Benefit Cost Analysis
Benefit Cost Analysis
©McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom. No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
LEARNING OUTCOMES
1. Explain difference in public vs. private sector
projects
2. Calculate B/C ratio for single project
3. Select better of two alternatives using B/C
method
4. Select best of multiple alternatives using B/C
method
5. Use cost-effectiveness analysis (CEA) to
evaluate service sector projects
6. Describe how ethical compromises may enter
public sector projects
©McGraw-Hill Education.
Differences: Public vs. Private Projects
©McGraw-Hill Education.
Types of Contracts
Contractor does not share in project risk
Fixed price - lump-sum payment
Cost reimbursable - Cost plus, as negotiated
Note 1: All terms must be expressed in same units, i.e., PW, AW, or FW
Note 2: Do not use minus sign ahead of costs
©McGraw-Hill Education.
Decision Guidelines for B/C and PI
Benefit/cost analysis
If B/C ≥ 1.0, project is economically justified at
discount rate applied
If B/C < 1.0, project is not economically acceptable
B−D
Conventional B/C ratio =
C If B/C ≥ 1.0,
accept project;
B−D − M&O
Modified B/C ratio = otherwise, reject
C
Denominator is
PW of NCFt initial investment
PI =
PW of initial investment
If PI ≥ 1.0,
accept project;
otherwise, reject
©McGraw-Hill Education.
Example: B/C Analysis – Single Project
A flood control project will have a first cost of $1.4 million with an annual
maintenance cost of $40,000 and a 10 year life. Reduced flood damage is
expected to amount to $175,000 per year. Lost income to farmers is estimated
to be $25,000 per year. At an interest rate of 6% per year, should the project be
undertaken?
©McGraw-Hill Education.
Alternative Selection Using Incremental B/C
Analysis – Two or More ME Alternatives
©McGraw-Hill Education.
Example: Incremental B/C Analysis
Compare two alternatives using i = 10% and B/C ratio
Alternative X Y
First cost, $ 320,000 540,000
M&O costs, $/year 45,000 35,000
Benefits, $/year 110,000 150,000
Disbenefits, $/year 20,000 45,000
Life, years 10 20
©McGraw-Hill Education.
Example: ∆B/C Analysis; Selection Required
Must select one of two alternatives using I = 10% and ∆B/C ratio
Alternative X Y
First cost, $ 320,000 540,000
M&O costs, $/year 45,000 35,000
Benefits, $/year 110,000 150,000
Disbenefits, $/year 20,000 45,000
Life, years 10 20
©McGraw-Hill Education.
B/C Analysis of Independent Projects
Independent projects comparison does not require
incremental analysis
Compare each alternative’s overall B/C with DN option
©McGraw-Hill Education.
Cost Effectiveness Analysis
©McGraw-Hill Education.
CER Analysis for Independent Projects
Procedure is as follows:
(1) Determine equivalent total cost C, total effectiveness measure E and CER
(2) Order projects by smallest to largest CER
(3) Determine cumulative cost of projects and compare to budget limit b
(4) Fund all projects such that b is not exceeded
Cumulative
Program CER, $/graduate Program Cost, $ Cost, $
B 752 98,000 98,000
A 1203 305,000 403,000
D 1830 365,000 768,000
C 2010 126,000 894,000
©McGraw-Hill Education.
Example: CER for ME Service Projects (2)
Solution:
Order programs according to increasing effectiveness measure E
©McGraw-Hill Education.
Summary of Important Points
B/C method used in public sector project evaluation
Can use PW, AW, or FW for incremental B/C analysis, but must be
consistent with units for B,C, and D estimates
For multiple mutually exclusive alternatives, compare two at a time and
eliminate alternatives until only one remains
For independent alternatives with no budget limit, compare each against
DN and select all alternatives that have B/C ≥ 1.0
CEA analysis for service sector projects combines cost and
nonmonetary measures
Ethical dilemmas are especially prevalent in public sector projects
©McGraw-Hill Education.