02-Chapter 2 Network Element Commissioning
02-Chapter 2 Network Element Commissioning
02-Chapter 2 Network Element Commissioning
Contents
Figures
Tables
This chapter describes the network element (NE) commissioning for the OptiX
OSN 9500 after hardware installation. NE commissioning includes cabling test, NE
performance monitoring, and service indexes test. The NE commissioning method
is introduced through an example with the configuration shown in Figure 2-1.
The NE is configured as an ADM. The JL64 boards in slots IU 7 and IU 8 are
connected with upstream and downstream NEs respectively. The cross-connect
board, the clock board, the SCC board, and the power interface board are equipped
with active/standby protection. The JLH1 in slot IU 1 accesses 16 x STM-1 optical
signals and the JLHE in slot IU 18 accesses 16 x STM-1 electrical signals.
E
I I I I I I I I I I I I I I I I P E S S I I X X I I S P
M
Slot U U U U U U U U U U U U U U U U B O C C U U C C U U T I
P
0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 U W C C 3 3 H H 3 3 I U
U
1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 3 4 5 6
Board
J J J J J J J G G J J
name E
L L L P E S S X X S P
M
H 6 6 B O C C C C T I
P
1 4 4 U W C C H H I U
U
01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 55 51 47 48 33 34 41 42 35 36 58 52 56
I I I I I I I I I I I I I I I I D S S C I I X X I I S S P
U U U U U U U U U U U U U U U U C I I O U U C C U U T T I
1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 U G G M 3 3 H H 3 4 G G U
7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 7 8 9 0
J J G G J J J
L C X X S S P
H O C C T T I
E M H H G G U
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 53 49 50 54 37 38 43 44 39 40 45 46 57
Front Rear
Check hardware before the cabinet is powered on. This section gives the criteria for
several important testing items. For details, see OptiX OSN 9500 Intelligent Optical
Switching System Installation Guide.
Step Action
1 Check whether the cabinet is connected to the power supply equipment. If so, push the switch on the
power supply equipment to OFF.
2 On the power distribution unit, push power switches for the subrack to OFF .
3 Measure the resistance between NEG1 (–) of INPUT1 and RTN1 (+) of INPUT1. The value should
be ∞.
4 Measure the resistance between NEG1 (–) of INPUT1 and RTN2 (+) of INPUT1. The value should
be ∞.
5 Measure the resistance between NEG1 (–) of INPUT1 and the protection grounding post ( ). The
value should be ∞.
6 Measure the resistance between NEG2 (–) of INPUT1 and RTN2 (+) of INPUT1. The value should
be ∞.
7 Measure the resistance between NEG2 (–) of INPUT1 and RTN1 (+) of INPUT1. The value should
be ∞.
8 Measure the resistance between NEG2 (–) of INPUT1 and the protection grounding post ( ). The
value should be ∞.
9 Measure the resistance of INPUT2 refer to step 3–step 8.
10 On the power distribution unit, push power switches for the subrack to ON.
11 Measure the resistance between NEG1 (–) of INPUT1 and RTN1 (+) of INPUT1. The value should
be more than 20 kilohms.
12 Measure the resistance between NEG1 (–) of INPUT1 and RTN2 (+) of INPUT1. The value should
be more than 20 kilohms.
13 Measure the resistance between NEG1 (–) of INPUT1 and the protection grounding post ( ). The
value should be more than 20 kilohms.
14 Measure the resistance between NEG2 (–) of INPUT1 and RTN2 (+) of INPUT1. The value should
be more than 20 kilohms.
15 Measure the resistance between NEG2 (–) of INPUT1 and RTN1 (+) of INPUT1. The value should
be more than 20 kilohms.
16 Measure the resistance between NEG2 (–) of INPUT1 and the protection grounding post ( ). The
value should be more than 20 kilohms.
17 Measure the resistance of INPUT2 refer to step 11–step 16.
18 After the test, turn off power switches for the subrack on the power distribution unit.
Caution
The testing method must be correct. The positive pole of the ohmmeter should be
connected to RTN(+) , while the negative pole to NEG (–). If poles of the ohmmeter
are connected reversely, the obtained value will be smaller than the actual value,
usually less than 10 kilohms.
