Power Sector2
Power Sector2
PDB
VISION
To deliver uninterrupted quality power.
MISSION
To secure continuous growth of electricity for sustainable development and ensure customer
satisfaction.
The king of Bhawal of Gazipur of the then East Bengal (presently Bangladesh) under
British India is known as the first user of electricity in East Bengal.
The king of Bhawal of Gazipur illuminated his palace with the electricity using a
generator imported from England in the nineteenth century.
In 1901 a generator was installed at the residence of Mr. Ahsanullah, the Nawab of
Dhaka.
In 7th December, 1901 Mr. Bolton, a British citizen inaugurated electrification of
Ahsan Manzil by pressing an electric switch.
A company named Octavious Still, gradually brought a few elite buildings including
the Ahsan Manzil and some important roads of Dhaka under electrification by the
financial help of Nawab Ahsanullah.
In 1919, ‘DEVCO’ a British company introduced the commercial power distribution
system within a limited area of Dhaka.
1933, DEVCO company built “Dhanmondi Power House” with the generation
capacity of about 06 MW at Paribag in Dhaka and started to distribute power
commercially.
In 1947 the power supply to the then 17 provincial districts was within the township
in a limited range.
In 1947 the generation voltage was 400 volts.
In 1947 Dhaka City where power used to be supplied by two 1500 kW generators and
the generation voltage was 6600 volts and highest supply voltage.
In 1947 power used to be generated by some industries (tea, sugar and textiles) and
railway workshops.
In 1947 the total generation capacity of the country was only 21 MW and there
was no transmission system.
In 1947 power used to be generated by Dhakeswari Cotton Mills, Pahartali Railway
workshop, Saidpur Railway workshop and Sugar Mills.
In 1948, Electricity Directorate was created in order to plan and improve power
supply situation.
In 1957, the government acquired all private power houses and transmission
lines.
In 1959, Water and Power Development Authority (WAPDA) was created.
In 1960, Electricity Directorate was merged with WAPDA.
In 1960, several power plants were built at Siddhirganj, Chittagong and Khulna.
In 1960, Siddhirganj 10 MW steam turbine power plant was the highest capacity
power plant.
In 1960, Siddhirganj Three steam turbine units each of 10 MW capacity power
plant played an important role to fulfill the demand of electricity of Dhaka.
In 1960, Kaptai dam was under construction under Irrigation department.
In 1962, Karnaphuli hydro power plant started generation of electricity from its
two units of 40 MW capacity.
300-square miles lake artificially created by building a dam in Karnafuli river.
In 1962, Kaptai was considered to be the largest power plant of the country.
Side by side construction of 273 kilometer long Kaptai-Siddhirganj 132 KV
transmission line was completed and the both power stations (Siddhirganj and
Kaptai) were brought under same grid.
In 1962, Kaptai dam and commissioning of Kaptai-Siddhirganj (Dhaka-Chittagong)
132 KV transmission line are considered as milestones of power development of
this country.
BPDB was established on May 31, 1972 by the Presidential Order No. 59.
BPDB started operation with only 500 MW installed capacity.
BPDB was formed as an integrated utility with responsibility of power generation,
transmission and distribution.
BPDB’s transmission and some part of generation and distribution was handed
over to some other organizations such as
Rural Electrification Board (REB)
Dhaka Power Distribution Company (DPDC) Ltd.
Dhaka Electric Supply Company (DESCO) Ltd.
Power Grid Company of Bangladesh (PGCB) Ltd.
Ashuganj Power Station Company Ltd. (APSCL)
Electricity Generation Company of Bangladesh (EGCB) Ltd.
West Zone Power Distribution Company (WZPDC) Ltd.
North West Power Generation Company (NWPGC) Ltd.
Northern Electricity Supply Company (NESCO) Ltd.
Excepting REB, DPDC and DESCO, other companies are operating as enterprises
of BPDB.
