03 CDR Summary Statement Form

This document contains Peter Marc B. Bitar's summary statement for assessment as a Professional Engineer. It lists the competency units and elements that must be addressed, including knowledge and skill base, engineering application ability, professional and personal attributes. For each element, it provides paragraphs from career episodes that demonstrate how Peter has applied that element in his work as an engineer.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
427 views5 pages

03 CDR Summary Statement Form

This document contains Peter Marc B. Bitar's summary statement for assessment as a Professional Engineer. It lists the competency units and elements that must be addressed, including knowledge and skill base, engineering application ability, professional and personal attributes. For each element, it provides paragraphs from career episodes that demonstrate how Peter has applied that element in his work as an engineer.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

PROFESSIONAL ENGINEER

Summary Statement
OF
PETER MARC B. BITARA

These are the competency Units and Elements. These elements must be addressed in the Summary
Statement (see Section C). If you are applying for assessment as a Professional Engineer, you will
need to download this page, complete it and lodge it with your application.

Paragraph in the career


A brief summary of how you have
Competency Element episode(s) where the
applied the element
element is addressed
PE1 KNOWLEDGE AND SKILL BASE

I have used my knowledge in CE1.6, CE1.7, CE1.8,


Mathematics, Engineering Management, CE1.9, CE1.17, CE1.18,
PE1.1 Comprehensive, Concrete Design, Soil Mechanics, CE2.3, CE2.8, CE2.10,
theory-based understanding Engineering Estimates, Materials CE2.11, CE2.12, CE2.14,
of the underpinning natural Engineering, Quality Management and CE2.16, CE2.25, CE2.26,
and physical sciences and the Analytical Calculations to complete tasks CE2.27, CE2.28, CE2.29,
engineering fundamentals given to me. CE2.33, CE2.34, CE3.3,
applicable to the engineering CE3.7, CE3.11, CE3.13,
discipline CE3.14, CE3.15, CE3.17,
CE3.23, CE3.24, CE3.26,
CE3.27

I have applied my technical knowledge in CE1.6, CE1.8, CE1.18,


Engineering that aid me in successfully CE2.10, CE2.14, CE2.16,
analyzing and resolving given problems. CE2.27, CE2.28, CE2.29,
CE2.32, CE3.13, CE3.14,
I have used my strong educational CE3.15, CE3.16, CE3.17,
background and comprehensive CE3.23, CE3.24, CE3.26,
PE1.2 Conceptual theoretical knowledge to help in my CE3.27
understanding of the analysis.
mathematics, numerical
analysis, statistics and I developed engineering process and
computer and information systems to avoid errors and resolved
sciences which underpin the accordingly if one arises.
engineering discipline
I carried out design and mathematical
calculations, engineering management
and quality system based on engineering
principles, technical knowledge and
engineering standards.
I have proven knowledge in engineering CE1.7, CE1.8, CE1.9,
management, surveying, concrete design, CE1.12, CE1.14, CE1.15,
geotechnical engineering and structural CE1.16, CE1.18, CE2.7,
PE1.3 In-depth understanding integrity evaluation which I applied for the CE2.12, CE2.13, CE2.14,
of specialist bodies of successful completion of my projects. CE2.15, CE2.16, CE2.19,
knowledge within the CE2.24, CE2.25, CE2.27,
engineering discipline I am conversant in Project Quality CE2.30, CE2.32, CE2.33,
Management and its implementation in CE3.11, CE3.14, CE3.15,
Mega-Projects. CE3.17, CE3.23, CE3.24,
CE3.25, CE3.26, CE3.27

I regularly read technical books that CE1.7, CE1.16, CE1.17,


contain mathematical solutions and CE2.10, CE2.12, CE2.14,
PE1.4 Discernment of formulas, product specifications, CE2.16, CE2.22, CE2.24,
knowledge development and engineering standards, engineering CE2.25, CE2.26, CE2.28,
research directions within the journals, and I used the internet on a daily CE2.30, CE2.32, CE2.33,
engineering discipline basis to get updated about pioneering CE2.37, CE2.38, CE2.39,
solutions to problems similar to those I CE3.3, CE3.17, CE3.23,
was facing during my projects. CE3.27, CE3.30

