Mitp For Surveying Setting Out Approved
Mitp For Surveying Setting Out Approved
Mitp For Surveying Setting Out Approved
STD-00-000000-QA-5733-00049-0000
(PCAP Control ID # NA)
(Criticality Rating CR # 4)
00 Revision History
01 Holds List
NIL
Revisio
Reference Description Revision Date
n
SP-1279
Specification for Civil Construction Works 4 May 2021
CONDITIONS
1 General
Contract Scope of work Drawings stamped and/or signed All Drawings. Discipline
1.1 Approval of Drawings SP-1279 approved for construction (Contractor Engineer Approved Drawings H H R
Applicable Specs Scope)
SP-1279 Site Engineer/
1.2 Weather conditions Applicable Specs No high winds and heat hazards Each setting Supervisor / QC Report H M M
Inspector
Site Engineer/
Valid Calibration
1.3 Calibration of Instruments - Valid Calibration Certificates All Instruments Supervisor / QC H M M
Certificate
Inspector
Mark the benchmarks / Reference point Site Engineer/
Survey of Levels, Datum & SP-1279 as drawing / scope of work. -In case of Supervisor / QC To be added by
1.4 H W W
Setting Out disruption, go through earlier survey Every Survey Inspector Contractor
report before starting the work
Spot Level Survey & Associated Activities
2
Site Engineer/
To be added by
2.1 Spot level Survey [if SP-1279 As per Drawings/ Client Approval Every Survey Supervisor / QC H W W
Contractor
required] Inspector
All readings and entries Site Engineer/
are completed in the level Drawings and duly completed Records All level Survey Supervisor / QC To be added by
2.2 H W M
survey and same to be SP-1279 available Inspector Contractor
reflected in report
Cut-off shrubs, trees, bush, roots etc. Site Engineer/
Site Clearing SP-1279 (except trees and bushes required for All site Cleaning Supervisor / QC To be added by
2.3 H W M
replanting or to remain in place) as Inspector Contractor
required for the Construction.
Replanting & Protection of SP-1279 Excavate & replant on work site or Site Engineer/
To be added by
2.4 Plants (If applicable) elsewhere as directed by PDO All Supervisor / QC H W M
Contractor
Inspector
Stockpile the topsoil (removed from Site Engineer/
To be added by
2.5 Top-Soil removal SP-1279 excavated area) in protected area for its ALL Supervisor / QC H W M
Contractor
reuse Inspector
Site Engineer/
Dimensions of marked Approved or Standard As per Drawings All Dimensions Supervisor / QC
2.6 Dimensions Report H W M
layout Drawings Inspector