BPDB is engaged in purchasing power as a single buyer.
As on september-2019, total installed capacity including Captive Power &
Renewable is (19,195+2,800+334) =22,329 MW.
Out of Grid Capacity 18,969MW, (Public Sector 9,507 MW, Private Sector 8,528
MW & Power Import 1,160 MW) of Power Plants located at different parts of the
country.
The main fuel used for power generation is indigenous gas.
In Fy-2017-2018 Total 62,678 GWh electricity was generated (Public sector power
plant 31,083 GWh, Private Sector Power Plants 26,812 GWh and Power import
4,783 GWh) .
The maximum demand served during peak hours is 12,893 MW in 29 May, 2019.
The transmission network is about 11,500 ckt km long comprising 400, 230, 132
and 66 KV lines.
The total grid sub-stations capacity is about 37,000 MVA as on November-2018.
Government has already launched "500 MW Solar Power Mission"
Bangladesh Power Development Board formed the Directorate of Renewable
Energy and Research & Development in 2010.
Installed Capacity of BPDB Power Plants as on November 2021
Fuel Type Capacity(Unit) Total(%)
Coal 1768.00 MW 8.03 %
Gas 11450.00 MW 51.97 %
HFO 5953.00 MW 27.02 %
HSD 1341.00 MW 6.09 %
Hydro 230.00 MW 1.04 %
Imported 1160.00 MW 5.27 %
Solar 129.00 MW 0.59 %
Total 22031 MW 100 %
DPDC
DPDC had been incorporated on 25th October, 2005 under the Companies Act 1994.
DPDC authorized share capital of Tk. 10,000 crore.
DPDC started its function from 14th May 2007
DPDC started its commercial operation on 1st July of 2008 by taking over all assets
and liabilities from the then DESA.
While the company started its operation the number of customers were 6,55,908.
Now dpdc has around 15,03,181 customers.
CORPORATE MOTTO: Dependable Power - Delighted Customer.
Human Resources (existing) – 5400
Total area covered - 250 sq. km.
Total transmission and distribution line - 5741.16 km.
132 KV Transmission Line - 234.36 km
33 KV Transmission Line - 460.82 km
0.4 KV 11 KV 11/0.4 KV Line - 5045.98 km
Total number of substation - 73 Nos
Total 11/0.4 KV Distribution Transformer - 20270 Nos.
Max. Demand (July, 2019) - 1633.20 MW
System Loss - 6.69% (FY 2020-21)
Approved Demand: Single Phase 0-7.5 KW and Three Phase 0-80 KW
LT- a: Residential:
Life Line: 00-50 Units - 3.75
First Step: From 00 to 75 units – 4.19
Second Step: From 76 to 200 units – 5.72
Third Step: From 201 to 300 units – 6.0
LT- b: Agricultural pumping: 4.16
Chairman of the Board of Directors, DPDC - Md. Habibur Rahman
DESCO
BREB
Total PBSs – 80 Nos.
Approved Projects – 81 Nos.
District included in RE program – 61 Nos.
Upazillas included in RE program - 462 Nos. (461 On-grid & 01 Off-grid)
100% Electrified Upazillas - 288 Nos. (Opening Completed), 173 Nos. (Waiting to
inaugurate)
Villages included in RE program - 84,800 Nos.
Villages Electrified - 84,544 Nos.
Line constructed - 5,63,721 Km
Line energized - 5,30,228 Km
Number of 33/11KV Sub-station & Capacity - 1136 Nos. & 14,795 MVA
System loss (80 PBSs) - 9.67% (12 Month Avg), 9.58% (This Month)
Peak demand – 7100 MW
LT-A (Domestic) consumer – 2,86,53,254
LT-B (Irrigation) consumer – 2,81,352
Mission Statement: Provide quality electricity at grass root level in a
democratic manner.
Vision Statement: Electricity for all by 2021.
Chairman - Major General Moin Uddin (Ret.)
