Competency Demonstration Report - CDR: Career Episode 3 - Ce 3
Competency Demonstration Report - CDR: Career Episode 3 - Ce 3
CAREER EPISODE 3 – CE 3
A. INTRODUCTION
CE3.1 In this career episode, I will discuss my job from March 2010 to present. I am
currently employed at Zuhair Fayez Partnership Consultants for the King Khalid
University Projects, a Kingdom of Saudi Arabia government project by the Ministry
of Education to establish an educational institution in the Southern Province;
CE3.3 Main task is to ensure that all construction processes complies with the established
system as the organization is a certified ISO 9001:2008 company, and ensure that,
products are delivered to the client as per requirements and on – time.
B. BACKGROUND
CE3.4 Zuhair Fayez Partnership Consultants is one of the leading and most established
Architectural, Engineering, Project Management, Constructions Management and
Engineering Information System Consultancy firms in the Kingdom of Saudi Arabia;
CE3.8 King Khalid University (KKU) Projects is a US$ 3.4 Billion project of the Governorate
of Kingdom of Saudi Arabia’s Southern Province. Our Scope consists of 3 phases,
Phase – 1 as Male Academic Campus with 16 Buildings for Engineering, Sciences
and Administrative use, Phase – 2 as Medical City with 6 buildings for Medical
Sciences and a 800 beds Teaching Hospital, Phase – 3 are for KKU Administration
Buildings which comprise of 5 buildings for administrative use;
CE3.9 Included in our scope are the infrastructures, road networks and service buildings.
1. Prepared list of all Quality Documents that Contractors had to submit such as the
following:
Project Quality Control Manual;
Project Quality Systems;
List of Testing Equipment and Machineries;
List of Method Statements for all site activities;
List of Inspection and Test Plan;
Recommended List of Materials and Suppliers;
List of nominated Sub-Contractors including Testing Company;
Concrete Damage Prevention and Repair Methods;
2. Required Contractors to prepare and submit Materials Delivery Schedule which
paralleled to the Construction Master Schedule
3. Conducted site survey with the Contractors QA/QC Team to identify materials lay
down yard and locations for the materials warehouse.
CE3.15 Immediate superior tasked me to analyze and study the applicability of current
Quality Processes the company has in regards to the processes at site and current
organizational structure. Part of this task was to find loophole in the procedures, and
ensure that all procedures once issued should produce an efficient process for the
project team.
CE3.17 Using Engineering skills and knowledge in quality system based on previous
experience and review the Contractors Project Quality Plans, ZFP Quality Manual
and Project Contract, taking notes of QA procedures that require revisions to suit
the project requirements.
E. PROBLEMS ENCOUNTERED
CE3.18 During review with the current ZFP Quality Manual, the QA processes has been
noticed on; works instructions, work procedures and Quality Control Forms are
incomplete and some are ambiguous, which are not applicable to the current project
site and might lead to confusion between the ZFP Management Team and
Contractors and will impede the achievement of total quality control on the site.
CE3.19 Also, noticed that several Quality Assurance Forms are missing, forms that are
basic requirements for QA/QC processes.
CE3.20 At the start of the construction stage, the Contractors suggested to include in their
interim payments the materials that will be delivered on the site, ZFP Management
team have opposed this suggestion since the materials that will be delivered are not
inspected or tested.
CE3.22 The Projects Coordination Manager which is the 2nd in – charge from the Project
Director assigned me to author a Site Quality Manual that would be suitable for the
implementation of Quality Control at site and ensure the efficient implementation of
QA/QC Processes.
CE3.23 Based on the project and construction requirements in regards to the Technical and
Engineering activities, a Site Quality Manual was prepared to include Work
Procedures and Work Instructions, ZFP Company Quality Manual and ISO
9001:2008 Quality Management System are used as reference.
CE3.24 Also revised the Quality Control Forms and add the missing forms and includes the
Quality Manual flow charts to ensure processes will be understood.
CE3.25 Completed the Manual within six (6) months period including revisions and attached
are indexes and few of the processes contained in the Quality Manual including the
forms (refer to attachment on pages 6 – 18).
CE3.26 To solve the Quality issue of ensuring the materials delivered on the site will be as
per approved and specified requirements, procedure has to be prepared titled
Materials/Equipment Delivery Inspection and also prepared the
CE3.27 One of the main problems of QA/QC process is keeping its applicability at the site.
Resolve this problem by proposing a program to the management to make a yearly
audit and orientation program to the project team.
CE3.28 Every process is reviewed and prepares any changes and submits it to the QA
Department in the ZFP headquarters for approval.
G. SUMMARY
CE3.29 Working on a prestigious and multi –billion cost project is a challenging one,
especially for a QA/QC Engineer. Once completed, King Khalid University will be
the biggest university in the Southern Province and one of the biggest in the
Kingdom of Saudi Arabia with three (3) million square meters developed area.
CE3.30 During the preparation of Site Quality Manual, It has given me more experienced
and knowledge in the field of Quality Management System, showing knowledge and
dedication to my work, the company promoted me to Senior QA/QC Engineer level
after two (2) years and six (6) months working with the company. The promotion
gave me additional challenge when the management made me in – charge for
QA/QC Department of the entire KKU Project. Knowledge in engineering processes
was enhanced more and was exposed to troubleshooting repairs and problem
solving and anticipating problems during the construction stage.
CE3.31 Also, in charge in the Handover and Testing and Commissioning stage which raised
my knowledge in the turn – over of mega projects including different engineering
field such as supervising the handover of medical facilities and equipments.