When the power switch on the subrack is pushed to ON position, if the resistance
between cabling posts is less than 20 ohms, it indicates that a short circuit occurs
between the –48 V working power and the working ground. Resolve the fault before
proceeding to the power-on test.
Boards are inserted completely and board front panels are locked.
In case of any exception, contact local offices of Huawei Technologies Co., Ltd
(hereinafter referred to as Huawei) as soon as possible.
Caution
Always wear an ESD wrist strap or ESD glove whenever you touch a board.
Note
Usually, the J12 jumper cap of the EMPU has been removed before shipped. But you
must check to ensure that.
Warning
Ensure that all power switches are in the OFF position after the hardware check.
Caution
Touching the power supply equipment directly or indirectly through damp objects may
result in fatalities.
Step Action
1 Measure the voltage of the power supply equipment at the top of the cabinet.
The value should range between –48 V +/- 20% (or between –60 V +/- 20% if
the standard input voltage is –60 V). Ensure that the positive and negative poles
are connected correctly.
caution:
If the output voltage of the power supply equipment is not within this working
range, solve this problem and do not power on the equipment.
2 Check the status of subrack power switches and the corresponding switches on
the power supply equipment. All the switches should be in the OFF position.
Step Action
3 Check the labels of the power cables. If the labels are not filled or affixed
properly, fill and affix new labels instead.
4 Connect one end of the power cables, power grounding cables, and protection
grounding cables to the power distribution unit on the top of the cabinet.
5 Connect the other end of the power cables, power grounding cables and
protection grounding cables to the power supply equipment.
6 Turn on corresponding power switches on the power supply equipment.
Note
The indicators at the top of the OptiX OSN 9500 cabinet are driven by the EMPU
board. Therefore, the indicators are on only after the subrack is powered on.
Step Action
1 Check whether the subrack power cables are correctly connected to DB3 of
JPIU boards. Make sure all connectors on the JPIU board are fixed.
2 Turn on the switches for each subrack on the DC power distribution unit in
order.
3 After the test, push the power switches of the upper and lower subracks to the
ON position. All subracks can be powered on normally.
Caution
Do not insert or remove power plugs or JPIU boards with power on.
Step Action
1 Check the running indicator on the front panel of the fan. The indicator is green
normally. If it is red or yellow, then the fan is faulty. Resolve the fault
immediately.
2 You can feel wind blowing when you put your hand on the top or at the bottom
of the subrack. Do not touch the fan.
Note
The fan tray assembly of the OptiX OSN 9500 is hot-swappable (avoid as much as
possible). The fan tray assembly has indicators but no switch.
There is an air filter at the bottom of the subrack. Clean the air filter once every two
weeks.
Step Action
1 Switch on the power switch on the subrack. After two or three minutes, the
JSCC board is in service.
2 Log in to the T2000 as administrator, create an NE, and add the board to the NE.
Note:
During NE commissioning, the NE should be set to a gateway NE because it is
connected directly to the T2000.
Step Action
4 Observe the running indicator (green). It is one second on and one second off.
5 Observe the alarm indicator (red). It is off without any alarm. When there is an
alarm, it flashes once to three times every other second.
Step Action
1 Connect the ETH interface to the computer where T2000 runs, and observe the
interface indicator. The indicator shows the connection is normal.
2 Press the RESET button on the JSCC board. The board is reset after several
minutes.
3 Select the NE from the Main Topology on the T2000 and right-click it. Select
Login from the shortcut menu. If the NE can be logged in to, the JSCC reset
button is normal.
4 Double-click the NE icon to log in to the NE. Normally, the NE is in the running
state.
5 If you fail to log in to the NE or the T2000 reports alarms, resolve the fault
before proceeding to the next test.
Note
The ETH interface on the JSCC has two indicators. The green indicator indicates the
NE is connected to the T2000 and the flashing yellow indicator indicates that data is
transmitted between the NE and the T2000.