Each Director is elected for a term of five (5) years
য আটিার কগলরিা” বলা হয় এটদ্র
“দ্ুটর্াটগ
BIFPCL
50:50 JV between NTPC & BPDB
PGCB
Year of Incorporation - 1996 [C-31820(941)/96]
Status - Public Limited Company (Listed)
Business - Transmission of Power
Authorized Capital - Tk. 10,000 Crore
Paid-up Capital as on 30.06.2020 - Tk. 712.73 Crore
Manpower as on 30 June, 2020 - 2748 persons
Transmission Line as on: September, 2021
400kv – 950 circuit km
230kv – 3770 circuit km
132kv – 8109 circuit km, 146.8 circuit km(others)
Substation as on: September, 2021
400kv - 1 Nos. 2x500MW HVDC Back to Back station
No of upcoming projects – 8
No of ongoing project – 22
No of complete project - 38
APSCL
As on October 2019, APSCL having installed capacity of about 17% of total electricity
generation capacity in the public sector.
At present, the total capacity of its eight (8) units is 1690 MW.
APSCL has been incorporated on June 28, 2000 as a private limited company
On March 01, 2003 the company converted into public limited company.
Installed Capacity – 1690 MW
Present net capacity – 1568
APSCL plays a significant role in the national economic development by generating
about 8.76% of the total electricity generation of the country.
Natural gas from Bakhrabad Gas Distribution Company Limited is used as the primary
fuel for electricity generation
Water from the river Meghan is used for steam generation and cooling of the plants
This discharging water irrigates about 36,000 acres of land of Brahmanbaria district.
APSCL and BPDB vendors’ agreement 22 may 2003.
To enhance electricity generation from existing 1690 MW to 4327 MW by 2030
To achieve auxiliary consumption at 4.5%
Registration No C-40630 (2328)/2000
Generating unit - 8 (ST-3, GT – 1, CCPP – 3, modular – 1)
Unit # 3 of 150MW capacity was commissioned in 1986
Present Capacity (net output) – 1597
Ongoing project – 2
All the activities of the company officially started from 01st June, 2003
The authorized share capital of APSCL is BDT 5,000 crore, which is divided into
500 crore shares worth BDT 10 each
Paid-up share capital of the company is BDT 1218.76 crore.
Initially, the paid-up capital of the company was BDT ten lacs only
BPDB is the owner of 99.99% of the total shares of the company
The remaining shares (0.01%) are owned by Finance Division, Planning Division,
Power Division and Energy and Mineral Resources Division
Ashuganj is located near the Titas gas field and on the banks of the Meghna River
Commercial operation of these two units began in July 1970
APSCL undertook the project to construct the 'Kalapara 1320 MW Coal Based
Power Plant' at Kalapara in Patuakhali District
EGCB
On 23rd November 1996 BPDB formed Meghnaghat Power Company (MPC) Ltd
On 16th February 2004 the Meghnaghat Power Company (MPC) Ltd. has been re-
named as Electricity Generation Company of Bangladesh (EGCB) Ltd. (an Enterprise
of BPDB)
The company's major share is currently held by BPDB.