I understand the interactions between CE1.8, CE1.9, CE1.10,


engineering systems and the different CE1.13, CE1.14, CE1.15,
PE1.5 Knowledge of stakeholders of every project. CE1.16, CE1.17, CE2.14,
contextual factors impacting CE2.18, CE2.25, CE2.30,
the engineering discipline CE2.31, CE2.32, CE3.15,
CE3.16, CE3.17, CE3.26,
CE3.27

I always utilized systematic principles, CE1.7, CE1.8, CE1.9,


PE1.6 Understanding of the methodologies and scientific approach to CE1.13, CE1.14, CE1.15,
scope, principles, norms, undertake and complete tasks for my CE1.18, CE2.12, CE2.27,
accountabilities and bounds of projects. CE2.28, CE2.30, CE2.32,
contemporary engineering CE2.33, CE2.38, CE2.39,
practice in the specific I ensure that systems and processes CE3.3, CE3.11, CE3.16,
discipline adhere to the limitations set by governing CE3.22, CE3.23, CE3.25
standards of every project.

PE2 ENGINEERING APPLICATION ABILITY

I address engineering problems from CE1.7, CE1.8, CE1.13,


simple to complex processes using sound CE1.14, CE1.15, CE1.16,
and fundamental engineering principles. CE1.17, CE1.18, CE1.19,
PE2.1 Application of CE2.9, CE2.14, CE2.16,
CE2.24, CE2.25, CE2.27,
established engineering
CE2.30, CE2.32, CE2.33,
methods to complex CE3.14, CE3.15, CE3.17,
engineering problem solving CE3.23, CE3.24, CE3.26,
CE3.27
I am able to conduct problem detection in CE1.7, CE1.8, CE1.9,
engineering designs, processes and CE1.10, CE1.11, CE1.12,
systems by conducting research and CE1.14, CE1.16, CE1.17,
PE2.2 Fluent application of experiments, analyze and interpret CE1.18, CE1.19, CE2.14,
gathered data to formulate conclusive CE2.16, CE2.19, CE2.20,
engineering techniques, tools
solutions and preventive actions. CE2.24, CE2.25, CE2.27,
and resources CE2.28, CE2.32, CE2.33,
CE3.14, CE3.15, CE3.17,
CE3.23, CE3.24, CE3.26,
CE3.27

I always adhere and conforms project CE1.8, CE1.15, CE1.16,


requirements, governing standards, CE1.17, CE1.19, CE2.14,
PE2.3 Application of stakeholders needs and applicable CE2.18, CE2.24, CE2.25,
regulations for each project. CE2.26, CE2.27, CE2.28,
systematic engineering
CE2.30, CE2.32, CE2.33,
synthesis and design CE2.34, CE2.38, CE2.39,
processes CE3.14, CE3.17, CE3.23,
CE3.26, CE3.27, CE3.28,
CE3.31

I always include into consideration CE1.6, CE1.7, CE1.8,


financial management in my project CE1.9, CE1.13, CE1.14,
objectives. CE1.15, CE1.19, CE2.10,
PE2.4 Application of CE2.12, CE2.14, CE2.16,
systematic approaches to the I always ensure application of proficient CE2.25, CE2.26, CE2.27,
conduct and management of systems engineering, project CE2.28, CE2.30, CE2.31,
engineering projects management and processes during CE2.32, CE2.33, CE2.39,
planning and execution of the project to CE3.13, CE3.14, CE3.17,
ensure project are completed as per CE3.23, CE3.26, CE3.27,
requirements. CE3.28