Step Operation
1 Press the LAMP TEST button on the front panel of the board. The green
running indicator and red alarm indicator on the front panel of all the boards
inserted in the subrack will be on.
2 Remove the fibre jumper connected to any optical interface board. The NE will
report the R_LOS alarm (critical), and the buzzer will beep. At this time, press
the MUTE button. The buzzer stops beeping.
Step Operation
1 Check the orderwire phone. The phone plug should be inserted in the PHONE
port on the JEOW board. The dialling mode of the orderwire phone should be
set to T (dual-tone multi-frequency)
2 Remove the orderwire phone, and press the talk button. The indicator on the
phone should be on with dialling tone. In this case, the orderwire phone is in
off-hook status. Press the talk button again. Then the indicator is off (on hook).
3 If there is no dialling tone, maybe the orderwire phone is not configured.
Configure the orderwire phone through the T2000 and then perform the
orderwire test.
Note
The ringing switch of the orderwire phone should be set to ON, so the phone will ring
when there is an orderwire call.
Step Action
1 Check the label on the alarm cable to ensure the cable correctly connects to the
centralised alarm processing device.
2 Remove the fibre jumper connected to the IN optical interface of the NE (or shut
down the laser of the corresponding optical interface through the T2000), so as
to enable the NE to report R_LOS alarm. Then, the buzzer will beep, and the
centralised alarm processing device will give audio and visual alarm
notification.
3 Connect the fibre jumper which is removed in step 2(or turn on the laser which
is shut down in step 2).
Note
When the centralised alarm processing device is in the audio alarm mode, the mute
function is required.
Step Action
1 Check the label of the network cable. If the label is not filled or affixed properly,
fill and affix a new one instead.
2 Use the multimeter to test the network cables connecting the NE and the T2000.
The communication is normal.
3 Check the cable length, which should not exceed 100 m.
4 Check the network cables connecting the gateway NE and the T2000. The
network cables should connect to the ETH interface on the JSCC board.
Step Action
5 Check the network card of the computer where T2000 runs. Select the
auto-negotiation mode for the network card and set its IP address and NE IP to
the same segment.
6 Observe the indicators of the ETH interface.
The green LINK indicator indicates the connection status. When on, it indicates
successful connection; otherwise, it is off. The orange ACT indicator indicates
data receiving and transmitting. It flashes to indicate data receiving or
transmitting; otherwise, it is off.
Step Action
This section describes the guideline for configuring commissioning data through
the example described in section 2.1. For details, see OptiX OSN 9500 Intelligent
Optical Switching System Configuration Guide.
In the following commissioning process, we assume that the computer where
T2000 runs is connected to the NE and the communication is normal.
TX RX TX 1 RX TX 2 RX TX 1 RX TX 2 RX
Fibre
Fibre Fibre Fibre Fibre
optical jumpers
jumpers jumpers jumpers jumpers
attenuator
optical optical optical optical
attenuator attenuator attenuator attenuator
Self-looping for TM Self-looping for Cross-looping for
ADM ADM
Figure 2-2 Looping back the optical interface board
Step Action
1 Log in to the T2000 as administrator, create an NE, and upload the NE data.
2 Connect an SDH analyser to the first receiving and transmitting electrical
interface on the JLHE board in slot 18.
3 Configure the first VC-4 of the JLHE board to the second VC-4 on this board
through the T2000.
4 According to Table 2-2, complete the service configuration for others VC-4s.
5 Self-loop the electrical interfaces and optical interfaces of all SDH service
boards except the first electrical interface of the JLHE board.
Note:
Add an appropriate optical attenuator before looping back the optical interfaces.
6 Perform BER test for ten minutes. Observe the SDH analyser. No bit error is
reported.
7 Query NE alarms and performance events on the T2000. If the NE reports
alarms or performance events, locate the fault and resolve it before proceeding
to the next test.
8 After the test, cancel the self-loop of the electrical interfaces and the optical
interfaces.
