Saep 324
Saep 324
Saep 324
1 Scope............................................................. 2
2 Conflicts and Deviations................................. 2
3 Applicable Documents.................................... 2
4 Definitions and Acronyms............................... 3
5 Responsibilities............................................... 5
6 Instructions......................................................6
1 Scope
1.2 Unless specifically noted otherwise the term welder shall also mean welding
operator.
1.3 Welders Performance and Guidelines Criteria are provided in Appendix I of this
procedure.
1.5 This procedure does not apply to permanent Manufacturers Fabrication Facilities.
1.6 This procedure does not apply to Maintenance Projects as defined in Section 4.
Conflicts between this Engineering Procedure and any other Saudi Aramco Standard
shall be resolved by the Chairman of the Inspection Engineering Standards Committee
of the Inspection Department in writing.
3 Applicable Documents
Unless stated otherwise, all codes and standards referenced shall be the latest issue
(including Revisions and Addenda). When industry codes and standards, or Saudi
Aramco standards are required for use by project specification they shall become a part
of this Engineering Procedure.
Page 2 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
Certified Welder: A welder that has a valid welder certification. A certified welder is
only qualified to weld with those welding processes, and within the essential variables,
of the valid certification according to the qualification governing code.
Contractor Welder: A welder working directly for, and under the supervision of, a
contractor.
Fabrication Shop: A building used for the fabrication and/or assembly of equipment
and structures such as pipe spools, pressure vessels, etc.
Fabrication Yard: A large open outdoor area used for the fabrication and/or assembly
of very large structures such as offshore platforms, large pressure vessels, etc.
Field Fabrication Shop: A temporary fabrication shop set up in the field near a
construction project by a contractor to fabricate piping, fittings and/or structural
components.
Page 3 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
Saudi Aramco Approved Welder Testing Agencies: list available from ID website or
as recommended by ID representative on site.
Saudi Aramco Construction Safety Manual: as available from Saudi Aramco Loss
Prevention Department
Uncertified Welder: A welder that does not have a valid welder certification.
Page 4 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
Welder Certification: Certification in writing that a welder has produced a test weld
meeting a defined standard.
5 Responsibilities
5.2. The Project Welder Tracking Coordinator is responsible for tracking all issued
JCC’s, welder performance and revoking of JCC’s either at section level for
small to medium size projects or on a single Mega Project.
Page 5 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
6 Instructions
6.1.1 Contractors, fabricators and vendors are responsible for the testing and
certification of welders working under their supervision in accordance
with the governing Codes, standards, and or specifications of each
project.
6.1.2 The project inspector shall have the right to require the removal or retest
of any welder at any time due to unsatisfactory work or poor
performance as indentified in Appendix I Welder Performance
Guidelines.
6.1.5 The first three (3) production groove welds by each new contract welder
shall be radiographed 100%. Radiograph acceptance shall be as
specified by the applicable Code.
6.1.6 The first three production groove welds will not be included in the project
welding statistics or weld repair rates for daily welding production
percentage. The percentage radiography requirement is as listed in the
applicable SAES-W-011 Section 17 and SAES-W-012 Section 16. Each
welders and Welder operators work shall be represented in the
percentage required.
6.1.7 For decision path on the first three (3) production welds see Appendix III.
Page 6 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
6.2.4 Contractor welders that have not been properly certified shall not be
permitted to weld.
6.2.7 The project inspector shall monitor the contractors quality control
program to determine whether contractor welder certifications are being
maintained in accordance with the governing Codes and standards of the
job or project. Contractor welders that do not maintain valid
certifications shall have their JCC withdrawn. Once withdrawn, JCC's
will only be reinstated upon receipt of written proof of training, and the
successful completion of a recertification test. All withdrawn JCC's shall
be sent to the Project Welder Tracking Coordinator, where they will be
kept on file for a period of at least three years.
Page 7 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
6.2.8 For offshore pipelines and structures all welders welding primary joints
(refer to SAES-W-013, Table 4, Note 7) shall be requalified if the
original performance qualification test was not witnessed by a third party
inspection agency. Requalification testing shall be witnessed by a third
party inspection agency or the project inspector.