PE3 PROFESSIONAL AND PERSONAL ATTRIBUTES

I always uphold engineering standards, CE1.7, CE1.13, CE1.14,


established operating procedures, CE1.15, CE1.16, CE1.17,
policies and codes of professional ethics CE2.12, CE2.18, CE2.22,
PE3.1 Ethical conduct and
relevant to engineering discipline and my CE2.23, CE2.30, CE2.32,
professional accountability field of practice. CE2.37, CE3.3, CE3.12,
CE3.13, CE3.15, CE3.21,
CE3.22, CE3.28, CE3.30
I have written and prepared engineering
documents, technical reports, work
procedures, technical processes and
documented communications. CE1.6, CE1.7, CE1.16,
PE3.2 Effective oral and CE1.17, CE1.19, CE2.8,
written communication in I liaise with Client’s, designers, vendors, CE2.9, CE2.12, CE2.14,
professional and lay domains my supervisors, other engineering CE2.36, CE2.37, CE3.13,
department, team members of different CE3.14, CE3.21, CE3.23,
nationalities to address and resolve CE3.24, C3.25, CE3.28
issues that arise before and during the
project execution.

I have used innovative approach to CE1.13, CE1.14, CE1.15,


complete projects and explored CE1.16, CE1.17, CE1.18,
alternative concepts, solutions and CE1.19, CE2.14, CE2.16,
procedures, challenged and revised CE2.25, CE2.26, CE2.27,
engineering practices and explored CE2.28, CE2.29, CE2.32,
PE3.3 Creative innovative and
principles and ideas beyond engineering CE2.33, CE2.34, CE3.23,
proactive demeanor procedures to tackle issues and CE3.24, CE3.26, CE3.27,
problems. CE3.28

I anticipated problems and tackle issues


promptly to avoid delays.

I am proficient in gathering information CE1.6, CE1.7, CE1.8,


and data and cross referencing to several CE1.16, CE1.17, CE1.18,
engineering standards, guidelines, CE1.21, CE1.23, CE2.8,
specifications and textbooks to verify my CE2.12, CE2.13, CE2.14,
analysis. CE2.27, CE2.31, CE2.37,
CE3.13, CE3.14, CE3.15,
I prepared various engineering reports CE3.17, CE3.21, CE3.22,
and presented it to my immediate CE3.23, CE3.24, CE3.25,
supervisor for their feedback and CE3.26, CE3.27, CE3.28,
information. CE3.30, C3.31

I have documented the task that I have


completed as well as the issues that I
PE3.4 Professional use and
have encountered for future reference.
management of information
I am conversant on Quality Management
System and part of this is the total control
of documents.
I always sought advice from my CE1.6, CE1.15, CE1.16,
supervisors and colleagues who have CE1.17, CE1.19, CE1.23,
extensive years of experience. CE2.8, CE2.9, CE2.12,
CE2.14, CE2.24, CE2.27,
PE3.5 Orderly management I keep myself up-to-date by continuously CE2.31, CE2.32, CE2.33,
reading technical manuals, engineering CE2.34, CE2.36, CE2.38,
of self, and professional standards and procedures and published CE3.3, CE3.12, CE3.14,
conduct materials. CE3.15, CE3.23, CE3.27,
CE3.28, CE3.31
I always comported myself in a
professional manner when dealing with
the stakeholders of the project.

I have successfully carried out duties and CE1.3, CE1.6, CE1.7,


completed several task given without CE1.8, CE1.13, CE1.14,
supervision. CE1.15, CE1.16, CE1.17,
CE1.19, CE1.20, CE2.3,
I always communicate with other team CE2.8, CE2.10, CE2.11,
members, superiors, clients, designers, CE2.12, CE2.31, CE2.32,
contractors and suppliers to complete the CE2.33, CE2.36, CE3.11,
PE3.6 Effective team project undertaken. CE3.13, CE3.14, CE3.15,
membership and team CE3.16, CE3.21, CE3.22,
leadership I trained and guided our project team CE3.26, CE3.27, CE3.28,
members on proper execution and CE3.31
observation of processes and
procedures.

I guided project team members for the


Testing and Commissioning and
Handover process of the project.