7-JL64-1-1 to 63 7-JL64-1-2 to 64
7-JL64-1-64 8-JL64-1-1
8-JL64-1-1 to 63 8-JL64-1-2 to 64
8-JL64-1-64 1-JLH1-1-1
1-JLH1-1 to 15-1 1-JLH1-2 to 16-1
This section lists the common test items of the NE commissioning, and gives
operation procedures and precautions for mandatory items. If test tools are
available, it is recommended to test the optional items in addition. For details, see
Appendix A "Test of Common Indexes".
Step Action
1 Clean fibre jumper connectors and flange carefully with special cleaning tissue.
2 Set the optical power meter to the desired wavelength.
3 Connect the fibre jumper on the OUT optical interface to the input port of the
optical power meter, as shown in Figure 2-3.
4 Read the mean launched optical power after the output power keeps stable.
5 Compare the test result with the index. If the result does not conform to the
index, find out the causes until passing the test.
Note:
The optical interface board may be set with the automatic laser shutdown (ALS)
function, which makes the optical interface unable to emit light. If no optical
power is received, check whether the ALS function is enabled.
Optical
interface Tested
Fiber board optical
jumper interface
-
OUT
IN
Optical
pow er meter
Warning
It is strictly forbidden to stare straightly at the optical interface board and optical
interface, lest the laser beam inside the optical fibre would hurt your eyes.
Caution
Make sure the flange on the optical fibre connector is clean and connected properly.
Test the attenuation of the fibre jumper in advance.
Select the fibre jumper with a connector matching the interface shape.
Step Action
5 Check the fibre line. After resolving the fault, return to step 1 to test the received
optical power again.
Note:
If the received optical power is too small, check the cable length, the optical fibre
connector, and connection of the flange at the ODF side. If the fibre connector is
dirty, clean it. For too high attenuation, rebuild the line. If the optical cable is too
long, replace the board with a new one with higher launched optical power or add
more optical signal amplifier boards.
6 Add another attenuator at the ODF side. After resolving the fault, go back to
step 1 to test the received optical power again.
7 If the test value still cannot meet the requirement, check the fibre connection
and the boards at the remote station. If there is any fault, resolve the fault. Then
test again from step 1.
Optical
interface
board Tested
Fiber
optical
jumper Fiber
interface
- jumper
ODF ODF
OUT
IN
After connecting cables with the OptiX equipment and DDF, perform electrical
interface on/off and cabling error-free tests.
Step Action
1 Set the first 155 Mbit/s port to Outloop on the T2000. Connect the BER tester to
the first 155 Mbit/s port on the DDF. The T_ALOS alarm should disappear.
2 Cancel Outloop on the T2000. In this case, the BER tester gives an alarm,
indicating the BER tester is connected to the first 155 Mbit/s port and the
receiving and transmitting cables are connected correctly.
3 Similarly, check the receiving and transmitting cables of each 155 Mbit/s port in
order. Test in both the ON and OFF states.
4 Ensure the on/off function of all electrical interfaces is normal (reliable cable
connection, no short circuit or blocking).
Step Action
5 Ensure that the port numbers at the equipment side correspond to those at the
DDF side, and the receiving or transmitting sequences of all ports on the DDF
are consistent. If any fault occurs, resolve the fault first.
6 After the test, disconnect the cables connected during the test. And make sure
the Outloop configured in step 1 has been canceled.
It is to check whether two fibre jumpers are correctly connected to the receiving and
the transmitting interfaces of one optical interface board respectively.
Follow the steps below to test the fibre jumper distribution.
Step Action
1 Connect one end of a fibre jumper to the transmitting end of an optical interface
on a board. Test the other end using an optical power meter at the ODF side and
ensure the optical power is not 0. Remove the fibre jumper and ensure the
optical power of the other end is 0. The optical power meter shows the Loss
status.
2 Connect the fibre jumpers from the ODF side to the receiving and the
transmitting ends of an optical interface on the board, and then perform
loopback at the ODF side. Then, the R_LOS alarm of this optical interface
should disappear.