6.2.9 For offshore pipelines and structures all welders welding joints other
than primary joints shall be retested on a 10% random basis, as selected
by the project inspector unless the original performance qualification test
was witnessed by a third party welder testing agency. Requalification
testing shall be witnessed by a third party inspection agency or project
inspector. If the requalification failure rate exceeds 20%, all welders
shall be retested.
6.3.1 For a land based Permanent fabrication yard or Project temporary field
fabrication yard, the fabricator shall maintain a welder identification
system acceptable to the project inspector. Welders shall carry an
identification card that includes a photo, welders name, company
identification number, and welders symbol.
6.3.2 A list of all welders shall be submitted to the project inspector prior to
the start of work. This list shall be maintained up to date by the
fabricator. The list shall include the welders name, symbol, processes
qualified and all other important essential variables as well as
certification issue dates.
6.3.3 The project inspector shall regularly audit welder certifications to ensure
fabricator compliance with the Codes, standards and approved Quality
Plan.
6.4.2 Job Clearance Cards are only valid for the job or project for which they
are issued.
6.4.3 Job Clearance Cards can be withdrawn by the project inspector at any
time for cause if the contractor welder is not producing work of
acceptable quality. Once withdrawn, JCC's will only be reinstated upon
Page 8 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
6.4.4 Job Clearance Cards shall be returned to the Project Welder Tracking
Coordinator when the contractor welder goes on home leave or is
terminated from the project. Contractor welders that return to work
within three months from home leave (to the same project) may be
reinstated without retesting.
Revision Summary
27 September 2009 Major revision.
Page 9 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
Notes:
1. Contractor’s Welding Process Control Procedure (Company approved) shall clearly state acceptable Welding
Performance parameters for initial and weekly production.
2. Procedure shall define Linear & Joint method performance targets and these quality targets shall be acceptable
to COMPANY and approved before welding begins.
3. Procedure shall detail NDT requirements of initial Welder production to determine acceptability of welder
performance, especially with new welders.
a. First three joints as a minimum shall be examined.
b. Welders shall not make additional initial production welds until their “initial performance” has been verified
and NDT results are acceptable per the procedure.
c. First three joints shall not be counted as routine daily production for project WRR.
4. Procedure states maximum number of consecutive weeks when a welder exceeds performance targets.
Severe weather or other factors beyond welder control may be considered.
5. Procedure shall state the amount of NDT up to 100% when target repair rates are exceeded or when a welder
has been removed from Work.
6. Pipeline Projects using Semi-automatic / Automatic / Combination Processes may utilize even more stringent
Weld Quality Guidelines than those listed above for Manual process.
7. Level A, B & C Welders
a) In all cases, Welder performance should target “A” Classification results with the lowest possible Linear &
Joint Repair Rates achievable.
b) Continuing Process Improvement, Cost Effectiveness is acceptable for Cat. A & B welders.
c) Cat. C welders are not cost effective and require close supervision)
Page 10 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
8. Level D Welders
a) Welders may exceed the 7.5% joint WRR weekly for a maximum period of 2-3 weeks with close
surveillance on all repairs.
b) Additional supervision / additional NDT (to 100%) is required until consistent results of 7.5%
WRR or less (joint repair rate) are achieved.
c) If WRR target is not achieved within 2-3 weeks, the options are: (i) welder may be considered
candidate for re-training and retesting or (ii) revoke qualification and remove from production
work.
Page 11 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
WBS Photo
Project
Contractor
Welder Name Symbol
Note: This clearance card is for welding on the above mentioned project
only, and may be revoked if welder's performance is not satisfactory.
Card must be returned when welder is removed from this project.
PID Section
Material P-No's
Process
Electrodes/F-No's
Position/Progression
Min/Max Thickness
Diameter Range
JCC No.
Page 12 of 13
Document Responsibility: Inspection Engineering Standards Committee SAEP-324
Issue Date: 27 September 2009 Certification Review and
Next Planned Update: 27 September 2014 Registration of Project Welders
Page 13 of 13