Nos.441 & 447 of Poppalguda
(V), Rajendranagar (M) is deleted.
89. The width of the proposed road passing through Sy. Nos.371 & 372 of
Gajularamaram Village, Quthubullapur Mandal is designated as 18 meters.
90. The existing 60 feet wide road below the H.T.line on the western side of Neralla
cheruvu, Kondapur village is continued further to connect the existing Kothaguda to
Kondapur road.
91. The 200 feet wide road proposed through Sy. No. 49 & 51 of Kowkur village is
realigned towards southern side to converge it with the existing alignment shown in
the Layouts approved by HUDA.
92. The proposed width of the existing R& B road from Miapur to Dundigal X roads,
Gajularamaram (V), Qutubullahpur (M) is designated as 60 meters.
93. The width of the proposed road connecting Old Bombay Highway with the New
Bombay Highway passing through Sy.No.49, 50, 48 etc. of Madeenaguda Village
and Sy.No.73, 85 and 83 of Serilingampally village is designated as 45 meters.
94. The proposed road passing through Sy.Nos.403 and 404 of Tellapur village, RC
Puram Mandal is realigned along the existing road.
95. The proposed road passing through Sy. Nos. 1011/5, 1011/6, 1011/7A, 1011/8,
1011/9, 1011/10 and 1011/11 of Moosapet is realigned along the existing IDL Road
and existing 12 meters kutcha road
96. The width of the proposed road from Sainakpuri Cross roads to College of Defence
Management is designated as 24 meters.
97. The existing road passing all along plot Nos 11 to 19 in Sy.Nos. 310, 311, 318 to
323 and 337 of Poppalaguda Village, Rajendranagar Mandal, Ranga Reddy District
is designated as 18meters road.
98. The proposed 24 meters road passing through Sy.Nos.152, 155, 159, 160 of
Neknampur village is extended up to radial road leading to Narsingi (Gandipet Main
road).
99. A new 30 meters road is proposed all along the existing kutch road through S.
Nos.15, 10 of Osmansagar village and S.No.124 and 262 of Gopanapally (v)
connecting Gopanpally - Vattinagulapally main road with the another proposed 30
meters road located on southern side of Sy.No.14 of Osmannagar village.
100. 18 meters wide road connecting Nizampet road (near K Raghava Reddy Gardens)
and Bolarum Road (near Dr Reddy’s Research Foundation) underneath the H.T.
line is proposed.
101. The proposed 30 m road in Sy Nos 168, 171 to 175, 202 to 205, 211, 229 to 232,
240, 243, 244, 260 and 263 of Nagaram (V) is realigned along the existing 18
meters road. Another 30 meters road passing through Sy Nos. 43, 46, 47,51 to 53
and 56, 67 of Cheralapalli (V) Sy.No.67 is realigned through the road on western
side of Mint to Cherlapally (V)
102. The width of the link road (abutting the Survey of India premises) connecting
Tarnaka-Uppal Inner Ring Road and Ramanthapur-Uppal Road is designated as
36 meters.
103. The proposed width of existing road in Sy No. 1046/1 and 2 of Medchal (V) is
designated as 18 meters.
39

104. The road proposed through N.F.C Complex (D.A.E. Lands) Moulali from Sy. No.
368/1 of Malkajgiri village up to over bridge near Mallapur is deleted.
105. The proposed master plan roads passing through Sy. Nos. 923 to 926, 933 to 935,
946, 952 and 957 to 961 of Jawahar nagar Village, Shameerpet Mandal are
realigned along the layout roads.
106. The road existing on the western side of the Peerancheruvu lake and Govt.,
housing passing through Sy. No. 24, of Peerancheruvu village is designated as 30
meters road and continued further through Sy. No. 33,35,36 of Peerancheruvu
village and S.Nos. 44 and 45 of Bairagiguda village and connected to proposed 30
meters Peerancheruvu-Gandhamguda road (located on the eastern side of
Peerancheruvu lake).
107. New link road of 30 meters width connecting Radial Road No.17 upto the present
ORR junction with NH. 202 is proposed.
108. The proposed 30 meters road parallel to Railway line from Rampally and Pocharam
is extended up to NH 202
109. The width of the road from R K Puram to ECIL X Road is designated as 45 m
110. The proposed width of the road passing through the Sy Nos. 476(P) to 479(P) of
Attapur village is designated as 18 meters.

The above modifications are subject to the following conditions:

(i) In respect of lands which are partly falling in HUDA Master Plan and partly
falling in ORR Growth Corridor, the above modifications will apply only to the
extent of land which is outside the ORR Growth Corridor.

(ii) The above modifications shall not be used as the proof of any title of the land.

(iii) The applicants shall obtain prior permission from Hyderabad Urban
Development Authority/Local Authority concerned as the case may be before
undertaking any development.

(iv) The owners/applicants are solely responsible for any misrepresentation with
regard to ownership/ title, Urban Land Ceiling Clearances etc. The owners/
applicants shall be responsible for any damage claimed by any one on
account of above changes.

(v) The owners/ applicants shall handover the areas affected under the notified
roads to the local bodies at free of cost.

(vi) The owners/ applicants shall develop the roads free of cost as may be
required by the local authority.

(vii) As per the revenue records if any tanks / water bodies / nalas are located in
the above Sy. Nos. same shall be retained as it is and required buffer zone as
per extant rules shall be provided all along such tanks / water bodies / nalas.
40

S.P. SINGH
PRINCIPAL SECRETARY TO GOVERNMENT

SECTION OFFICER

You might also like