3 Remove the fibre jumper from the transmitting end, the optical interface reports
an R_LOS alarm. Insert the fibre jumper again. Then, the R_LOS alarm
disappears.
4 Check the labels of the fiber jumpers. If the labels are not filled or attached
properly, make new labels and attach them to the corresponding fiber jumpers.
5 After the test, cover all optical interfaces with dustproof caps.
Step Action
1 Measure the actual receiving optical power at the ODF of this station.
2 Compare it with the launched power of the remote station, see the standard
optical cable attenuation, and judge whether the attenuation is too high.
3 If so, find the causes and make an improvement.
Note
For the method of testing optical cable attenuation, see Appendix D "Optical
Transmission Distance" of OptiX OSN 9500 Intelligent Optical Switching System
System Description.
Step Action
1 Measure the actual receiving optical power at the ODF of this station and the
optical interface board respectively.
2 Compare the two values, which should be a little different (within 1.5 dB).
3 If the attenuation is too high, find the causes and make an improvement.
Note
Common causes for high fibre jumper attenuation:
The fibre jumper interface is in bad contact with the interface on the optical
interface board.
The fibre jumpers are bound too tight. If so, it is necessary to reroute the fibre
jumpers.
The fibre jumper has a bad performance. In this case, replace the fibre jumpers.
Caution
If service interruption occurs or an alarm is reported during the test, resolve the fault
before proceeding to the next step.
The interval between the switching of two boards must be more than one minute.
Step Action
Step Action
1 Perform service configuration according to section 2.10.1 and connect the SDH
analyser.
2 Turn on the tact switch of the clock board in slot 45. Observe the SDH analyser.
The service should be normal and no alarm is reported to the T2000.
3 Turn off the tact switch of the clock board in slot 45. Observe the SDH analyser.
The service should be normal, and no alarm is reported to the T2000.
Step Action
4 Turn on the tact switch of the clock board in slot 46. Observe the SDH analyser.
The service should be normal and no alarm is reported to the T2000.
5 Turn off the tact switch of the clock board in slot 46. Observe the SDH analyser.
The service should be normal, and no alarm is reported to the T2000.
Step Action
1 Perform service configuration according to section 2.10.1 and connect the SDH
analyser.
2 Turn on the tact switch of the SCC board in slot 47. Observe the SDH analyser.
The service should be normal and no alarm is reported to the T2000.
3 Turn off the tact switch of the SCC board in slot 47. Observe the SDH analyser.
The service should be normal, and no alarm is reported to the T2000.
4 Turn on the tact switch of the SCC board in slot 48. Observe the SDH analyser.
The service should be normal and no alarm is reported to the T2000.
5 Turn off the tact switch of the SCC board in slot 48. Observe the SDH analyser.
The service should be normal, and no alarm is reported to the T2000.
Step Action
1 Perform service configuration according to section 2.5 and connect the testing
instrument.
2 Self-loop the electrical interfaces and optical interfaces of all SDH service
boards, except the first electrical interface of the JLHE board (with an
appropriate attenuator to be added).
3 Perform 24-hour performance test, and there should be no bit errors or alarms.
4 Log in to the T2000 as the system administrator.
5 Set performance monitoring on the T2000. The performance data should be
normal. For example, the bit error and point justification should be 0, and
temperature performance data should be within the normal range.
6 During performance monitoring, view NE alarms periodically and remove all
alarms caused by unknown reasons.
7 Clear the services configured during this test. Remove the fibres, cables and
instruments connected during this test.
8 Connect the cables and fibres from the DDF and the ODF to the equipment
according to the labels on the cables and fibres.
Note
For any problem during the test, solve it before continuing with the test.
Step Action
When there are multiple NEs in one station (for example, one main subrack and
several extended subracks), these NEs should be able to log in to one another.
Step Action
Step Action
Note
Conduct this test after the backing up of NE database described in section 2.12 is
complete.
Step Action
1 Power on the NE after power failure. Within 10 minutes, all boards should be
able to operate normally without manual intervention.
2 The services can be activated normally. Self-loop the optical interface board and
test typical services to ensure that no bit error or performance event occurs.