Existing project – 1
Power plant – 3 (Siddhirganj 2*120 MW, Haripur 412 MW CCPP, Siddhirganj 335
MW CCPP)
BERC
The Bangladesh Energy Regulatory Commission was established on March 13, 2003
The commission became effective on April 27, 2004
The 1st Chairman was appointed on june 4, 2005
Power Cell
No of power plant - 146
Power generation capacity – 25235MW
Maximum power generation – 13792MW
Transmission line – 12982 circuit km
Grid substation capacity – 52739 MVA
Import energy – 1160 MW
Distribution line – 616000 circuit km
People with access to electricity – 99.75%
Per capita power generation – 560 kwh
Power consumers – 41400000
Whole system loss – 8.49%
Annual development program allocation – 21083 cores
Irrigation connection number – 212000
Total Renewable Energy – 730.49MW
Solar – 496.6MW
Wind – 2.90MW
Hydro – 230MW
Biogas - .63MW
Biomass - .40MW
Power generation plan of 2021- 2610MW (Public 1785MW+Private 825MW)
Power generation plan of 2022 – 5451MW(Public 324+JV 1240+Private 2391+Import
1496MW)
Power generation plan of 2023 – 5466MW(Public 1950+JV 2491+Private 1025)
Power generation plan of 2024 – 5500MW(Public 3260+JV 1200+Private 1040)
Power generation plan of 2025 – 775MW (Public 775)
Moittri Super Thermal Power Project – 1320MW - Bangladesh -India JV - June,2019
Matarbari Coal Based Power Pant – 1200MW – CPGCBL - June, 2022
Paira Coal Based Power Plant – 1320 MW - NWPGCL-China JV- June, 2022
G to G Coal Based Power Plant – 1320MW - Bangladesh –S. Korea JVS - June, 2023
Moheshkhali Coal Based Power Plant – 1200MW – BPDB - June,2021
Moheshkhali Coal Based Power Plant – 1320MW - Bangladesh -Malaysia JV- June,
2022
Ashuganj 2x660 MW Power Plant – 1320MW – APSCL
1320 MW Coal Based Power Plant – 1320MW - BPDB –CHDHK, China JV - June,
2021
ববদ্ুুৎ কেন্দ্র প্রেল্প সংখ্ুো 151 (118 complete)
Public – 52 (42 complete)
JV – 4 (1 complete)
Rental – 20 (20 complete)
IPP – 75 (55 complete)
Under Construction Power Plant - 24
Public sector – power plant 9 + Renewable Energy 1
JV - power plant – 3
Private - power plant 12 + Renewable Energy 8
SREDA
SREDA- Sustainable and Renewable Energy Development Authority
SREDA has started its journey - 22nd May 2014
To reduce global warming, environmental hazard risk, to ensure energy security by
reducing dependency on fossil fuel through the use and expansion of Renewable
Energy.
Chairman of SREDA – Mohammad Alauddin
WZPDCL
Public Limited Company.
NESCO
Total no. of Consumers (Till December-2020) Rajshahi – 917019
Total no. of customer (Till December-2020) Rangpur – 713224
Total no. of customer – 1630243
Vision: Our vision is to ensure power for all by 2021. We look forward to ensure our
company to be sustainable in its operation through modernized, ICT backed and
dependable infrastructure
Mission: Our mission is to ensure reliable and affordable power. We focus to extend
quality and satisfactory service to our valued consumers.
Authorized Capital: BDT 250 crore divided into 2.5 crore equity shares of BDT 100
each.
Paid Up Capital: 999,900 taka divided into 9999 Nos equity shares of BDT 100 each.
Total number of share holding – 9999
Bangladesh Power Development Board (BPDB) – 9991
No of organizations for share holding – 9
System loss – 10.34
Running projects – 3
Supply Division – 2 (Rajshahi, Rongpur)
CPGCBL
CPGCBL - an enterprise of the Government of the People's Republic of Bangladesh,
public limited company
Register - 5th September 2011.
Fuel – coal
Status - 2x600 MW Ultra Super Critical Coal Fired Power Plant
BEPRC
BEPRC - Bangladesh Energy & Power Research Council
RPCL
RPCL registered as public limited company on 31 December 1994
RPCL was promoted by REB and 5 PBSs
Generating capacity 542MW
Present shareholder are BREB & 13 PBSs
BR Powergen
B-R Powergen was established as a public limited company on 2010
BPDB & RPCL have equal shares
BERC
BERC – Bangladesh Energy Regulatory Commission
BERC was established on March 13, 2003
BERC became effective on April 27, 2004
BPMI
BPMI – Bangladesh Power Management Institute
BPMI) was formed in 2017